comments on: use expected finish in primavera p6 to speed updates - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/ project controls training & courses thu, 10 feb 2022 22:07:53 +0000 hourly 1 by: michael lepage //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-89215 thu, 10 feb 2022 22:07:53 +0000 //www.deco-dalles.com/?p=31417#comment-89215 in reply to cindy hammack.

hi cindy, thanks for your comments here. yeah expected finish has it foibles like everything else. i have been burned by having activities pass their ef dates and earlier versions of p6 would choke slightly on this.
one trick i use is to put the expected finish column up so i can easily find them and manage them.
i agree somewhat that using remaining duration avoids ef issues. but of course, with rm updates you can have non-work days you’ve forgotted about and you can get the rm wrong as well. in the end, we all do our best and work the way that’s best for us.

]]>
by: cindy hammack //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-89120 sun, 06 feb 2022 03:13:50 +0000 //www.deco-dalles.com/?p=31417#comment-89120 in reply to jared o’dell.

how about this scenario. a construction activity is started and given an actual start date. instead of throwing a dart hoping to come up with some imaginary expected finish date, you find out from the source how much longer its going to take to finish something. if somebody can guesstimate a date, they can guesstimate a duration. expected finish dates are easy, sure but sometimes – most times – laziness is not the way to approach an update. also, why not move the data date before you update? then the can tell you when and just adjust the finish date and remaining duration will automatically update. if someone tells you they will finish on whatever date and you drop that lug in, everytime the data date moves the remaining duration automatically reduces and appears that work is tracking. what if it’s not? what if zero progress has been made? is it possible, do you think its possible, that activity, due to lack of progress is now actually critical? you would never be able to tell because remaining duration is depleted as time rolls on. when in actuality, they still need x days to complete it.

and for all the time you claim will be saved by updating this way, you’d end up spending way more just to track down all of those surpassed expected finish dates and the results you will be publishing are just a fabrication.

move the data date before updating, adjust the finish date or change the rd. as the data date changes and as the work continues to make no progress it will still show they need x days to complete it.

in my mind (i’ve been a scheduler for over 22 years) the only time it would possibly reasonable to us an expected finish date is on things that have a set duration. procurement, design maybe, other than that it is totally unnecessary and in the end will actually take more time to deal with than figuring out 3 weeks on a 5 day calendar is 15 days. a constraint is a constraint and there is no where i have i ever heard it said that the more constraints the better.

just do the work. that’s what they’re paying you for.

]]>
by: michael lepage //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-75188 tue, 23 apr 2019 17:43:49 +0000 //www.deco-dalles.com/?p=31417#comment-75188 in reply to george.

hi george,
1) expected finish and mandatory finish are very different animals. as this article explains, expected finish is helpful in recalculating remaining duration during updates. mandatory finish will not do any of that. it will pin the activity to that mandatory date with superglue. i do not recommend using mandatory constraints as they can serious mess up critical path.
2) no not at all. that is a good way to get an accurate remaining duration.

]]>
by: george //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-75187 tue, 23 apr 2019 14:12:10 +0000 //www.deco-dalles.com/?p=31417#comment-75187 hi all,
1.- is there a working difference comparing an expected finish to a mandatory finish?
the latter is easier to add and to remove.

2.- is there anything against asking the person responsible for the activity about an educated guess for a remaining duration? leaving responsibility where it belongs.

]]>
by: saqib ali //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-75097 sun, 31 mar 2019 07:07:44 +0000 //www.deco-dalles.com/?p=31417#comment-75097 good article on calculation of remaining duration, really a easy job to using the expected finished date option during in progress activities.

]]>
by: gustavo rezende //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-75068 fri, 22 mar 2019 13:38:15 +0000 //www.deco-dalles.com/?p=31417#comment-75068 thanks michael for this material, it’s been very helpful for my work with primavera.
also, could someone tell me why some activities that i had set up expected finish date and marked as started, when i hit f9 and run the schedule with new data date (before the expected date) they do not register progress on “duration % complete” field.

i appreciate your comments.

]]>
by: jcr //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-63458 sat, 04 aug 2018 02:02:14 +0000 //www.deco-dalles.com/?p=31417#comment-63458 in reply to michael lepage.

during the execution phase when updating an integrated master schedule composed of several interrelated projects through logic with tens of thousands of activities (ship building), it is imperative to utilize simple functions for progressing activities to retain accurate metrics. for in-progress activities, the expected finish field must be populated, thereby allowing the advancement of the data date to automatically decrement remaining durations. updating or altering the expected finish field for a thousand + activities only requires an import from day excel in a supported format of estimated finish date (calendar based udf), then running a global change to alter expected finish to equal the estimated finish. the construction owner is simply required to notify the scheduler of when the task has started and then alter the estimated finish date in a spreadsheet if appropriate. scheduler handles the rest. running a report for in-progress activities with rdu=zero calls out the neglected activities that construction owes a new estimated finish date or actual finish date to the scheduler.

]]>
by: avi //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-46764 wed, 19 jul 2017 20:05:43 +0000 //www.deco-dalles.com/?p=31417#comment-46764 in reply to steve f.

steve,

very valid points. however, i would say that its easier to progress a schedule prior to moving the data date because once you move the data date and don’t update status all activities that have not been progressed will be pushed after the data date and it will be very challenging to determine what activities need to be actualized.

]]>
by: eshor lawal //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-42701 thu, 26 jan 2017 16:34:11 +0000 //www.deco-dalles.com/?p=31417#comment-42701 thanks michael for this. i tried adding expected finish date to all my in-progress activities now, and i noticed, something. as soon as i hit f9, it changed free floats of all the activities to 0.

]]>
by: samir nadra //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-39576 fri, 03 jun 2016 06:35:41 +0000 //www.deco-dalles.com/?p=31417#comment-39576 great article, thank you!
btw before any update i usualy check the “not started activities with exp.finish” (using filters)
also i do check activities as late as posible activities with expected finish as they also can cause a scheduling problem !

]]>
by: mammad //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-36352 wed, 23 dec 2015 05:28:10 +0000 //www.deco-dalles.com/?p=31417#comment-36352 in reply to louie.

hi louie,

what about resource dependent activities?

thanks.

mammad

]]>
by: jared o'dell //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-35335 wed, 25 nov 2015 02:45:15 +0000 //www.deco-dalles.com/?p=31417#comment-35335 in reply to brian.

i would agree that is the probably the first and most important rule of using expected finish

]]>
by: jared o'dell //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-35333 wed, 25 nov 2015 02:40:12 +0000 //www.deco-dalles.com/?p=31417#comment-35333 in reply to derek cairns.

your exactly right, i usually schedule off of actual dates and so by the time i run a new data date my expectation is that nothing moves. that is how i now that i have accounted for everthing before hand in the way of making sure all started activities have expected finish dates. another thing to keep in mind is that logic ties will overide the expected finish in the way of calculating the finish dates but will still show a remaining duration of zero in any case. usually this is spotted pretty easily on the gantt and can work to your advantage if you can figure out the behaviors. the disadvantages are that it can look funny on the chart and mess with earned value calculations if resource loaded, however can be remedied fairly easy with a quick scan and fix or a global change.

]]>
by: jared o'dell //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-35331 wed, 25 nov 2015 02:27:08 +0000 //www.deco-dalles.com/?p=31417#comment-35331 in reply to kent vaughan.

i run into this all the time, but it has actually become a preference for me as it is an indicator of an activity that needs to have an expected finish. when an expected finish is not updated i find that its usually because it is done at or near the expected and not that no progress was made which would be the assumption by p6 had it not reset the remaining duration to zero. the lesser of two evils i guess.

]]>
by: jared o'dell //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-35329 wed, 25 nov 2015 02:15:14 +0000 //www.deco-dalles.com/?p=31417#comment-35329 you have pretty much hit this spot on. i have been using and instructing the use of finish dates in lieu of remaining duration and % complete for years now. generally speaking it is much more useful than the latter, this is particularly so when having none typical schedulers yet owners of activities updating a master directly.

]]>
by: steve f //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-34763 wed, 04 nov 2015 02:49:41 +0000 //www.deco-dalles.com/?p=31417#comment-34763 why not update the data date before taking status? for an in progress task, if the data date is already correct, then inputting a new finish date (not “expected finish”) will automatically adjust the remaining duration based on the number of work days (from the applied calendar) for the task from the first business date following the data date to the selected finish date. this remaining duration will be applied to the next data date move, resulting in a finish date that is one week later than the previously entered finish date…until status is again entered.

]]>
by: michael lepage //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-32287 wed, 09 sep 2015 14:17:59 +0000 //www.deco-dalles.com/?p=31417#comment-32287 in reply to maurice jefferies.

maurice thanks for this contribution.

]]>
by: maurice jefferies //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-32253 wed, 09 sep 2015 04:47:53 +0000 //www.deco-dalles.com/?p=31417#comment-32253 i have run into other limitation of expected finish dates when i am using different calendars to model different project scenarios. on engineering projects subject to inclement weather i typically run both wet and dry weather scenarios by replacing the standard production calendar with a calendar which includes non working days for potential weather events. under this scenario, wip activities constrained with an expected finish date don’t react to the calendar change with an extension of the finish date but rather reverse engineer the remaining duration against the alternate calendar and hold the same finish date. in saying this i am still a big user of expected finish dates and just accept this limitation for the immediate wip activities.

]]>
by: michael lepage //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-29282 mon, 20 jul 2015 17:45:26 +0000 //www.deco-dalles.com/?p=31417#comment-29282 in reply to derek cairns.

thanks to both you and kent – this was something that i completely forgot about. i’ll see if i can incorporate some tips on this into the article.

]]>
by: mohammed savad //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-29091 wed, 15 jul 2015 09:41:28 +0000 //www.deco-dalles.com/?p=31417#comment-29091 thanks a lot. usually i also calculate the remaining days to get the finish date exactly. some times due to calendar it comes wrong. now i know how to deal. thanks michael

]]>
by: derek cairns //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-29088 wed, 15 jul 2015 08:31:49 +0000 //www.deco-dalles.com/?p=31417#comment-29088 kent highlights the only issue that i have encountered with this. don’t let the data date outrun an expected finish date. i’m not sure i agree with kent’s remedy – seems to me it’s treating the symptom. i would say check for expected finish date earlier than data date (before hitting f9) and go back for specific updates on the relevant activities. if the job owner doesn’t co-operate then i normally remove the expected finish date and run with the remaining duration from the last update and let the job owner explain the overrun to the pm.

]]>
by: kent vaughan //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-28988 mon, 13 jul 2015 12:12:09 +0000 //www.deco-dalles.com/?p=31417#comment-28988 we use expected finish dates on i/p task dependent activities. the only issue we’ve had is when the data date goes beyond the expected finish date. the task does not complete (of course) but the duration goes to zero. end users should not allow this to occur, but at times they input an expected finish date and fail to keep it current. to remedy this, we run globals adding 1 hour to the duration in these situations. anyone else had this issue? any better resolution?

]]>
by: brian //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-28897 fri, 10 jul 2015 07:51:11 +0000 //www.deco-dalles.com/?p=31417#comment-28897 totally agree with activity should always be started before applying expected finish otherwise when you keep moving data date forward you will eventually turn all your original and remaining durations to zero on activities not started. this is the real danger of expected finish dates being applied.

]]>
by: louie //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-28869 thu, 09 jul 2015 13:14:51 +0000 //www.deco-dalles.com/?p=31417#comment-28869 i have been using expected finishes for many years now and they have saved me a great deal of time. they present an excellent way to hold end dates without fear of p6 recalculating and changing dates on you. once i have completed my updates i use a global change as follows to give me expected finishes across the project:

where: activity status = in progress
and: activity type = task dependent
then: expected finish = finish

we use “in progress” because you don’t want to add an expected finish to activities that are not in progress; and we use task dependent because you cannot add an expected finish to a milestone activity or a level of effort activity.

]]>
by: gmarcus8 //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-28868 thu, 09 jul 2015 12:06:57 +0000 //www.deco-dalles.com/?p=31417#comment-28868 very helpful tip. thanks for sharing michael.

]]>
by: merdan //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-28867 thu, 09 jul 2015 11:34:00 +0000 //www.deco-dalles.com/?p=31417#comment-28867 just simple and effective. thanks

]]>
by: yinka //www.deco-dalles.com/expected-finish-in-primavera-p6-speedy-updates/#comment-28864 thu, 09 jul 2015 10:14:51 +0000 //www.deco-dalles.com/?p=31417#comment-28864 never knew this trick until now. this is why i always tell people that you should never stop learning.
thank you for sharing this.

]]>