comments on: ask 世界杯2022亚洲比赛时间 : how to fix p6 partial durations - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/fix-p6-partial-durations/ project controls training & courses tue, 16 jul 2024 20:04:21 +0000 hourly 1 by: terence underwood //www.deco-dalles.com/fix-p6-partial-durations/#comment-67124 wed, 05 dec 2018 01:51:10 +0000 //www.deco-dalles.com/?p=36129#comment-67124 great information for p6 beginners. thanks for this
terry

]]>
by: keith wylde //www.deco-dalles.com/fix-p6-partial-durations/#comment-41067 mon, 17 oct 2016 20:19:47 +0000 //www.deco-dalles.com/?p=36129#comment-41067 this video provides an excellent way to identify partial days (by turning
on the decimal settings to 2 and/or setting the user preferences time to
hours).

however, there is no p6 filter that can be constructed to capture or list
partial day activities. in addition, it’s possible for activities to be
free of partial days, however, the total float value may be partial.

in the software known as “zümmer – cpm construction analysis &
comparison”, there are a number of reports designed to list “partial days”
issues. the advantage here is the ability to isolate and quantify the
partial day activities. having a specific list allows the p6 user to
quickly resolve the partial days without having to scroll through the
entire network.

for further information, please go to the zümmer group in linkedin and
read the conversation titled: “partial day durations”.

keith

]]>