comments on: what is a level of effort activity in primavera p6? [faqs] - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/level-of-effort-faq/ project controls training & courses fri, 12 jan 2024 16:05:20 +0000 hourly 1 by: paul nixon //www.deco-dalles.com/level-of-effort-faq/#comment-85718 wed, 07 jul 2021 10:57:40 +0000 //www.deco-dalles.com/?p=2011#comment-85718 in reply to neda.

hello,
progress the schedule and p6 will update the schedule % complete. you will then need to copy this to the physical % complete in order to capture a accurate ev cost / spi.

hope this helps.

kind regards
paul

]]>
by: kiendinh //www.deco-dalles.com/level-of-effort-faq/#comment-75484 fri, 26 jul 2019 03:49:43 +0000 //www.deco-dalles.com/?p=2011#comment-75484 thanks for your level of effort. it’s quite useful to get something new

]]>
by: emma anene //www.deco-dalles.com/level-of-effort-faq/#comment-46229 thu, 22 jun 2017 10:00:10 +0000 //www.deco-dalles.com/?p=2011#comment-46229 please, can someone help me with a detailed wbs for a gas turbine installation and commissioning project ?. thank you

]]>
by: pranab deb //www.deco-dalles.com/level-of-effort-faq/#comment-41699 fri, 02 dec 2016 16:48:41 +0000 //www.deco-dalles.com/?p=2011#comment-41699 in reply to warren.

hi warren,

did you figure a way out for this?

kind regards

pranab

]]>
by: mohammad //www.deco-dalles.com/level-of-effort-faq/#comment-40018 thu, 21 jul 2016 05:01:02 +0000 //www.deco-dalles.com/?p=2011#comment-40018 in my project, drawing submission can not start without kick of meeting with customer. however, as per above logic, this meeting will be level of effort activity. but if this meeting delays then whole engineering work get delay. so, even if this activity is loe but still it has to be on critical path.

any suggestion……

]]>
by: lohit //www.deco-dalles.com/level-of-effort-faq/#comment-39769 wed, 22 jun 2016 09:12:13 +0000 //www.deco-dalles.com/?p=2011#comment-39769 hi,

how to fix the loe activities expenses..??

when the links for these activities are ss and ff, actual start date of the activity is from the predecessor activity but how about the % complete or earned value cost (expenses) under this activity..??

earned value cost seems to be 0..??

performance % complete appears to be 0%.

can you advise on this issue..??

]]>
by: sebastian //www.deco-dalles.com/level-of-effort-faq/#comment-37761 tue, 09 feb 2016 08:06:22 +0000 //www.deco-dalles.com/?p=2011#comment-37761 sir,

how to fix the loe 世界杯时间比赛时间 distribution? the distribution of the 世界杯时间比赛时间 is beyond the finish date.

thanks & regards

]]>
by: plannertuts //www.deco-dalles.com/level-of-effort-faq/#comment-24959 thu, 06 nov 2014 13:48:18 +0000 //www.deco-dalles.com/?p=2011#comment-24959 in reply to christia u festus.

how you considered our online training for primavera p6? click the home link above for more information – it’s all on this site.
michael

]]>
by: christia u festus //www.deco-dalles.com/level-of-effort-faq/#comment-24945 wed, 05 nov 2014 05:31:49 +0000 //www.deco-dalles.com/?p=2011#comment-24945 what is the method to learn more or understanding more of primavera p6 .
for my work demands for that. as much as i try i meet new thing which i do not know tomorrow.

]]>
by: warren //www.deco-dalles.com/level-of-effort-faq/#comment-19480 tue, 03 jun 2014 10:00:53 +0000 //www.deco-dalles.com/?p=2011#comment-19480 sir michael,

i have an updated programme containing several loes where i used as a “revised baseline”. when this is updated, the loes show dates that are beyond the project finish date. what’s wrong with my schedule?

warren sika

]]>
by: hari rama subbiah //www.deco-dalles.com/level-of-effort-faq/#comment-12576 wed, 30 oct 2013 13:54:51 +0000 //www.deco-dalles.com/?p=2011#comment-12576 sir,

whether this loe can be used for engineering activities like shop drawing / materials submission & approvals??

please advice.

thankyou in advance..

]]>
by: neda //www.deco-dalles.com/level-of-effort-faq/#comment-12575 sat, 12 oct 2013 09:04:00 +0000 //www.deco-dalles.com/?p=2011#comment-12575 thanks for you.
i have another question , how calculate percent complete for level of effort activities?

]]>
by: anil varghese //www.deco-dalles.com/level-of-effort-faq/#comment-12574 sat, 12 oct 2013 06:45:30 +0000 //www.deco-dalles.com/?p=2011#comment-12574 as usual mr.michael’s lessons are very useful.
thank you very much

]]>
by: vishal a. g. //www.deco-dalles.com/level-of-effort-faq/#comment-12573 sat, 12 oct 2013 05:11:51 +0000 //www.deco-dalles.com/?p=2011#comment-12573 very much useful.

]]>
by: darrell //www.deco-dalles.com/level-of-effort-faq/#comment-12572 fri, 11 oct 2013 21:38:45 +0000 //www.deco-dalles.com/?p=2011#comment-12572 level of effort?
a level of effort not crtical? debate
level of effort! pedeccesor and sucssecor links?
we are not thinking hamocks?
p6 level of effort!
has only predecessor’s with a ss an ff!!
you want it to be critical! use a finish milestone with the last activity in the sequence (ff) milestone! all activities need to be linked!

all activities that make the level of effort must be linked in the predecessors section, if not then any activiy that is out of sequnce will not be captured! then why can is it level of effort cant be critical? it’s a no brainer, if the activities linked are crtical then the loe is!

]]>