activity id / unique id | task name | base duration | base duration unit | revised duration | revised duration unit | base total float | base total float unit | revised total float | revised total float unit |
a1210 | sb prepare span 2 deck | 160 | hr(s) | 160 | hr(s) | 360 | hr(s) | 248 | hr(s) |
a1220 | sb prepare span 3 t-beams | 160 | hr(s) | 160 | hr(s) | 256 | hr(s) | 160 | hr(s) |
a1700 | sb prepare span 3 deck | 160 | hr(s) | 160 | hr(s) | 360 | hr(s) | 248 | hr(s) |
a1230 | sb prepare bent 2 edge beam | 160 | hr(s) | 160 | hr(s) | 360 | hr(s) | 208 | hr(s) |
a1660 | sb approve span 3 t-beams | 120 | hr(s) | 120 | hr(s) | 360 | hr(s) | 224 | hr(s) |
a1940 | sb approve span 3 deck | 120 | hr(s) | 120 | hr(s) | 512 | hr(s) | 360 | hr(s) |
a1670 | sb approve bent 2 edge beam | 120 | hr(s) | 120 | hr(s) | 504 | hr(s) | 296 | hr(s) |
a1950 | sb approve bent 3 edge beam | 120 | hr(s) | 120 | hr(s) | 512 | hr(s) | 304 | hr(s) |
a2200 | sb approve bent 4 edge beam | 120 | hr(s) | 120 | hr(s) | 512 | hr(s) | 304 | hr(s) |
a1960 | sb approve span 4-6 deck | 120 | hr(s) | 120 | hr(s) | 488 | hr(s) | 352 | hr(s) |
a1680 | sb approve span 7-9 deck | 120 | hr(s) | 120 | hr(s) | 288 | hr(s) | 192 | hr(s) |
a2210 | sb approve span 1-6 bridge rail curb | 120 | hr(s) | 120 | hr(s) | 624 | hr(s) | 416 | hr(s) |
a1710 | sb prepare bent 3 edge beam | 160 | hr(s) | 160 | hr(s) | 360 | hr(s) | 208 | hr(s) |
a1970 | sb prepare bent 4 edge beam | 160 | hr(s) | 160 | hr(s) | 360 | hr(s) | 208 | hr(s) |
a1720 | sb prepare span 4-6 deck | 160 | hr(s) | 160 | hr(s) | 344 | hr(s) | 240 | hr(s) |
a1240 | sb prepare span 7-9 deck | 160 | hr(s) | 160 | hr(s) | 200 | hr(s) | 136 | hr(s) |
a1980 | sb prepare span 1-6 bridge rail curb | 160 | hr(s) | 160 | hr(s) | 432 | hr(s) | 288 | hr(s) |
a1990 | sb prepare span 7-9 f-rail | 160 | hr(s) | 160 | hr(s) | 592 | hr(s) | 448 | hr(s) |
a1250 | sb prepare bent 1 & 10 end panels | 160 | hr(s) | 160 | hr(s) | 1088 | hr(s) | 944 | hr(s) |
a1650 | sb approve span 2 deck | 120 | hr(s) | 120 | hr(s) | 504 | hr(s) | 352 | hr(s) |
a2220 | sb approve span 7-9 f-rail | 120 | hr(s) | 120 | hr(s) | 848 | hr(s) | 640 | hr(s) |
a1690 | sb approve bent 1 & 10 end panels | 120 | hr(s) | 120 | hr(s) | 1528 | hr(s) | 1336 | hr(s) |
a1500 | sb fabricate span 2 t-beams | 160 | hr(s) | 160 | hr(s) | 264 | hr(s) | 240 | hr(s) |
a1830 | sb fabricate span 2 deck | 160 | hr(s) | 160 | hr(s) | 360 | hr(s) | 256 | hr(s) |
a1840 | sb fabricate span 3 t-beams | 160 | hr(s) | 160 | hr(s) | 264 | hr(s) | 160 | hr(s) |
a2070 | sb fabricate span 3 deck | 160 | hr(s) | 160 | hr(s) | 360 | hr(s) | 256 | hr(s) |
a1260 | sb fabricate span 1 edge-beams | 160 | hr(s) | 160 | hr(s) | 104 | hr(s) | 16 | hr(s) |
a1270 | sb fabricate span 1 deck | 160 | hr(s) | 160 | hr(s) | 168 | hr(s) | 80 | hr(s) |
a1850 | sb fabricate bent 2 edge beam | 160 | hr(s) | 160 | hr(s) | 360 | hr(s) | 216 | hr(s) |
a2080 | sb fabricate bent 3 edge beam | 160 | hr(s) | 160 | hr(s) | 360 | hr(s) | 216 | hr(s) |
a2380 | sb fabricate bent 4 edge beam | 160 | hr(s) | 160 | hr(s) | 360 | hr(s) | 216 | hr(s) |
a2090 | sb fabricate span 4-6 deck | 160 | hr(s) | 160 | hr(s) | 352 | hr(s) | 248 | hr(s) |
a1860 | sb fabricate span 7-9 deck | 160 | hr(s) | 160 | hr(s) | 208 | hr(s) | 144 | hr(s) |
a2390 | sb fabricate span 1-6 bridge rail curb | 160 | hr(s) | 160 | hr(s) | 440 | hr(s) | 296 | hr(s) |
a2550 | sb fabricate span 7-9 f-rail | 160 | hr(s) | 160 | hr(s) | 440 | hr(s) | 296 | hr(s) |
a1870 | sb fabricate bent 1 & 10 end panels | 160 | hr(s) | 160 | hr(s) | 1096 | hr(s) | 952 | hr(s) |
a3400 | sb structure complete (sb/nb on) | 0 | hr(s) | 0 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3130 | ne sound wall - nb - shop drwgs. | 720 | hr(s) | 720 | hr(s) | 5784 | hr(s) | 872 | hr(s) |
a1290 | fabricate strip seals - wrb sb | 480 | hr(s) | 480 | hr(s) | 1088 | hr(s) | 944 | hr(s) |
a3320 | remove decomm demo containment | 160 | hr(s) | 160 | hr(s) | 984 | hr(s) | 272 | hr(s) |
a3370 | remove west work bridge | 152 | hr(s) | 152 | hr(s) | 984 | hr(s) | 272 | hr(s) |
a3300 | class 1 finish 3 tube curb (span 1-6) | 160 | hr(s) | 160 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3070 | bent 2 install expansion joints | 40 | hr(s) | 40 | hr(s) | 448 | hr(s) | 408 | hr(s) |
a2230 | bent 2 edge beam f/p/s | 80 | hr(s) | 80 | hr(s) | 560 | hr(s) | 432 | hr(s) |
a2400 | bent 3 edge beam f/p/s | 80 | hr(s) | 80 | hr(s) | 480 | hr(s) | 352 | hr(s) |
a2570 | bent 4 edge beam f/p/s | 80 | hr(s) | 80 | hr(s) | 360 | hr(s) | 216 | hr(s) |
a3350 | sb structure complete (sb on) | 0 | hr(s) | 0 | hr(s) | 152 | hr(s) | 112 | hr(s) |
a3120 | nb rebar - shafts/ftgs | 480 | hr(s) | 480 | hr(s) | 1056 | hr(s) | 896 | hr(s) |
a2160 | bent 1 backfill | 32 | hr(s) | 32 | hr(s) | 1072 | hr(s) | 928 | hr(s) |
a2260 | bent 1 end panel | 64 | hr(s) | 64 | hr(s) | 1048 | hr(s) | 904 | hr(s) |
a2970 | bent 4 closure pour complete | 80 | hr(s) | 80 | hr(s) | 472 | hr(s) | 408 | hr(s) |
a3050 | bent 4 install expansion joint | 40 | hr(s) | 40 | hr(s) | 472 | hr(s) | 408 | hr(s) |
a3220 | bent 7 install expansion joint | 80 | hr(s) | 80 | hr(s) | 344 | hr(s) | 280 | hr(s) |
a2660 | bent 10 f/p/s backwall | 80 | hr(s) | 80 | hr(s) | 576 | hr(s) | 512 | hr(s) |
a3010 | bent 10 jack end bent / bearings | 8 | hr(s) | 8 | hr(s) | 576 | hr(s) | 512 | hr(s) |
a2730 | bent 10 backfill | 32 | hr(s) | 32 | hr(s) | 576 | hr(s) | 512 | hr(s) |
a2780 | bent 10 end panels | 64 | hr(s) | 64 | hr(s) | 576 | hr(s) | 512 | hr(s) |
a1310 | span 1 precast floor beams | 24 | hr(s) | 24 | hr(s) | 240 | hr(s) | 152 | hr(s) |
a1730 | span 1 t-beams | 64 | hr(s) | 64 | hr(s) | 104 | hr(s) | 16 | hr(s) |
a1810 | span 1 deck | 80 | hr(s) | 80 | hr(s) | 104 | hr(s) | 16 | hr(s) |
a2940 | bent 10 install expansion joint | 40 | hr(s) | 40 | hr(s) | 576 | hr(s) | 512 | hr(s) |
a2890 | bent 10 f/p/s expansion joint | 40 | hr(s) | 40 | hr(s) | 576 | hr(s) | 512 | hr(s) |
a1910 | span 1 deck cure | 112 | hr(s) | 112 | hr(s) | 152 | hr(s) | 32 | hr(s) |
a2050 | span 1 post-tensioning & grout/blk outs | 56 | hr(s) | 56 | hr(s) | 104 | hr(s) | 16 | hr(s) |
a2580 | span 1 bridge rail curb | 48 | hr(s) | 48 | hr(s) | 720 | hr(s) | 576 | hr(s) |
a2610 | span 1 strip formwork | 80 | hr(s) | 80 | hr(s) | 2144 | hr(s) | 1456 | hr(s) |
a2710 | span 1 finish work | 80 | hr(s) | 80 | hr(s) | 2144 | hr(s) | 1456 | hr(s) |
a2810 | span 1 remove falsework | 40 | hr(s) | 40 | hr(s) | 3968 | hr(s) | 1720 | hr(s) |
a1130 | span 2 remove arch rib falsework | 120 | hr(s) | 120 | hr(s) | 288 | hr(s) | 200 | hr(s) |
a1320 | span 2 t-beam falsework | 256 | hr(s) | 256 | hr(s) | 288 | hr(s) | 200 | hr(s) |
a2170 | span 2 form t-beams | 160 | hr(s) | 160 | hr(s) | 104 | hr(s) | 16 | hr(s) |
a2440 | span 2 rebar t-beams | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 16 | hr(s) |
a2450 | span 2 erect floor precast beams | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 16 | hr(s) |
a2490 | span 2 pour t-beams | 16 | hr(s) | 16 | hr(s) | 104 | hr(s) | 16 | hr(s) |
a2530 | span 2 deck forming | 240 | hr(s) | 240 | hr(s) | 104 | hr(s) | 16 | hr(s) |
a2620 | span 2 deck rebar | 160 | hr(s) | 160 | hr(s) | 104 | hr(s) | 16 | hr(s) |
a2820 | span 2 bidwell setup / dry run | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 16 | hr(s) |
a2910 | span 2 pour deck | 24 | hr(s) | 24 | hr(s) | 104 | hr(s) | 16 | hr(s) |
a2960 | span 2 cure deck | 80 | hr(s) | 80 | hr(s) | 152 | hr(s) | 16 | hr(s) |
a3040 | span 2 strip t-beams | 56 | hr(s) | 56 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3080 | span 2 remove t-beam f/w | 160 | hr(s) | 160 | hr(s) | 1752 | hr(s) | 1104 | hr(s) |
a3090 | span 2 t/edge/deck closure pour - f/p/s | 160 | hr(s) | 160 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3250 | span 2 bridge rail curb | 64 | hr(s) | 64 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3260 | span 2 strip edge-beam falsework | 120 | hr(s) | 120 | hr(s) | 1752 | hr(s) | 1104 | hr(s) |
a1470 | span 3 jacking arch | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a1540 | span 3 arch rib closure | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a1550 | span 3 remove arch rib falsework | 120 | hr(s) | 120 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a1610 | span 3 t beam falsework | 256 | hr(s) | 256 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a2100 | span 3 form t-beams | 160 | hr(s) | 160 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a2410 | span 3 rebar t-beams | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a2420 | span 3 erectfloor precast beams | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a2460 | span 3 pour t-beams | 16 | hr(s) | 16 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a2470 | span 3 deck forming | 320 | hr(s) | 320 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a2690 | span 3 deck rebar | 160 | hr(s) | 160 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a2850 | span 3 bidwell setup / dry run | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a2980 | span 3 pour deck | 24 | hr(s) | 24 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a3020 | span 3 cure deck | 80 | hr(s) | 80 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a3100 | span 3 strip t-beams | 56 | hr(s) | 56 | hr(s) | 1976 | hr(s) | 1232 | hr(s) |
a3110 | span 3 t/edge/deck closure pour - f/p/s | 160 | hr(s) | 160 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a3210 | span 3 remove t-beam f/w | 160 | hr(s) | 160 | hr(s) | 1976 | hr(s) | 1232 | hr(s) |
a3270 | span 3 bridge rail curb | 64 | hr(s) | 64 | hr(s) | 104 | hr(s) | 64 | hr(s) |
a3280 | span 3 strip edge-beam falsework | 120 | hr(s) | 120 | hr(s) | 1992 | hr(s) | 1168 | hr(s) |
a1460 | span 4 pour bottom slab 1a | 8 | hr(s) | 8 | hr(s) | 584 | hr(s) | 504 | hr(s) |
a1480 | span 4 strip bulkheads slab 1a | 8 | hr(s) | 8 | hr(s) | 584 | hr(s) | 504 | hr(s) |
a1580 | span 6 install rebar x-beam/ stem | 32 | hr(s) | 32 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a1620 | span 6 install pt duct & trumpets | 32 | hr(s) | 32 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a1510 | span 6 rebar bottom slab | 32 | hr(s) | 32 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2130 | span 4 form stem walls 2a | 64 | hr(s) | 64 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2240 | span 4 form diahphragms 2a | 24 | hr(s) | 24 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2270 | span 4 pour stems/ diaphragms 2a | 8 | hr(s) | 8 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2300 | span 4 strip stems / diahphragms 2a | 16 | hr(s) | 16 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2350 | span 4 f/r stem walls /x-beam 2b | 16 | hr(s) | 16 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2360 | span 4 pour stem walls/x-beam 2b | 8 | hr(s) | 8 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2540 | span 4-6 deck rebar | 120 | hr(s) | 120 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2630 | span 4-6 setup bidwell / dry run (4-6) | 24 | hr(s) | 24 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2740 | span 4-6 pour deck | 8 | hr(s) | 8 | hr(s) | 208 | hr(s) | 144 | hr(s) |
a2770 | span 4-6 cure deck | 80 | hr(s) | 80 | hr(s) | 208 | hr(s) | 144 | hr(s) |
a2860 | span 4-6 post tensioning & blockouts | 80 | hr(s) | 80 | hr(s) | 208 | hr(s) | 144 | hr(s) |
a2990 | span 4-6 strip deck | 80 | hr(s) | 80 | hr(s) | 392 | hr(s) | 328 | hr(s) |
a3240 | span 4-6 finish work | 480 | hr(s) | 480 | hr(s) | 4040 | hr(s) | 1336 | hr(s) |
a2370 | span 4 strip stem walls / x-beam 2b | 40 | hr(s) | 40 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2430 | span 4 form deck/ overhang/eod | 80 | hr(s) | 80 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2870 | span 4-6 bridge rail curb | 160 | hr(s) | 160 | hr(s) | 352 | hr(s) | 288 | hr(s) |
a3060 | span 4-6 falsework removal | 120 | hr(s) | 120 | hr(s) | 392 | hr(s) | 328 | hr(s) |
a1390 | span 9 pour stem walls/x-beam 2b | 8 | hr(s) | 8 | hr(s) | 328 | hr(s) | 0 | hr(s) |
a1400 | span 9 strip stem walls / x-beam 2b | 16 | hr(s) | 16 | hr(s) | 328 | hr(s) | 0 | hr(s) |
a1420 | span 9 form deck/ overhang/eod | 80 | hr(s) | 80 | hr(s) | 328 | hr(s) | 0 | hr(s) |
a2110 | span 7-9 deck rebar | 120 | hr(s) | 120 | hr(s) | 208 | hr(s) | 144 | hr(s) |
a2340 | span 7-9 setup bidwell / dry run (4-6) | 24 | hr(s) | 24 | hr(s) | 208 | hr(s) | 144 | hr(s) |
a2480 | span 7-9 pour deck | 24 | hr(s) | 24 | hr(s) | 208 | hr(s) | 144 | hr(s) |
a2520 | span 7-9 cure deck | 80 | hr(s) | 80 | hr(s) | 208 | hr(s) | 144 | hr(s) |
a2590 | span 7-9 post tensioning & blockouts | 80 | hr(s) | 80 | hr(s) | 208 | hr(s) | 144 | hr(s) |
a2670 | span 7-9 strip deck | 80 | hr(s) | 80 | hr(s) | 640 | hr(s) | 576 | hr(s) |
a2680 | span 7-9 pt closure (pour with span 4-6) | 80 | hr(s) | 80 | hr(s) | 208 | hr(s) | 144 | hr(s) |
a2900 | span 7-9 finish work | 480 | hr(s) | 480 | hr(s) | 4288 | hr(s) | 1584 | hr(s) |
a2750 | span 7-9 falsework removal | 120 | hr(s) | 120 | hr(s) | 640 | hr(s) | 576 | hr(s) |
a2760 | span 7-9 closure pour cure | 80 | hr(s) | 80 | hr(s) | 520 | hr(s) | 456 | hr(s) |
a2720 | form/strip f-rail (span 7-9) | 152 | hr(s) | 152 | hr(s) | 440 | hr(s) | 296 | hr(s) |
a3030 | f-rail class 1 finish (span 7-9) | 120 | hr(s) | 120 | hr(s) | 440 | hr(s) | 296 | hr(s) |
a3310 | install 3 tube railing (span 1-6) | 160 | hr(s) | 160 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a2310 | remove work bridge/containment | 40 | hr(s) | 40 | hr(s) | 1096 | hr(s) | 1032 | hr(s) |
a3230 | concrete slope paving | 48 | hr(s) | 48 | hr(s) | 6616 | hr(s) | 1704 | hr(s) |
a2790 | ac shoulders | 0 | hr(s) | 0 | hr(s) | 544 | hr(s) | 880 | hr(s) |
a3340 | switch sb traffic onto new sb bridge | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a2500 | install crcp pavement | 160 | hr(s) | 160 | hr(s) | 544 | hr(s) | 880 | hr(s) |
a3330 | sb bridge ready for sb traffic | 0 | hr(s) | 0 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a2800 | install conc. shldr. barrier | 24 | hr(s) | 24 | hr(s) | 544 | hr(s) | 880 | hr(s) |
a3410 | nb demo detour span 1 | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3430 | nb demo detour span 2 (new bnt. 2) | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a2950 | place/cure 42 f-rail (span 7-9) | 56 | hr(s) | 56 | hr(s) | 440 | hr(s) | 296 | hr(s) |
a2880 | install temp. bridge drainage system | 160 | hr(s) | 160 | hr(s) | 512 | hr(s) | 448 | hr(s) |
a3190 | slope paving curbs | 40 | hr(s) | 40 | hr(s) | 6616 | hr(s) | 1704 | hr(s) |
a1340 | finish work | 80 | hr(s) | 80 | hr(s) | 1528 | hr(s) | 1384 | hr(s) |
a3440 | nb demo detour span 3 (river) | 80 | hr(s) | 80 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3530 | nb demo detour span 4 (river) | 80 | hr(s) | 80 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3630 | nb demo detour span 7 (river) | 80 | hr(s) | 80 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3680 | nb demo detour span 8 (river) | 80 | hr(s) | 80 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3720 | nb demo detour span 9 (new bnt. 4) | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a4220 | nb demo detour span 11 | 40 | hr(s) | 40 | hr(s) | 864 | hr(s) | 120 | hr(s) |
a3760 | nb demo detour span 10 | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a2830 | install guardrail | 16 | hr(s) | 16 | hr(s) | 688 | hr(s) | 1024 | hr(s) |
a4160 | nb demo detour span 12 | 40 | hr(s) | 40 | hr(s) | 864 | hr(s) | 120 | hr(s) |
a4080 | nb demo detour span 13 | 40 | hr(s) | 40 | hr(s) | 864 | hr(s) | 120 | hr(s) |
a3880 | nb demo detour span 16 (pre-cast) | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3840 | nb demo deotur span 17 | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3550 | nb demo detour span 5 (river) (new bnt. 3) | 80 | hr(s) | 80 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3600 | nb demo detour span 6 (river) | 80 | hr(s) | 80 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a3990 | nb demo detour span 14 | 40 | hr(s) | 40 | hr(s) | 864 | hr(s) | 120 | hr(s) |
a3930 | nb demo detour span 15 (rr pre-cast) | 40 | hr(s) | 40 | hr(s) | 152 | hr(s) | 0 | hr(s) |
a2840 | install perm. signing | 160 | hr(s) | 160 | hr(s) | 544 | hr(s) | 880 | hr(s) |
a4060 | nbbb bent 1 structure excavation | 16 | hr(s) | 16 | hr(s) | 2264 | hr(s) | 56 | hr(s) |
a4090 | nbbb bent 1 driven pile | 40 | hr(s) | 40 | hr(s) | 2264 | hr(s) | 56 | hr(s) |
a1350 | install concr. shldr. barrier | 8 | hr(s) | 8 | hr(s) | 1640 | hr(s) | 0 | hr(s) |
a4170 | nbbb bent 1 cap | 80 | hr(s) | 80 | hr(s) | 2264 | hr(s) | 56 | hr(s) |
a4280 | nbbb bent 1 back wall - f/p/s | 80 | hr(s) | 80 | hr(s) | 3008 | hr(s) | 200 | hr(s) |
a2250 | install crcp pavement | 160 | hr(s) | 160 | hr(s) | 544 | hr(s) | 880 | hr(s) |
a4480 | nbbb bent 1 wingwalls | 80 | hr(s) | 80 | hr(s) | 3008 | hr(s) | 200 | hr(s) |
a2640 | install conc. shldr. barrier | 16 | hr(s) | 16 | hr(s) | 832 | hr(s) | 1168 | hr(s) |
a3770 | nbbb bent 2 structure exc | 24 | hr(s) | 24 | hr(s) | 200 | hr(s) | 56 | hr(s) |
a2510 | install term. exp. joint | 120 | hr(s) | 120 | hr(s) | 832 | hr(s) | 1168 | hr(s) |
a3830 | nbbb bent 2 cofferdam & driller access | 160 | hr(s) | 160 | hr(s) | 200 | hr(s) | 56 | hr(s) |
a2600 | pave ac shoulders | 40 | hr(s) | 40 | hr(s) | 832 | hr(s) | 1168 | hr(s) |
a3360 | temp. paving / drainage - south end | 120 | hr(s) | 120 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a4070 | nbbb bent 2 drilled shafts #1 | 112 | hr(s) | 112 | hr(s) | 200 | hr(s) | 80 | hr(s) |
a4250 | nbbb bent 2 csl testing | 24 | hr(s) | 24 | hr(s) | 200 | hr(s) | 80 | hr(s) |
a4290 | nbbb bent 2 arch seats | 120 | hr(s) | 120 | hr(s) | 200 | hr(s) | 80 | hr(s) |
a4550 | nbbb bent 2 columns | 120 | hr(s) | 120 | hr(s) | 200 | hr(s) | 120 | hr(s) |
a3380 | establish traffic control measures | 40 | hr(s) | 40 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a4260 | nbbb bent 3 drilled shafts #1 | 56 | hr(s) | 56 | hr(s) | 784 | hr(s) | 144 | hr(s) |
a4370 | nbbb bent 3 csl testing | 24 | hr(s) | 24 | hr(s) | 784 | hr(s) | 144 | hr(s) |
a4560 | nbbb bent 3 arch seats | 160 | hr(s) | 160 | hr(s) | 720 | hr(s) | 80 | hr(s) |
a3790 | nbbb bent 5 install shoring | 40 | hr(s) | 40 | hr(s) | 1064 | hr(s) | 320 | hr(s) |
a3850 | nbbb bent 5 structure excavation | 40 | hr(s) | 40 | hr(s) | 1312 | hr(s) | 440 | hr(s) |
a4380 | nbbb bent 5 drilled shafts#1 | 56 | hr(s) | 56 | hr(s) | 1040 | hr(s) | 168 | hr(s) |
a4500 | nbbb bent 5 csl testing | 24 | hr(s) | 24 | hr(s) | 1040 | hr(s) | 168 | hr(s) |
a4490 | nbbb bent 6 csl testing | 24 | hr(s) | 24 | hr(s) | 840 | hr(s) | 96 | hr(s) |
a4520 | nbbb bent 6 columns | 80 | hr(s) | 80 | hr(s) | 840 | hr(s) | 96 | hr(s) |
a3780 | nbbb bent 4 drilled shafts #2 | 112 | hr(s) | 112 | hr(s) | 112 | hr(s) | 104 | hr(s) |
a3920 | nbbb bent 4 csl testing | 24 | hr(s) | 24 | hr(s) | 1184 | hr(s) | 544 | hr(s) |
a4680 | nbbb bent 5 columns | 80 | hr(s) | 80 | hr(s) | 968 | hr(s) | 96 | hr(s) |
a4330 | nbbb bent 6 drilled shafts #1 | 56 | hr(s) | 56 | hr(s) | 840 | hr(s) | 96 | hr(s) |
a4130 | nbbb bent 7 install shoring | 40 | hr(s) | 40 | hr(s) | 176 | hr(s) | 96 | hr(s) |
a4210 | nbbb bent 7 strucutre excavation | 16 | hr(s) | 16 | hr(s) | 176 | hr(s) | 96 | hr(s) |
a4230 | nbbb bent 7 drilled shafts #1 | 56 | hr(s) | 56 | hr(s) | 176 | hr(s) | 96 | hr(s) |
a4340 | nbbb bent 7 csl testing | 24 | hr(s) | 24 | hr(s) | 176 | hr(s) | 168 | hr(s) |
a4030 | nbbb bent 8 install shoring | 40 | hr(s) | 40 | hr(s) | 152 | hr(s) | 96 | hr(s) |
a4120 | nbbb bent 8 structre excavation | 16 | hr(s) | 16 | hr(s) | 152 | hr(s) | 96 | hr(s) |
a4140 | nbbb bent 8 drilled shafts #2 | 56 | hr(s) | 56 | hr(s) | 152 | hr(s) | 144 | hr(s) |
a4240 | nbbb bent 8 csl testing | 24 | hr(s) | 24 | hr(s) | 152 | hr(s) | 144 | hr(s) |
a4270 | nbbb bent 8 f/p/s footing | 64 | hr(s) | 64 | hr(s) | 152 | hr(s) | 144 | hr(s) |
a4530 | nbbb bent 8 columns | 80 | hr(s) | 80 | hr(s) | 104 | hr(s) | 96 | hr(s) |
a4000 | nbbb bent 9 driller access | 16 | hr(s) | 16 | hr(s) | 152 | hr(s) | 96 | hr(s) |
a4040 | nbbb bent 9 drilled shafts #2 | 56 | hr(s) | 56 | hr(s) | 152 | hr(s) | 144 | hr(s) |
a4420 | nbbb bent 7 f/p/s footing | 64 | hr(s) | 64 | hr(s) | 168 | hr(s) | 160 | hr(s) |
a4690 | nbbb bent 7 columns | 80 | hr(s) | 80 | hr(s) | 104 | hr(s) | 96 | hr(s) |
a4150 | nbbb bent 9 csl testing | 24 | hr(s) | 24 | hr(s) | 192 | hr(s) | 184 | hr(s) |
a4350 | nbbb bent 9 column | 80 | hr(s) | 80 | hr(s) | 104 | hr(s) | 96 | hr(s) |
a3940 | nbbb bent 10 drilled shafts #2 | 56 | hr(s) | 56 | hr(s) | 104 | hr(s) | 96 | hr(s) |
a4050 | nbbb bent 10 csl testing | 24 | hr(s) | 24 | hr(s) | 104 | hr(s) | 96 | hr(s) |
a4100 | nbbb bent 10 f/p/s footings | 64 | hr(s) | 64 | hr(s) | 104 | hr(s) | 96 | hr(s) |
a4200 | nbbb bent 10 column | 80 | hr(s) | 80 | hr(s) | 104 | hr(s) | 96 | hr(s) |
a3890 | nbbb bent 11 structure exc | 40 | hr(s) | 40 | hr(s) | 192 | hr(s) | 136 | hr(s) |
a4620 | nbbb bent 11 drive pile | 40 | hr(s) | 40 | hr(s) | 2728 | hr(s) | 80 | hr(s) |
a4300 | span 1 falsework | 160 | hr(s) | 160 | hr(s) | 2264 | hr(s) | 56 | hr(s) |
a4630 | span 1 precast trans beams | 24 | hr(s) | 24 | hr(s) | 2264 | hr(s) | 56 | hr(s) |
a4700 | span 1 t-beams | 120 | hr(s) | 120 | hr(s) | 2264 | hr(s) | 56 | hr(s) |
a3570 | nbaa bent 1 structure excavation | 16 | hr(s) | 16 | hr(s) | 624 | hr(s) | 24 | hr(s) |
a3580 | nbaa bent 1 pile | 40 | hr(s) | 40 | hr(s) | 624 | hr(s) | 24 | hr(s) |
a2650 | install crcp term. exp. joint | 120 | hr(s) | 120 | hr(s) | 544 | hr(s) | 880 | hr(s) |
a3620 | nbaa bent 1 cap | 80 | hr(s) | 80 | hr(s) | 624 | hr(s) | 24 | hr(s) |
a3640 | nbaa bent 1 cure cap | 80 | hr(s) | 80 | hr(s) | 704 | hr(s) | 104 | hr(s) |
a3650 | nbaa mse wall #21315 | 80 | hr(s) | 80 | hr(s) | 1000 | hr(s) | 400 | hr(s) |
a3690 | nbaa bent 1 backfill | 32 | hr(s) | 32 | hr(s) | 1016 | hr(s) | 416 | hr(s) |
a3590 | nbaa bent 2 structure excavation | 16 | hr(s) | 16 | hr(s) | 688 | hr(s) | 88 | hr(s) |
a3610 | nbaa bent 2 pile | 40 | hr(s) | 40 | hr(s) | 688 | hr(s) | 88 | hr(s) |
a3660 | nbaa bent 2 cap | 80 | hr(s) | 80 | hr(s) | 624 | hr(s) | 24 | hr(s) |
a3700 | nbaa bent 2 cure cap | 80 | hr(s) | 80 | hr(s) | 624 | hr(s) | 24 | hr(s) |
a3710 | nbaa mse wall #21316 | 80 | hr(s) | 80 | hr(s) | 1000 | hr(s) | 400 | hr(s) |
a3740 | nbaa bent 2 backfill | 32 | hr(s) | 32 | hr(s) | 1000 | hr(s) | 400 | hr(s) |
a3750 | nbaa span 1 erect beams | 16 | hr(s) | 16 | hr(s) | 624 | hr(s) | 24 | hr(s) |
a3800 | nbaa span 1 diaphragms & end walls | 120 | hr(s) | 120 | hr(s) | 624 | hr(s) | 24 | hr(s) |
a3950 | nbaa span 1 form deck | 120 | hr(s) | 120 | hr(s) | 624 | hr(s) | 24 | hr(s) |
a4180 | nbaa span 1 pour deck | 8 | hr(s) | 8 | hr(s) | 624 | hr(s) | 24 | hr(s) |
a4190 | nbaa span 1 deck cure | 112 | hr(s) | 112 | hr(s) | 896 | hr(s) | 40 | hr(s) |
a4320 | nbaa bent 1 end panel | 64 | hr(s) | 64 | hr(s) | 624 | hr(s) | 24 | hr(s) |
a4450 | nbaa bent 2 end panel | 64 | hr(s) | 64 | hr(s) | 624 | hr(s) | 24 | hr(s) |
a4580 | nbaa span 1 bridge rail | 80 | hr(s) | 80 | hr(s) | 624 | hr(s) | 144 | hr(s) |
a3810 | close fn1 offramp | 0 | hr(s) | 0 | hr(s) | 4104 | hr(s) | 160 | hr(s) |
a3820 | obliterate roadway | 32 | hr(s) | 32 | hr(s) | 4360 | hr(s) | 384 | hr(s) |
a3960 | excavation/embankment | 160 | hr(s) | 160 | hr(s) | 4272 | hr(s) | 296 | hr(s) |
a3970 | construct dt6 ditch | 40 | hr(s) | 40 | hr(s) | 4312 | hr(s) | 336 | hr(s) |
a4010 | construct sw5 swale | 80 | hr(s) | 80 | hr(s) | 4312 | hr(s) | 336 | hr(s) |
a4110 | install drainage | 120 | hr(s) | 120 | hr(s) | 4232 | hr(s) | 336 | hr(s) |
a4310 | aggregate base | 32 | hr(s) | 32 | hr(s) | 4232 | hr(s) | 296 | hr(s) |
a4460 | permanent shoulder barrier | 24 | hr(s) | 24 | hr(s) | 5128 | hr(s) | 296 | hr(s) |
a4390 | ac base paving | 16 | hr(s) | 16 | hr(s) | 4232 | hr(s) | 296 | hr(s) |
a4400 | install temporary barrier | 16 | hr(s) | 16 | hr(s) | 4232 | hr(s) | 328 | hr(s) |
a4410 | temporary striping | 8 | hr(s) | 8 | hr(s) | 4248 | hr(s) | 296 | hr(s) |
a4430 | ac top lift paving - ramp | 16 | hr(s) | 16 | hr(s) | 3072 | hr(s) | 296 | hr(s) |
a3420 | work bridge | 160 | hr(s) | 160 | hr(s) | 728 | hr(s) | 24 | hr(s) |
a3520 | nbaa detour bridge removal | 160 | hr(s) | 160 | hr(s) | 624 | hr(s) | 24 | hr(s) |
a4440 | install perm. signing | 8 | hr(s) | 8 | hr(s) | 4232 | hr(s) | 328 | hr(s) |
a4510 | permanent striping | 8 | hr(s) | 8 | hr(s) | 5128 | hr(s) | 296 | hr(s) |
a3560 | install permanent drainage | 120 | hr(s) | 120 | hr(s) | 3968 | hr(s) | 880 | hr(s) |
a3490 | general excavation | 120 | hr(s) | 120 | hr(s) | 3968 | hr(s) | 880 | hr(s) |
a4470 | aggregate base | 120 | hr(s) | 120 | hr(s) | 3336 | hr(s) | 128 | hr(s) |
a3510 | embankment | 80 | hr(s) | 80 | hr(s) | 4008 | hr(s) | 920 | hr(s) |
a4590 | obliterate roadway | 40 | hr(s) | 40 | hr(s) | 3192 | hr(s) | 24 | hr(s) |
a4660 | general excavation | 160 | hr(s) | 160 | hr(s) | 3192 | hr(s) | 24 | hr(s) |
a3290 | project landscaping - sb | 480 | hr(s) | 480 | hr(s) | 3744 | hr(s) | 928 | hr(s) |
a4670 | embankment | 40 | hr(s) | 40 | hr(s) | 3312 | hr(s) | 144 | hr(s) |
a3670 | aggregate base | 120 | hr(s) | 120 | hr(s) | 4328 | hr(s) | 600 | hr(s) |
a3470 | embankment | 120 | hr(s) | 120 | hr(s) | 4328 | hr(s) | 600 | hr(s) |
a3730 | ac base paving | 80 | hr(s) | 80 | hr(s) | 4328 | hr(s) | 600 | hr(s) |
a3860 | perm concrete shoulder barrier | 40 | hr(s) | 40 | hr(s) | 4328 | hr(s) | 600 | hr(s) |
a4640 | ne soundwall ln1 655+00 | 200 | hr(s) | 200 | hr(s) | 4872 | hr(s) | 0 | hr(s) |
a3540 | install permanent drainage | 240 | hr(s) | 240 | hr(s) | 4328 | hr(s) | 600 | hr(s) |
a3450 | general excavation | 40 | hr(s) | 40 | hr(s) | 4328 | hr(s) | 600 | hr(s) |
a3900 | install permenant fencing | 80 | hr(s) | 80 | hr(s) | 4328 | hr(s) | 600 | hr(s) |
a3390 | switch nb traffic to sb bridge | 8 | hr(s) | 8 | hr(s) | 104 | hr(s) | 0 | hr(s) |
a4710 | nbbb bent 6 structure backfill | 56 | hr(s) | 56 | hr(s) | 840 | hr(s) | 120 | hr(s) |
a3870 | nbbb bent 6 install shoring | 40 | hr(s) | 40 | hr(s) | 1064 | hr(s) | 320 | hr(s) |
a3910 | nbbb bent 6 structure excavation | 40 | hr(s) | 40 | hr(s) | 1064 | hr(s) | 320 | hr(s) |
a1160 | span 4 rebar bottom slab | 32 | hr(s) | 32 | hr(s) | 296 | hr(s) | 192 | hr(s) |
a1410 | span 4 install pt duct | 24 | hr(s) | 24 | hr(s) | 336 | hr(s) | 0 | hr(s) |
a1360 | span 8 form stem walls 2a | 64 | hr(s) | 64 | hr(s) | 296 | hr(s) | 0 | hr(s) |
a1090 | span 7 form stem walls 2a | 64 | hr(s) | 64 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a3000 | 60 day cure for perm. expansion joint | 240 | hr(s) | 240 | hr(s) | 488 | hr(s) | 408 | hr(s) |
a1170 | span 4 rebar stems/x-beam | 32 | hr(s) | 32 | hr(s) | 336 | hr(s) | 256 | hr(s) |
a1430 | span 7 pour stem walls 2a | 8 | hr(s) | 8 | hr(s) | 240 | hr(s) | 0 | hr(s) |
a1440 | span 7 strip stems/diaphragms 2a | 16 | hr(s) | 16 | hr(s) | 368 | hr(s) | 272 | hr(s) |
a1140 | span 7 form diaphragms | 24 | hr(s) | 24 | hr(s) | 280 | hr(s) | 184 | hr(s) |
a1370 | span 5 pour bottom slab 1a | 8 | hr(s) | 8 | hr(s) | 536 | hr(s) | 0 | hr(s) |
a1770 | span 6 pour bottom slab 1a | 8 | hr(s) | 8 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a1380 | span 5 strip bulkheads 1a | 8 | hr(s) | 8 | hr(s) | 768 | hr(s) | 0 | hr(s) |
a1780 | span 6 strip bulkheads 1a | 8 | hr(s) | 8 | hr(s) | 584 | hr(s) | 488 | hr(s) |
a1920 | span 5 form stems 2a | 64 | hr(s) | 64 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a1790 | span 6 form stems 2a | 64 | hr(s) | 64 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2040 | span 5 form diaphragms | 24 | hr(s) | 24 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a1880 | span 6 form diaphragms | 24 | hr(s) | 24 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2060 | span 5 pour stems/diaphragms 2a | 8 | hr(s) | 8 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a1890 | span 6 pour stems/diaphragms 2a | 8 | hr(s) | 8 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2120 | span 5 strip stems/diaphragms 2a | 16 | hr(s) | 16 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a1900 | span 6 strip stems/diahpragms 2a | 16 | hr(s) | 16 | hr(s) | 240 | hr(s) | 144 | hr(s) |
a2140 | span 5 form stems/x-beam 2b | 16 | hr(s) | 16 | hr(s) | 376 | hr(s) | 280 | hr(s) |
a1930 | span 6 form stems/x-beam 2b | 16 | hr(s) | 16 | hr(s) | 488 | hr(s) | 392 | hr(s) |
a1560 | span 5 pour bottom slab 1b | 8 | hr(s) | 8 | hr(s) | 680 | hr(s) | 600 | hr(s) |
a1800 | span 6 pour bottom slab 1b | 8 | hr(s) | 8 | hr(s) | 584 | hr(s) | 488 | hr(s) |
a2150 | span 5 pour stems/x-beam 2b | 8 | hr(s) | 8 | hr(s) | 376 | hr(s) | 280 | hr(s) |
a2000 | span 6 pour stems/x-beam 2b | 8 | hr(s) | 8 | hr(s) | 488 | hr(s) | 392 | hr(s) |
a2190 | span 5 form deck/overhang | 80 | hr(s) | 80 | hr(s) | 376 | hr(s) | 280 | hr(s) |
a2030 | span 6 form deck/overhang | 80 | hr(s) | 80 | hr(s) | 488 | hr(s) | 392 | hr(s) |
a2180 | span 5 strip stems/x-beam 2b | 16 | hr(s) | 16 | hr(s) | 376 | hr(s) | 280 | hr(s) |
a2010 | span 6 strip stems/x-beam 2b | 16 | hr(s) | 16 | hr(s) | 488 | hr(s) | 392 | hr(s) |
a1450 | bent 7 pt strip blockouts | 40 | hr(s) | 40 | hr(s) | 240 | hr(s) | 144 | hr(s) |