comments on: how to find out-of-sequence activities in primavera p6 professional - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/ project controls training & courses thu, 03 dec 2020 07:09:29 +0000 hourly 1 by: tt //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-82335 thu, 03 dec 2020 07:09:29 +0000 //www.deco-dalles.com/?p=39440#comment-82335 hi, why the early start date and early finish date will be same date if the duration is more than 1 days. your response are much appriciated,.

]]>
by: mudiaga //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-76056 sat, 25 jan 2020 08:05:40 +0000 //www.deco-dalles.com/?p=39440#comment-76056 very informative, good work jerome!

]]>
by: tanvir //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-75281 thu, 23 may 2019 16:32:03 +0000 //www.deco-dalles.com/?p=39440#comment-75281 jerome:
i have one activity that finishes on 5/26/19 but the other activity does not start till 7/11/19. why is p6 doing this & how do i fix this gap?
2nd question:
suppose i have 4 lathe machines r4=lathe (l1, l2,l3, l4) i would like p6 to assign each of these like l1,l2,l3,l4 and then again l1,l2,l3,l4 in this sequence but it does not do that. is there a way to make p6 do that? and how.
thanks
tanvir

]]>
by: prabhakar pandey //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-75210 wed, 01 may 2019 08:57:57 +0000 //www.deco-dalles.com/?p=39440#comment-75210 simply log into file and see which activities are out of sequence, correct the sequence if its predecessor is activity and still successor is not completed then you should change the relationship, its simple.its better to keep the retain logic and not progress override to keep the schedule up to date.

]]>
by: cas //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-65514 thu, 25 oct 2018 17:16:26 +0000 //www.deco-dalles.com/?p=39440#comment-65514 *** i meant lower left

]]>
by: cas //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-65513 thu, 25 oct 2018 17:15:41 +0000 //www.deco-dalles.com/?p=39440#comment-65513 fazl, thank you, sir !!!!!! excellent p6 thread. i would also like to add:
i further recommend after following your instructions, for other users to also go to >edit, >user preferences, then select 24 hr, and check the box for “show minutes”.
(now save that layout for purpose of outofsequence analysis). you can now more easily see that the (es or ef) delta from dd (within your relationships / predecessors view, typically lower right) …………..is often less than a full day. sometimes the delta is only a few hours !!

]]>
by: fazl //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-56986 sun, 08 apr 2018 05:34:21 +0000 //www.deco-dalles.com/?p=39440#comment-56986 i have to monitor the out of sequence (oos) activities and get approval for the soft logic changes for the oos activities during update if required. so that i need more clarity on the oos as follow;

i wanted to know that how primavera identify the oos?
how can we categorized the oos?
how can we filter the oos activities (not from the log)?

]]>
by: tijo kurian //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-54428 fri, 05 jan 2018 13:52:28 +0000 //www.deco-dalles.com/?p=39440#comment-54428 is it required to document the logic change. is possible to do progress override instead of retain logic. please clarify

]]>
by: hatem ismail //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47376 wed, 09 aug 2017 10:29:43 +0000 //www.deco-dalles.com/?p=39440#comment-47376 this is an nice example of ron winter’s paper notes about relationships dates in p6. way to go.

]]>
by: viet tran //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47277 mon, 07 aug 2017 01:44:01 +0000 //www.deco-dalles.com/?p=39440#comment-47277 after scheduling, open the log file you will see the out of sequence error (predecessor does not complete while successor completed) and that is the cause to push the finish date of successor out of sequence. and the way i solve is the same with mr. jerome ijachi odeh proposed, in this case we can break the link and assign new relationship.

thanks mr. jerome ijachi odeh,

]]>
by: azeemus muhammad //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47260 sun, 06 aug 2017 12:03:23 +0000 //www.deco-dalles.com/?p=39440#comment-47260 very handy tip jeome. thanks.

azeemus

]]>
by: sami abu al heijaa //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47220 sat, 05 aug 2017 10:36:09 +0000 //www.deco-dalles.com/?p=39440#comment-47220 in reply to michael lepage.

greetings to all

i really do not realize how consultant asks for such logs to be kept and recorded, it is either they are super-powerful planners and above the nature or they are really do not know the volume of work required to log such changes.
to be more specific when working in a none typical project that consist of multiple buildings in different locations and multi disciple activities of epc nature with restrictions on 世界杯时间比赛时间 such as offshore projects, and a list of activities that exceed 10k, the sequence of work is something that cannot be controlled during the execution specially when the work open front is not released for contractor as planned, if we need to keep logging such stoppage and resubmit the schedule with all backups to get client approval we will end up doing the planning package on every weekly report and never have a constant plan / target.

as a contractor i would agree the schedule with client approval and keep the logic unchanged whatsoever this will serve the project forecast and eot.

however at a certain stage, the schedule forecast completion date will absolutely become unacceptable, this is when a real change is required by re-visiting the critical path and the remaining works status with respect to uncompleted activities that are driving the critical path, a revised schedule then can be submitted to get the necessary approval but again this is to be done when it is really required.

]]>
by: jerome ijachi odeh //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47217 sat, 05 aug 2017 09:52:34 +0000 //www.deco-dalles.com/?p=39440#comment-47217 in reply to nelson.

thanks nelson,

=jerome

]]>
by: jerome ijachi odeh //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47216 sat, 05 aug 2017 09:51:37 +0000 //www.deco-dalles.com/?p=39440#comment-47216 in reply to riyad abdul salam.

riyad,

appreciate your comment about contractual implication of changing logic but the tutorial is about a quick way to trace out of sequence activities when retained logic setting in p6 is in place. instead of spending minutes trying to find where the problem lies, it is hoped that this method will save time.

i also added a caveat in my conclusion that logic should only be changed if permitted on the project.

kind regards,
=jerome

]]>
by: nelson //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47215 sat, 05 aug 2017 09:30:34 +0000 //www.deco-dalles.com/?p=39440#comment-47215 excellent tip and comments!

]]>
by: michael lepage //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47209 sat, 05 aug 2017 06:54:45 +0000 //www.deco-dalles.com/?p=39440#comment-47209 in reply to riyad abdul salam.

progressing situations with out-of-sequence issues are sticky indeed. if the schedule was progressed in an order that is not represented in the schedule, and a contract or schedule spec states that p6 must stick to retained logic, then the recommendation is to adjust the logic of the progressed activities to represent the order that activities were in fact executed. the most important aspect about this is communication about out-of-sequence with the team – a discussion that focuses on how to handle these situations and how to reflect them in the schedule. so discuss first so everyone understands what you’re doing to the schedule. utimately, the progress schedule should reflect how the work was executed in the field, and a log should be kept with the changes made to the logic. of course, every project and contract will be different (and likely frustrating).

]]>
by: riyad abdul salam //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47197 fri, 04 aug 2017 22:50:05 +0000 //www.deco-dalles.com/?p=39440#comment-47197 i work for consultants and clients at present – most of the contracts clearly states that it doesn’t allow such changes to logic (past logic) except in a revised baseline programme.

in the absence of any mention in the contract i have followed the task of identifying and correcting the out-of-sequence relationships in already progressed activities in few of my contracts with strict coordination and agreement with the contractor. i have seen in such cases that the forecast dates are very reliable. the major disadvantage is that such transparency needs to be ensured throughout especially considering the fact that the contractors mostly fail to maintain a log leading to the control over the updated schedule practically spoiled. it can lead to further unnecessary complications when dealing with the extension of time claims especially when there are disagreements on the implemented changes to logic.

i suggest to adopt this step if we can maintain logs and the contractor and consultant agrees on the changes as a log each time before such changes actually takes place and the log is communicated, verified and agreed upon – otherwise the normal constraints like ‘baseline programme to be maintained as a bible’ applies. practically i have noticed that it is not a good decision considering the several instances where the contractor’s planning person makes several changes without logging them.

the practical way of getting out is to estimate precisely when to raise the flag regarding revised baseline programme which is implemented in most projects due to the resistance of the contractor and the existence of claim events. the revised programme should be submitted and approved at a fast pace before these out-of-sequence activities exceed an acceptable level and the updated baseline programme becomes a useless entity which misleads the whole project and it’s stakeholders.

in projects where the logs were maintained and the contractor was transparent and honest, the results were outstanding and the programme gave realistic dates. the idea is to first verify the programme without the required changes in logic and then do the changes in coordination and agreement after updating the necessary logs. each time you have to observe the status of the yet to start activities and note that the dates are realistic – if they are not an expert decision has to made on when to raise the flag to go for a revised and updated baseline programme.

the above is not applicable in projects where the contract allows for a ‘progress override’ method while observing out-of-sequence activities. this also has its merits and demerits when it comes to extension of time claims which itself is a wider topic to cover here.

]]>
by: jerome ijachi odeh //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47190 fri, 04 aug 2017 18:23:38 +0000 //www.deco-dalles.com/?p=39440#comment-47190 in reply to joe valdez.

thanks joe

=jerome

]]>
by: joe valdez //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47189 fri, 04 aug 2017 18:13:10 +0000 //www.deco-dalles.com/?p=39440#comment-47189 fear jerome,

usually i just deleted the predecessor when this happen, there 100% anyway it’s a shortcut solution if your are not constrained by the client scheduling requirements.

but this is the way we should fix the error, and i salute you for giving us this tips.

thank you.

]]>
by: jerome ijachi odeh //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47186 fri, 04 aug 2017 16:58:40 +0000 //www.deco-dalles.com/?p=39440#comment-47186 in reply to tijo kurian.

tijo,

unfortunately, i’m not in a position to produce a video tutorial.

jerome

]]>
by: tijo kurian //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47185 fri, 04 aug 2017 16:52:32 +0000 //www.deco-dalles.com/?p=39440#comment-47185 dear jerome ,

can you please prepare the video for this

]]>
by: jerome ijachi odeh //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47176 fri, 04 aug 2017 11:38:11 +0000 //www.deco-dalles.com/?p=39440#comment-47176 in reply to derek cairns.

thanks derek,

glad you found this quick tip useful.

kind regards,
jerome

]]>
by: derek cairns //www.deco-dalles.com/find-out-of-sequence-activities-primavera-p6/#comment-47175 fri, 04 aug 2017 11:28:21 +0000 //www.deco-dalles.com/?p=39440#comment-47175 jerome, brilliant solution. i so rarely use “early” dates – i either use start/finish and frequently remaining early start but it’s an annoying problem sometimes and this is a great way to get to the bottom of it. like all the best solutions it’s simplicity itself. i’ve been doing this job for a hundred years and still learning!

]]>