comments on: one trick to export p6 resource assignment data to excel - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/export-p6-resource-assignment-data-excel/ project controls training & courses wed, 03 apr 2024 15:39:29 +0000 hourly 1 by: charlotte j siegel //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-97788 mon, 28 nov 2022 21:27:08 +0000 //www.deco-dalles.com/?p=1812#comment-97788 in reply to zoltan palffy jr..

i have been doing the copy/paste from p6 to excel for the past year and a half using p6 version 17. now i just got version 21 in the cloud, and i created the same layout that i was using for the past year and a half to copy paste all dollars from p6 by month for the entire project into excel. i did the copy, but when i opened the excel spreadsheet – nothing. i keep trying and still nothing. what happened? my clipboard is empty.

]]>
by: anthony //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-97113 fri, 04 nov 2022 15:29:36 +0000 //www.deco-dalles.com/?p=1812#comment-97113 super helpful. nice job.

]]>
by: terry //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-89595 tue, 08 mar 2022 21:47:34 +0000 //www.deco-dalles.com/?p=1812#comment-89595 is there anyway to import resource plan back into primavera on the timescale. the goal is to have each pm update the remaining plan based on resource availability and coordination with project portfolio expectations. we manual plan hours verses standard curves for better planning. currently we manually adjust hours but would like to import the updated export reviewed by pm’s

]]>
by: michael lepage //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-86023 thu, 12 aug 2021 21:01:53 +0000 //www.deco-dalles.com/?p=1812#comment-86023 in reply to roberto suarez.

in that case, you’ll have to change some settings in the wizard. on step 8, you can click the “timescale” button and choose “months”, and you can set the averaging in there as well.

]]>
by: roberto suarez //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-85904 mon, 26 jul 2021 06:13:49 +0000 //www.deco-dalles.com/?p=1812#comment-85904 hi michael, the method really works and very easy. thank you. however, talking about the resource summary, when i changed the units to mandays and have the spreadsheet options set to calculated average, the p6 table shows the required average mandays per month. but when the report is run, the resulting values are still in manhours. how do we change that? thank you.

bobby

]]>
by: michael lepage //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-83348 mon, 11 jan 2021 17:05:52 +0000 //www.deco-dalles.com/?p=1812#comment-83348 in reply to john mccoy.

thanks john!

]]>
by: john mccoy //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-83345 mon, 11 jan 2021 16:22:06 +0000 //www.deco-dalles.com/?p=1812#comment-83345 great solution. you made s curves easy. thanks

]]>
by: balaji //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-83210 wed, 06 jan 2021 09:08:45 +0000 //www.deco-dalles.com/?p=1812#comment-83210 on the resource assignment sheet is their a possibility we could spread earned units like budgeted & actual units. !

]]>
by: janaki sundaram //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-76217 tue, 03 mar 2020 16:38:18 +0000 //www.deco-dalles.com/?p=1812#comment-76217 hi jijo.

have you got any idea to import the resource spreadsheet with changes.?? if so, pls share. it would be a great help.

thanks in advance.

]]>
by: janaki sundaram //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-76216 tue, 03 mar 2020 16:37:23 +0000 //www.deco-dalles.com/?p=1812#comment-76216 in reply to jijo.

hi jijo.

have you got any idea to import the resource spreadsheet with changes.?? if so, pls share. it would be a great help.

]]>
by: michael lepage //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-75620 mon, 26 aug 2019 23:19:54 +0000 //www.deco-dalles.com/?p=1812#comment-75620 in reply to paul johns.

you’re very welcome!

]]>
by: paul johns //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-75597 wed, 21 aug 2019 21:33:44 +0000 //www.deco-dalles.com/?p=1812#comment-75597 thank you for this !!!

most of us will admit we have put a lot of time and effort into solving this, but thanks to 世界杯2022亚洲比赛时间 ( again ! and again !!!…….) and all the hard working people behind this company. we appreciate everything ! this is why we use 世界杯2022亚洲比赛时间 as one of our most visited 世界杯时间比赛时间 for p6.

]]>
by: balan //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-75537 fri, 09 aug 2019 08:36:06 +0000 //www.deco-dalles.com/?p=1812#comment-75537 i really enjoyed this article. i need more information to learn so kindly update it.

]]>
by: aasha //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-75522 tue, 06 aug 2019 05:32:26 +0000 //www.deco-dalles.com/?p=1812#comment-75522 wonderful post!!! thanks for sharing this great post with us…

]]>
by: greg s //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-74990 thu, 28 feb 2019 17:35:30 +0000 //www.deco-dalles.com/?p=1812#comment-74990 after paste to excel, the units include the alpha character d (units/time period = day). e.g.; the cells in excel contain “2.0d” instead of “2.0”. i just want the numeric values copied to excel without the alpha characters. the “d” does not show the p6 resource assignments window. i’m using citrix in case that matters.

]]>
by: adidas stan smith 1 //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-68006 thu, 20 dec 2018 09:33:20 +0000 //www.deco-dalles.com/?p=1812#comment-68006 your web site appears to be having some compatibilty problems in my chrome browser. the text seems to be running off the webpage pretty bad. if you want you can contact me at: %email% and i’ll shoot you over a screen shot of the problem.
adidas stan smith 1 http://www.frwebs.fr/adidas%20stan%20smith%201-id11890.html

]]>
by: adam //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-54480 tue, 09 jan 2018 09:53:57 +0000 //www.deco-dalles.com/?p=1812#comment-54480 or just click an activity hit ctrla open excel hit ctrlv, same thing really but much quicker

]]>
by: patrick skipton //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-52048 mon, 27 nov 2017 16:47:46 +0000 //www.deco-dalles.com/?p=1812#comment-52048 got it, you can adjust the timescale in date options. thanks

]]>
by: patrick skipton //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-52047 mon, 27 nov 2017 16:44:43 +0000 //www.deco-dalles.com/?p=1812#comment-52047 hi, is there a way to present the information instead of monthly, lets say weekly?

]]>
by: jn //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-45504 wed, 24 may 2017 17:46:29 +0000 //www.deco-dalles.com/?p=1812#comment-45504 pretty decent workaround when you’re unable to copy+paste to excel (i.e. p6 via citrix)

it’s still important to double check the data though, as generating csv reports in p6 can sometimes have formatting issues.

]]>
by: vjbaskar //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-42333 mon, 02 jan 2017 11:03:56 +0000 //www.deco-dalles.com/?p=1812#comment-42333 i tried those steps in my tool, it was uploaded but some of the activities, especially the budget estimation had completely collapsed & it is in different value
is there is any other way to get it clear???
i got some help from this site, but i need clear explanation

]]>
by: ahmed //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-40903 thu, 06 oct 2016 11:50:56 +0000 //www.deco-dalles.com/?p=1812#comment-40903 thanks so much

]]>
by: ahmed //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-40181 mon, 08 aug 2016 06:27:46 +0000 //www.deco-dalles.com/?p=1812#comment-40181 dear sir,
what is the quickest method to estimate and assignment materials and manpower 世界杯时间比赛时间 ? by another meaning i need a simple data structure to be easy re-exported from excel to p6

]]>
by: kim //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-39703 tue, 14 jun 2016 19:55:24 +0000 //www.deco-dalles.com/?p=1812#comment-39703 in reply to ann collins.

i know this is way later than your comment but i use the select all command under edit, sometimes i have to do the select all twice but then just past in excel and done.

]]>
by: hariom kumar //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-39669 fri, 10 jun 2016 06:55:19 +0000 //www.deco-dalles.com/?p=1812#comment-39669 can you please explain this topic in with video please

]]>
by: pablo roldos //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-38747 wed, 27 apr 2016 16:06:40 +0000 //www.deco-dalles.com/?p=1812#comment-38747 hi there – how can i display “budget units / time” instead of displaying “budget units”? i want to generate a ‘head count’ report, instead of having a men-hours report.
thank you

]]>
by: gopan //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-38714 sun, 24 apr 2016 02:59:19 +0000 //www.deco-dalles.com/?p=1812#comment-38714 thanks, found it useful

]]>
by: michael lepage //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-38564 wed, 06 apr 2016 14:00:12 +0000 //www.deco-dalles.com/?p=1812#comment-38564 in reply to hatem ismail.

it’s not the filter, but the resource assignments screen only displays 世界杯时间比赛时间 that are assigned to the currently opened project.

]]>
by: hatem ismail //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-38561 wed, 06 apr 2016 10:59:21 +0000 //www.deco-dalles.com/?p=1812#comment-38561 i would like to ask.is the filter defined in this tutorial is enough to ensure that 世界杯时间比赛时间 displayed are only assigned to the open project and not to other projects?

]]>
by: samir //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-38231 thu, 10 mar 2016 09:00:45 +0000 //www.deco-dalles.com/?p=1812#comment-38231 ill try that, thank you very much!

]]>
by: jonathan cornett //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-37945 tue, 16 feb 2016 16:26:50 +0000 //www.deco-dalles.com/?p=1812#comment-37945 in reply to zoltan palffy.

thanks so much!!! i didn’t have much luck running the report wizard, but this worked.

]]>
by: zen //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-35958 wed, 09 dec 2015 09:08:03 +0000 //www.deco-dalles.com/?p=1812#comment-35958 in reply to rajaram redkar.

tell us steps to understand

]]>
by: rajaram redkar //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-34496 fri, 23 oct 2015 13:56:04 +0000 //www.deco-dalles.com/?p=1812#comment-34496 no need to such a big procedure for transferring resource assignment in excel,
>> from table of p6, copy required and paste it to excel file…
so simple….along with distribution its related all information like activity details, dates will come automatically.

enjoy p6

]]>
by: michael lepage //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-34409 mon, 19 oct 2015 18:05:27 +0000 //www.deco-dalles.com/?p=1812#comment-34409 in reply to emmal67.

no. i think you want to turn on cell wrapping in excel to see all the activity description in the same cell with no truncation. try that.

]]>
by: emmal67 //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-34395 mon, 19 oct 2015 05:43:26 +0000 //www.deco-dalles.com/?p=1812#comment-34395 hi, i found this very useful except when i exported into excel some of the formatting was off and i had to spend some time fixing the format so everything was in the right place for me to then run a resource curve. is there a limit on the number of characters in an activity description that will be exported before carrying over to the next cell?

thanks

emma

]]>
by: syed minhaj ahmad //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-34145 mon, 12 oct 2015 07:20:08 +0000 //www.deco-dalles.com/?p=1812#comment-34145 dear sir,

i exported my 世界杯时间比赛时间 which is my boq value as the budgeted cost. but now i want to make import this after making changes in the amount . i could not import this. can you guide me to make this.

thanks

syed

]]>
by: jijo //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-33628 wed, 30 sep 2015 12:13:50 +0000 //www.deco-dalles.com/?p=1812#comment-33628 hi,

could anybody help me with resource importing from excel to primavera p6??

if resource wizard is created in p6 & exported to excel, then the data will import. but it doesn’t import when additional data is inserted in excel.

thanks

]]>
by: ziq //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-32779 tue, 15 sep 2015 10:25:12 +0000 //www.deco-dalles.com/?p=1812#comment-32779 good tutorial.. what if we use the ‘activities’ instead of ‘activities resource and role assignments’? are we still able to get the manhour data from it?

]]>
by: zyman //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-28904 fri, 10 jul 2015 10:54:37 +0000 //www.deco-dalles.com/?p=1812#comment-28904 thank you. can you publish similar article on “how to input actual resource information?” let’s say if i update weekly.

]]>
by: dheekshith //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-26694 tue, 21 apr 2015 18:02:47 +0000 //www.deco-dalles.com/?p=1812#comment-26694 it will be very helpful.

]]>
by: craig //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-25870 wed, 25 mar 2015 00:22:41 +0000 //www.deco-dalles.com/?p=1812#comment-25870 i’m not sure what happened. one of my schedulers tried this and now when the get into the resource assignments icon all they get is a error “0.000000h/d is an invalid unit of measure” i’ve tried to hwelp but not getting anywhere. any ideas?

]]>
by: bagus setyawan //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-25384 tue, 27 jan 2015 20:01:40 +0000 //www.deco-dalles.com/?p=1812#comment-25384 thank you for information, it’s very helpful

]]>
by: adonis //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-25279 thu, 25 dec 2014 04:03:15 +0000 //www.deco-dalles.com/?p=1812#comment-25279 great, thanks.

]]>
by: george //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-25193 mon, 15 dec 2014 21:10:23 +0000 //www.deco-dalles.com/?p=1812#comment-25193 great tip. thanks very much.

]]>
by: fareed //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-24750 thu, 16 oct 2014 12:56:53 +0000 //www.deco-dalles.com/?p=1812#comment-24750 in reply to zoltan palffy.

and since there’s no one way for it, you can chose whichever you like whenever…!!!

]]>
by: zoltan palffy //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-24749 thu, 16 oct 2014 12:11:42 +0000 //www.deco-dalles.com/?p=1812#comment-24749 in reply to ann collins.

ann

all you have to do is select the first cell and hold down the shift and the control key at the same time and select your month and the top row with the number in it. then press control c open excel then press control v. i have done it a hundred of times.

]]>
by: fareed //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-24748 thu, 16 oct 2014 11:55:17 +0000 //www.deco-dalles.com/?p=1812#comment-24748 in reply to ann collins.

you can actually use the ‘activity usage spreadsheet’ button (from the bar chart window/activity view instead of the resource assignment view). just make the necessary changes to the layout at the bottom of the screen so it shows what you want and then copy and paste. here you won’t have any problem copying.

]]>
by: fareed //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-24747 thu, 16 oct 2014 11:49:59 +0000 //www.deco-dalles.com/?p=1812#comment-24747 in reply to steve.

sounds like there was only one incidence of the resource selected. or maybe you selected the ‘only summary’ option?

]]>
by: ann collins //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-21620 mon, 11 aug 2014 01:29:58 +0000 //www.deco-dalles.com/?p=1812#comment-21620 i’ve worked it out. on the ‘report generated’ screen, prior to selecting ‘run report’, deselect the ‘format numbers’ box. the report can then be run and sent to ‘ascii text file’ without the comas or decimal points disrupting the formatting.

]]>
by: ann collins //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-21617 sun, 10 aug 2014 23:32:28 +0000 //www.deco-dalles.com/?p=1812#comment-21617 appreciate your reply zoltan. unfortunately the screen view won’t allow me to select the text,
otherwise i would do exactly that, which has led me to investigate the report export option.

]]>
by: zoltan palffy //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-21534 fri, 08 aug 2014 10:45:40 +0000 //www.deco-dalles.com/?p=1812#comment-21534 an alternative to running the report wizard is to highlight the data then copy and paste into excel

]]>
by: ann collins //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-21524 fri, 08 aug 2014 06:39:22 +0000 //www.deco-dalles.com/?p=1812#comment-21524 kazem … life saver! i’ve been busting my head on how to do this.
question … what i’m more interested is exporting the cumulative budgeted costs as i’m trying to fudge a cashflow scurve.
i’ve created a nonlabour resource and applied a total budgeted cost.
following your instructions, but where i come unstuck is the figures in the spreadsheet aren’t exportinging cleanly e.g. figure is splitting over 2 columns, or $20,000.00 comes out as 000.00$20.
any tips?

]]>
by: hatem ismail //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-20134 tue, 01 jul 2014 21:49:10 +0000 //www.deco-dalles.com/?p=1812#comment-20134 thanks a lot,
i have done that many times before without using report wizard, only selecting first left topmost cell of the left pane on p6 resource assignment page ,pressing shift and selecting last left bottommost cell of the same pane then ctrl+c and ctrl+v to excel sheet, and it is done. it worked well all these times.

]]>
by: steve //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-16945 thu, 15 may 2014 10:41:37 +0000 //www.deco-dalles.com/?p=1812#comment-16945 it didn’t produce an excel report in the format that you show. it just listed the activity id, description, dates and units all along the same line.

any pointers?

]]>
by: billf //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-12529 wed, 05 mar 2014 18:56:05 +0000 //www.deco-dalles.com/?p=1812#comment-12529 when trying to run the report at step 9, i get an application event code
vqasc-0071-e and am unable to run the report.

]]>
by: pankaj vatsa //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-12528 tue, 11 feb 2014 16:38:03 +0000 //www.deco-dalles.com/?p=1812#comment-12528 p6 keep throwing error and hangs up as soon as i enter in the filter where budgeted units/time is greater than 0. please help.

]]>
by: zoltan palffy jr. //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-12527 fri, 11 oct 2013 15:09:57 +0000 //www.deco-dalles.com/?p=1812#comment-12527 in your example you really do not need to export the resource information to excel. you can just highlight the data in p6 and copy and paste it into excel.
all of the steps after step #4 are not needed.

]]>
by: haider //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-12526 mon, 16 sep 2013 07:47:48 +0000 //www.deco-dalles.com/?p=1812#comment-12526 thanks alot buddy. hghly helpful. 🙂

]]>
by: ferrandi //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-12525 wed, 24 jul 2013 14:28:51 +0000 //www.deco-dalles.com/?p=1812#comment-12525 converting to manpower from the hours have one challenge in that it does not cater for simultaneous jobs. therefore by example if i have 2 jobs of 4 hours for an instrument role, one starts at 8am and the other follows at 10am, i require 2 x instrument technicians. the outcome as per your example will produce a manpower requirement of 1 instead of 2. (8 hours in an 8 hour or 12 hour shift)

]]>
by: saeed //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-12524 sat, 29 jun 2013 23:39:21 +0000 //www.deco-dalles.com/?p=1812#comment-12524 thanks , very useful

]]>
by: janshar //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-12523 sat, 22 jun 2013 04:52:09 +0000 //www.deco-dalles.com/?p=1812#comment-12523 sir, it shows error when i put the zero or 8h/d for filtering(step-3). i have to restart primavera for further use. please help

]]>
by: roozbeh hemmati //www.deco-dalles.com/export-p6-resource-assignment-data-excel/#comment-12522 mon, 10 jun 2013 17:28:19 +0000 //www.deco-dalles.com/?p=1812#comment-12522 so many thanks for your good thinkness
sincerely

]]>