comments on: approve updates from subcontractors using reflection projects in oracle primavera [video] - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/ project controls training & courses tue, 12 mar 2019 16:53:21 +0000 hourly 1 by: whale //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-75034 tue, 12 mar 2019 16:53:21 +0000 //www.deco-dalles.com/?p=1131#comment-75034 you did a great teaching overthere bro. however, preventing the overwriting sucks and tidious. am a main contractor with 5 contractor. with over 25,000 activities. will.i sitdown to uncheck all the activities of each contractor during merging? any other techniques?

also please i have a expense loaded program. i use to use earned value cost for performance measurement on other project, but this time around, the pmc what the % cost complete. please how can i make %cost complete = %activity complete. any global change techniques??

]]>
by: amelie //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-35105 thu, 19 nov 2015 12:37:50 +0000 //www.deco-dalles.com/?p=1131#comment-35105 hi michael,
i have not used the reflection much yet but i did try it on one of my programmes. i used your tutorial and it was most helpful, but instead of updating 世界杯时间比赛时间 , i updated status of activities. what i had to update was: some of the activities had been progressed and completed while on site, the reality of things is they were struggling to complete the task. so in the reflection, i changed the status of some activities from completed to not started or in progress and adjusted the actual and remaining durations.
i proceeded with the merge and it went through fine, except when i reopened my master project, it had not taken into consideration some of the durations i altered. it changed the status fine but the durations were weird. have you come across this problem before?
it was only for a few lines but this makes me worry a bit if i need to update more lines.
the next reflection i need to do is for activities that are all in the future so they’re at status “not started”. will that merge better? i wouldn’t want to use the reflection tool if i end up spending as much time fixing line as i would just changing the master programme manually…
do you have any advice? many thanks

]]>
by: michael lepage //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-25339 mon, 12 jan 2015 18:56:25 +0000 //www.deco-dalles.com/?p=1131#comment-25339 in reply to zahid khan.

hi zahid, i’d like to help, but i’m not familiar with companies that could help based in india. if you’re looking to learn primavera p6, have you checked out our online training? http://www.plannertuts.com/courses

]]>
by: zahid khan //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-25334 fri, 09 jan 2015 09:51:03 +0000 //www.deco-dalles.com/?p=1131#comment-25334 dear sir,

i need some help , i am new to primavera and needs some clarifications , i am intending to work in gcc as planning engineer. my total experience is 16 years out of which 10 yrs as qs (5yrs in gcc as qs). now i want to work as planning. i am good with practical knowledge . need some initial help in softwares. can you suggest if any gcc return planning in mumbai or anywhere in india who can help he in my queries.

thanks

zahid khan

]]>
by: michael lepage //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-24793 mon, 20 oct 2014 17:39:27 +0000 //www.deco-dalles.com/?p=1131#comment-24793 in reply to umar farooq.

no difference. p6 works the same in either case.
michael

]]>
by: umar farooq //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-24757 fri, 17 oct 2014 19:39:18 +0000 //www.deco-dalles.com/?p=1131#comment-24757 hi michael ,

great discussion with your valuable comments with deep insight. i just want to know how and what does make difference if we server or standalone p6 to update multiple constructors schedules , any special condition in case of server or no ?

regards

umar

]]>
by: peter protopapa //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-24703 thu, 09 oct 2014 13:44:07 +0000 //www.deco-dalles.com/?p=1131#comment-24703 michael,

i look through the tutorial and the web but haven’t seen an answer to this “simple” question.

can you continue to make changes to the original schedule while using reflection? my guess would be, as long as it isn’t obviously activities you are changing in reflection it would be okay.

your thoughts?

thank you.

]]>
by: ali ali //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-23667 wed, 10 sep 2014 20:54:53 +0000 //www.deco-dalles.com/?p=1131#comment-23667 hi michael,

the creation of reflections and merging it after the subcontractors have updated them is really a very efficient solution on handling a master schedule with many subcontractors. as you were saying in one of your previous comments,one way to satisfy that the subcontractors do not modify/see other activities is to:

1) allow contractor access to your database to update their section of the master schedule (reflection) directly. using p6 permissions you can limit what part of the schedule a contractor can see. the reason i suggest this as best, is that it provides you with the most control over the entire process – eliminates problems importing schedules, problems with multiple data dates, copying and pasting and other conumdrums. i know it’s not always possible – but i think there should be a trend in this direction

since,some of us may not have used the permissions part of p6 before, is it possible that you elaborate the process by either explaining it briefly here or publishing a demo in youtube?

thank you,
ali

]]>
by: qais //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-23102 wed, 03 sep 2014 08:58:47 +0000 //www.deco-dalles.com/?p=1131#comment-23102 nice effort michael,
thanks for the video very helpful.

]]>
by: mani //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12226 tue, 01 oct 2013 12:15:36 +0000 //www.deco-dalles.com/?p=1131#comment-12226 hi michael,

i want to merge subcontractor program to master schedule in p6 is possible

]]>
by: david //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12225 wed, 26 jun 2013 17:52:54 +0000 //www.deco-dalles.com/?p=1131#comment-12225 hi michael,
great and useful tutorial!
i would like to use this method in order to update subcontractors activities in my master schedule. i have two questions:

1. if subcontractor change activity relationships, these ones will be updated in my master schedule?

2. if subcontractor remove or adds an activity, these changes will be updated in my master schedule?

thanks for your work,
david.

]]>
by: michael lepage //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12224 mon, 04 mar 2013 19:54:31 +0000 //www.deco-dalles.com/?p=1131#comment-12224 hi jeevan,
i’m not sure i completely understand your issue, but in response to the question of whether a reflection can be merged into a different source project, it cannot.
if you can clarify some more on your issue, we’ll see if we can make a recommendation. usually filters and layouts only affect how the data is shown on the screen and they do not affect the data of the project itself. so i’m not sure i understand what trouble you are having with losing the wbs.
michael

]]>
by: jeevan //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12223 mon, 04 mar 2013 04:50:58 +0000 //www.deco-dalles.com/?p=1131#comment-12223 hi michael,
is it possible to merge the the subcontractor scheudle to my master schedule, which is basically the same but with change in the layout structure and many filtering and reporting format. the problem i am facing is that subcon gives me every week their update. each time i need to change the filtering, since no two project takes same id, which mean the wbs value is lost.

the refelction project can it be added to a different source project, in my case is a schedule with my layout and filtering and reporting formats..

please help me

]]>
by: alton nelson //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12222 tue, 15 jan 2013 19:11:29 +0000 //www.deco-dalles.com/?p=1131#comment-12222 your comments

thanks for the link you provided it was a great help to me.

can you plz give a brief description about the baseline feature in p6

]]>
by: michael lepage //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12221 tue, 15 jan 2013 14:09:41 +0000 //www.deco-dalles.com/?p=1131#comment-12221 @alton, did you look at our other reflection tutorial? http://www.plannertuts.com/primavera-p6-tutorials/use-reflections-primavera-p6-to-merge-scenarios-32/ is there something specific you are struggling with?

]]>
by: alton nelson //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12220 tue, 15 jan 2013 11:17:31 +0000 //www.deco-dalles.com/?p=1131#comment-12220 hi mike

your tutorial on reflections is the same here as it is on youtube.
i want to knw how to use the reflection functionality from the start.
is there any tutorial you can refer me

thanks

]]>
by: aj //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12219 wed, 19 sep 2012 15:19:39 +0000 //www.deco-dalles.com/?p=1131#comment-12219 thanks for your great response michael, and for the cpm solutions link. more stuff to teach an old dog new tricks!

i’ve used variants of 2, 3, and 4 above. admittedly i hadn’t really considered 1. but why not – i use p6 permission rights and the obs to control project and wbs access for internal employees. it would seem to make sense for contractors too, especially in this day and age with cloud computing and viable remote access. got to think through some of the logistics, but excellent food for thought.

]]>
by: michael lepage //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12218 wed, 19 sep 2012 13:26:57 +0000 //www.deco-dalles.com/?p=1131#comment-12218 in reply to aj.

hi aj,
a good question with no simple answer. if i had to rate best approaches, i would put this first
1) allow contractor access to your database to update their section of the master schedule (reflection) directly. using p6 permissions you can limit what part of the schedule a contractor can see. the reason i suggest this as best, is that it provides you with the most control over the entire process – eliminates problems importing schedules, problems with multiple data dates, copying and pasting and other conumdrums. i know it’s not always possible – but i think there should be a trend in this direction.
2) individual contract schedules (reflections) that combine into a master schedule. in p6, it’s not always necessary to build a master schedule. you can open multiple schedules at once and link them and manage them as though they are all 1 schedule. video tutorial i did on this over at cpm’s site http://www.cpmsolutions.ca/learning/flash/linking-projects-together . still some challenges with data dates and linking, mind you, but this can work.
3) individual contractor schedule that drive a summarized master. the master can be just a summary of the contractor schedules – using level of efforts and milestones, etc. some clients won’t like this, but it does work.
4) individual contractor schedules (reflections) that get cut and pasted into a master. less than ideal because cutting and pasting is soo much fun, but it gets the job done too.
so, i come back to 1) where you get the best control. 2 – 4 offer a lot of work and a lot of challenges too.
hope that helps.
michael

]]>
by: aj //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12217 tue, 18 sep 2012 18:41:37 +0000 //www.deco-dalles.com/?p=1131#comment-12217 michael:

thanks for your insight. i am curious, though, what you think is the best way to integrate multiple contractor schedules into the master when you don’t want the contractors to have the ability to view the entire schedule (which they will have with a reflection as you mentioned above).

i’ve used a couple of methods – individual contractor projects in the eps with interproject links to the master, copy and paste contractor wbs into master – and they all have their own pitfalls.

regards – aj

]]>
by: michael lepage //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12216 fri, 20 jul 2012 13:56:32 +0000 //www.deco-dalles.com/?p=1131#comment-12216 hi chandrakant,

when you open 2 projects at the same time in p6, the projects will show up in the activity list one after the other – all in the same screen. when you use the bottom layout to show the activity list again (on top and on bottom), then you can scroll to one project in the top and scroll to the other project in the bottom. that should allow you to compare both projects visually.

if you need a detailed project comparison, you could also try using claim digger (from the tools menu). claim digger will provide a very detailed report comparing 2 projects. i won’t say it’s fool-proof though. sometimes it doesn’t work well because it runs outside of p6 using a java applet. but give it try.
hope that helps. happy planning!
michael

]]>
by: chandrakant //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12215 fri, 20 jul 2012 04:30:34 +0000 //www.deco-dalles.com/?p=1131#comment-12215 hi michale,

can you help me to know how to open two project in one window to compare, as i am using bottom layout option but it is opening the same project.

]]>
by: sanjay //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12214 thu, 28 jun 2012 05:42:24 +0000 //www.deco-dalles.com/?p=1131#comment-12214 i appreciate you taking to time to contribute that’s very hlefpul.

]]>
by: faye //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12213 wed, 06 jun 2012 16:58:26 +0000 //www.deco-dalles.com/?p=1131#comment-12213 excellent reminder…another reason to encourage subcontractors to purchase primavera….thank you

regards,
faye

]]>
by: michael lepage //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12212 tue, 22 may 2012 15:50:44 +0000 //www.deco-dalles.com/?p=1131#comment-12212 in reply to jkl.

hi jim,
answers below:
1) copy the subs activities into the master schedule. the merge will not do this for you. merging only provides “updates” so the activities need to be in the master schedule before the merge part can happen.
2) it may be possible for them to have different data dates, but ideally these should be the same.
3) that depends if you want to maintain any activity coding that the contractor put in place. if so, then global code may be the easiest solution.

just to be clear. i’m suggesting putting all subcontractor activities into a master project. then, creating a reflection of the master project and sending it to the sub for updates. merging the updates and rescheduling. for some, it may not be allowed to send the sub the master project and asking them to update their piece. although it may not be allowed, it is the easiest way to maintain a master project and get updates via export from a sub.

hope that helps jim,
regards,
michael

]]>
by: jkl //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12211 tue, 22 may 2012 15:19:57 +0000 //www.deco-dalles.com/?p=1131#comment-12211 your comments
michael,

the reflection tutorial is very helpful. i am trying to use this method on a large project i am currently working on. i have a few questions if you would not mind;
1. do you copy the activities from the subcontractor’s original submitted schedule into your master schedule? or is a merge done to initially capture these activities.
2.does the source project and relfection project have to have the same data date to import and update properly?
3.do both the source project and initial subcontractor xer file have to have the same global, eps or project codes?

thanks,

jim

]]>
by: jackson //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12210 wed, 09 may 2012 21:07:12 +0000 //www.deco-dalles.com/?p=1131#comment-12210 great lessons!

]]>
by: michael lepage //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12209 thu, 19 apr 2012 20:26:42 +0000 //www.deco-dalles.com/?p=1131#comment-12209 in reply to ziq ahmad.

ziq, thanks again! we’ll add these to our list.

]]>
by: ziq ahmad //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12208 thu, 19 apr 2012 02:46:18 +0000 //www.deco-dalles.com/?p=1131#comment-12208 michael maybe you can share a tuts how to generate the s-curve and manpower loading graph from the p6, global function, and maybe cost tracking in p6. i think this website has a great oppurtunity to be a one stop learning centre for a newbie planner like me to enhance the knowledge and to maximise the use of the scheduling tools & planning stuff.

good luck & all the best,
ziq ahmad

]]>
by: michael lepage //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12207 wed, 18 apr 2012 12:58:30 +0000 //www.deco-dalles.com/?p=1131#comment-12207 in reply to ziq ahmad.

ziq, thanks for your comments. if you have any topics you’d like to see, just put them in a comments section and we’ll add them to our growing list.

]]>
by: ziq ahmad //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12206 wed, 18 apr 2012 08:39:45 +0000 //www.deco-dalles.com/?p=1131#comment-12206 great teaching michael. keep the tutorial coming..

]]>
by: michael lepage //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12205 mon, 16 apr 2012 13:02:07 +0000 //www.deco-dalles.com/?p=1131#comment-12205 in reply to jose rodriguez.

jose,
many thanks! we plan to forge ahead.
michael

]]>
by: jose rodriguez //www.deco-dalles.com/approve-updates-from-subcontractors-using-reflection-projects-in-oracle-primavera-video/#comment-12204 mon, 16 apr 2012 01:57:26 +0000 //www.deco-dalles.com/?p=1131#comment-12204 your comments
michael geat job. you are very clear and your teaching tools are great. keep on going

]]>