comments on: fix out of sequence progress in primavera p6 schedule - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/ project controls training & courses mon, 10 apr 2023 10:53:09 +0000 hourly 1 by: kumar //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-101076 mon, 10 apr 2023 10:53:09 +0000 //www.deco-dalles.com/?p=1877#comment-101076 hi, i had doubts. the approved baseline schedule missed the logic link for one activity. which is a predominant delay for the whole project but the mistake which is not linked to project completion in the approved baseline. how to resolve it without knowing other parties.

]]>
by: phillip sotelo //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-82140 wed, 25 nov 2020 13:20:11 +0000 //www.deco-dalles.com/?p=1877#comment-82140 by adjusting the oos in the update, then a manual update will be done every time since there will be no more predecessor activity to drive. or by if predecessor and successor are originally fs, then eventually became parallel, then an additional work for the planner to monitor this changes not to show illogical scenario in the future updates.

the best adjustment will be replacing the current fs logic to ss/ff+lag to maintain the integrity of the sequence of work.

]]>
by: clarence maizes //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-61155 tue, 26 jun 2018 19:24:47 +0000 //www.deco-dalles.com/?p=1877#comment-61155 “best blogpost! hello mates, nice post and good arguments commented here, i am in fact_ enjoying by these.”

]]>
by: mohamed //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-59537 sat, 02 jun 2018 22:57:35 +0000 //www.deco-dalles.com/?p=1877#comment-59537 thanks sean for your article i found it very helpful.

do you correct the logic in baseline as well or just in the updates ? shouldnt you make sure that this logic adjustment does not affect the baseline project finish date ?

]]>
by: rzetelnie omówione //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-45490 tue, 23 may 2017 03:00:56 +0000 //www.deco-dalles.com/?p=1877#comment-45490 machinery in factories and warehouses often are required to be professionally inspected for efficiency and safety reasons. since the human eye cannot naturally always see the intricate inner workings of the machines, these scopes are perfect for getting that insider’s view.

http://www.bazarek.nl/user/profile/4708

]]>
by: nauman mustafa //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-44048 tue, 11 apr 2017 09:27:33 +0000 //www.deco-dalles.com/?p=1877#comment-44048 very informative post.

]]>
by: home //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-42068 fri, 23 dec 2016 11:15:38 +0000 //www.deco-dalles.com/?p=1877#comment-42068 ilpnyohsiplqnhmyemypfhfbvqjaxzporstfeqgejswjoyqpbzoxotmw
home http://www.smartbalanceworld.com

]]>
by: home //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-42014 tue, 20 dec 2016 08:16:48 +0000 //www.deco-dalles.com/?p=1877#comment-42014 zftofrvdbdmpexoncvexezghojrjyjjouyymqniojjuqrudytkrvxwgtml
home http://www.hoverboardkings.com

]]>
by: ahmad //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-40572 mon, 05 sep 2016 05:33:04 +0000 //www.deco-dalles.com/?p=1877#comment-40572 dear all,

1- i have an out of sequence, an activity still on progress and the successor activitiy has been completed by submitting an undertaken letter. meanwhile, the on progress activity still showing and driving the delay of the project, and primavera expect it to be finished before the project completion date. so why there is delay !!
2- i had a lot of oos activities, and i have changed the links, when i submitted a notice of delay to the consultat, he rejected the update due to changes in the relations. it seems that he was not revising the weekly submitted soft copy of the primavera file.
3- what is the best way to measure the progress % complete ? is it the cost ? or the duration ? or labour unit % complete?

thanks in advanced.

regards,

]]>
by: evie penley //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-38435 sat, 26 mar 2016 07:52:53 +0000 //www.deco-dalles.com/?p=1877#comment-38435 i was more than happy to seek out this internet-site.i needed to thanks on your time for this excellent read!! i undoubtedly having fun with every little bit of it and i have you bookmarked to take a look at new stuff you weblog post.

http://ow.ly/ziprq

]]>
by: youssef //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-37076 sun, 17 jan 2016 13:09:59 +0000 //www.deco-dalles.com/?p=1877#comment-37076 the report in p6 oracle do not show the nos of out of sequences activities

but when you filter you found a lot.

so please let me know what that guy did in the option of the schedule?

]]>
by: eric //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-36420 sun, 27 dec 2015 21:16:31 +0000 //www.deco-dalles.com/?p=1877#comment-36420 hi can i give my schedule for review? 🙂

]]>
by: finely processed new balance blue fluorescent yellow running //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-34560 tue, 27 oct 2015 03:05:46 +0000 //www.deco-dalles.com/?p=1877#comment-34560 hey would you mind letting me know which webhost you’re using? i’ve loaded your blog in 3 completely different browsers and i must say this blog loads a lot quicker then most. can you suggest a good internet hosting provider at a reasonable price? thanks, i appreciate it!
finely processed new balance blue fluorescent yellow running http://www.jccwebb.co.uk/images/config.php?super-discount-new-balance-blue-fluorescent-yellow-running-t-5855_354.html

]]>
by: jumana //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-33627 wed, 30 sep 2015 11:20:58 +0000 //www.deco-dalles.com/?p=1877#comment-33627 helpful information ,thanks all .
but as project management rules ,what is the proper request regarding oos activities.
in the contractor schedule there are many out of sequence activities occurred in weekly updates .and they try to solve by deleting and modification of relationship link type to shrink the delay and handing over dates.
please help as pm opinion to the schedule ,even that we requested a revised schedule ,but still not approved and still worked in previous submitted one before months ago.

]]>
by: kishore a nair //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-20015 sat, 28 jun 2014 08:10:00 +0000 //www.deco-dalles.com/?p=1877#comment-20015 in reply to sean cain.

thanks sean,

what you said is correct and logical. but generally i think we required prior consent from client for this kind of scheduling.

also could you please suggest me some references about this practice. so that i could convince my people over here about this practice.

thank you so much and will be watching the blog closely for these kind of informative tips.

]]>
by: mimoune djouallah //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-19970 thu, 26 jun 2014 04:14:31 +0000 //www.deco-dalles.com/?p=1877#comment-19970 thanks sean, you literally saved my day

regards
mimoune

]]>
by: sean cain //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-19897 mon, 23 jun 2014 14:20:07 +0000 //www.deco-dalles.com/?p=1877#comment-19897 kishore,

the update tracks the progress of a project and is supposed to adapt and change to what is going on with said project, whereas the baseline stays untouched. you must certainly fix any out-of-sequence progress encountered with the project because the update is not always going to track what the baseline laid out. this is very common in most forms of construction and is expected to be implemented where necessary. remember, the baseline is the original plan for the project and it is a best case scenario for the buildout of the the project. the update is as built status, current forecast and future forecast that changes with the project.

any delay notices should be based off the update, although you can also show delays in a copy of the baseline for some forms of delay analysis.

]]>
by: kishore a nair //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-19863 sun, 22 jun 2014 05:16:43 +0000 //www.deco-dalles.com/?p=1877#comment-19863 ** in this case that is, while fixing out of sequence activities, i think we are loosing a baseline to compare. because if we change the link in the update then the sequence in the baseline and the update will have a different flow . so we cannot compare the baseline dates and logic with the updates thereafter.

so on which program we will prepare the eot.
based on which program dates we can send delay notices?

]]>
by: sean cain //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-12540 mon, 16 sep 2013 19:10:21 +0000 //www.deco-dalles.com/?p=1877#comment-12540 another thing to remember is that even though a predecessor is complete, it’s predecessor may not and can continue to push through to follow-on successors.

]]>
by: sean cain //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-12539 thu, 12 sep 2013 15:12:28 +0000 //www.deco-dalles.com/?p=1877#comment-12539 tajamal,

that would be assuming the logic tie is a ss relationship. with the predecessor activity not complete, it will still drive the successor properly which is shown above in the example.

]]>
by: tajamal //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-12538 tue, 10 sep 2013 13:45:53 +0000 //www.deco-dalles.com/?p=1877#comment-12538 while updating the schedule the predecessor completed before its planned finish date , n this completion have no effect on successor whose start data is behind the data date .
as in my opinion successor should take the data date as the start date bcz the predecessor is completed before the its planned finish date.
plz reply mr. sean cain

]]>
by: sean cain //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-12537 mon, 08 jul 2013 11:38:12 +0000 //www.deco-dalles.com/?p=1877#comment-12537 freddie,

i would not advise switching between the retained logic or progress override setting on any project regardless of the out-of-sequence activities. you need to check what the contract specifies for which option is to be used and that setting should be used for the duration of the project. most projects will specify the use of retained logic.

]]>
by: gfreddiek //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-12536 sun, 07 jul 2013 12:19:53 +0000 //www.deco-dalles.com/?p=1877#comment-12536 in correcting the logic of the out of sequence activities, do you change the scheduling option from retained logic to progress overide? or you just keep it retained logic until the project is done.

]]>
by: sean cain //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-12535 mon, 01 jul 2013 11:28:55 +0000 //www.deco-dalles.com/?p=1877#comment-12535 mahmoud,

thanks for your comments. maybe i should have used a different example. typically, as a contractor, we do not get schedules from the general contractor and we need to track the key predecessors to our work (work by others that drives our work) in our schedule. in doing that we do not put the complete activity in but, just the predecessor. so in a case where the work by others is not complete and ultimately holds up our work, we leave the out-of-sequence work in place to show that we still need that predecessor to finish before our work can complete. i hope that is clearer.

larry,

to your first question, yes, the out-of-sequence work should be corrected even if one of the activities in question is complete. it is good practice to review all out-of-sequence work each update period to make sure you do not have a very long list (of oos) as well as not to have any remaining duration pushing through complete activity logic. the effect on the critical path will be that you have good forecasted end dates and not any issues of out-of-sequence working inadvertently pushing out any work that is not complete. in regards to the second question, you cannot ask for compensation until you have used up all available float (you’ve gone negative) and this can be quantified by comparing your current update to the baseline schedule to see if there has been a delay issue. out-of-sequence logic does not necessarily cause negative float but, it can use up available float very easily and the more out-of-sequence logic you have the more issues you will have with incorrect forecast dates and less available float for all the activities tied to the out-of-sequence (in question).

]]>
by: larry erbe //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-12534 sun, 30 jun 2013 21:31:14 +0000 //www.deco-dalles.com/?p=1877#comment-12534 follow up question, if the baseline showed an activity(s) as not critical how are you to determine (at the time of schedulimg) if, now that it was done out of sequence, whether or not is became critical and therefore any delay to the out of sequence work is subject to compensatory time? this is especially difficult for me if the out of sequence work is 100% completed between schedule updates.

]]>
by: larry erbe //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-12533 sun, 30 jun 2013 19:50:48 +0000 //www.deco-dalles.com/?p=1877#comment-12533 couple of questions, when out of sequence work occures and the work being done out of sequence is 100% complete, therefore no longer affecting it’s successor, is it still necessary to redo the logic? (in answering this question assume the remaining activity will start on the current data date therefore a logical predecessor is not needed to push the activity out to a specific start date.) also, more importantly, will not corrected logic for completed activities have any effect the remaining critical path activities? (i can’t imaging it does but need to be sure.)

]]>
by: mahmoud //www.deco-dalles.com/fix-out-of-sequence-progress-primavera-p6/#comment-12532 sat, 29 jun 2013 10:16:33 +0000 //www.deco-dalles.com/?p=1877#comment-12532 good lesson sean, but the third example in not clear..

]]>