comments on: how primavera calendars change durations – and what to do about it - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/primavera-calendars-change-durations/ project controls training & courses fri, 12 jan 2024 16:05:23 +0000 hourly 1 by: netasnet abera //www.deco-dalles.com/primavera-calendars-change-durations/#comment-101218 tue, 18 apr 2023 13:57:59 +0000 //www.deco-dalles.com/?p=1804#comment-101218 my problem in my p6 original duration of the project is different from finish date of the project ,how can i correct it

]]>
by: sid //www.deco-dalles.com/primavera-calendars-change-durations/#comment-99745 fri, 10 feb 2023 14:41:25 +0000 //www.deco-dalles.com/?p=1804#comment-99745 question:
let’s say, i also want to keep start and finish date same for activities after changing calendar. so, in the example in video, would the multiplying factor be 1.8 in global change?
(72/40 = 1.8)?

thank you for useful videos!

]]>
by: sid //www.deco-dalles.com/primavera-calendars-change-durations/#comment-99744 fri, 10 feb 2023 14:40:55 +0000 //www.deco-dalles.com/?p=1804#comment-99744 question:
let’s say, i also want to keep start and finish date same for activities after changing calendar. so, in the example in video, would the multiplying factor be 1.8 in global change?
(72/40 = 1.8)?

thank you for useful videos!

]]>
by: ahmad //www.deco-dalles.com/primavera-calendars-change-durations/#comment-95947 tue, 11 oct 2022 23:25:10 +0000 //www.deco-dalles.com/?p=1804#comment-95947 i have used this method for the duration and it went as you explained in this tutorial but the lags of my activities have changed? is there any method to update those automatically as well?

]]>
by: ali //www.deco-dalles.com/primavera-calendars-change-durations/#comment-95446 tue, 27 sep 2022 12:11:14 +0000 //www.deco-dalles.com/?p=1804#comment-95446 hello
i had a problem that i wanted you to help me with
in the schedule that i have prepared, when i change the calendar of the program in the middle of the project and disable months, in other systems this change is not displayed and the initial calendar of the program is shown, which reduces the weight and time of each activity. is it possible to help me understand where the problem comes from?

]]>
by: nowfal //www.deco-dalles.com/primavera-calendars-change-durations/#comment-78880 tue, 21 jul 2020 12:51:04 +0000 //www.deco-dalles.com/?p=1804#comment-78880 in reply to sudhar.

hi sudha,

it may be 21 jun 20 is sunday as holyday in your calendar.

]]>
by: sudhar //www.deco-dalles.com/primavera-calendars-change-durations/#comment-78436 fri, 26 jun 2020 23:19:15 +0000 //www.deco-dalles.com/?p=1804#comment-78436 hi there, thanks for the blog and it is really informative and useful. i have a quick question. trust you could help.

in p6, i have used 12hr 7day work week calendar 6.00 am to 5.00 pm (with 1 hour break so productivity is 11 hrs per day). so when i add a new activity in the schedule with 1 day duration, it shows correctly as i.e duration 1 | start 20-jun-20 6.00 am | end 20-jun-20 5.00 pm. which is correct, however, we i increase the duration to 2 days (or more), it shows me as duration 2 | start 20-jun-20 6.00 am | end 22-jun-20 8.00 am. i’m confused. any idea why is that? ideally it should be (if it is 2 day duration) start 20-jun-20 6.00 am | end 21-jun-20 5.00 pm right?

appreciate your support and response. big help.

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-78150 tue, 09 jun 2020 16:36:21 +0000 //www.deco-dalles.com/?p=1804#comment-78150 in reply to srinu.

it can be for a few different reasons. i would suggest you fix all activities to start at the same time of day.

]]>
by: srinu //www.deco-dalles.com/primavera-calendars-change-durations/#comment-78053 wed, 03 jun 2020 11:12:59 +0000 //www.deco-dalles.com/?p=1804#comment-78053 i observed in my start date the time of the day showing different timings instead of starts with 08:00 hrs for few activities.. is this because of using different calendars? in a same project….can help to resolve this.

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-77626 wed, 13 may 2020 17:48:23 +0000 //www.deco-dalles.com/?p=1804#comment-77626 in reply to sarah.

you’re welcome!

]]>
by: sarah //www.deco-dalles.com/primavera-calendars-change-durations/#comment-77615 wed, 13 may 2020 06:19:15 +0000 //www.deco-dalles.com/?p=1804#comment-77615 in reply to michael lepage.

thanks a lot for your quick response michael.
actually there are not partial durations : however, the summerized original duration in case of 8hr/5day calender related actvities are partial at wbs level since the project default calendar is 24hr/7day. moreover, the partial caculations can be seen only for total float and free float of activities having 8hr/5day calender.
also, i set calendar time periods according to employer request and general specifaction documents so i do not think it would be possible to change those settings.
again thank you so much michael. thanks to you i could improve a lot and learn new things.

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-77599 tue, 12 may 2020 15:53:53 +0000 //www.deco-dalles.com/?p=1804#comment-77599 in reply to sarah.

sarah, this is not a good approach. since you are using 2 different calendars, you would definitely expect to see partial total float & partial free float. these shouldn’t be a concern for you – why would they be a problem?
you can easily correct your partial durations however, but checking your calendar time periods are properly set before you enter in durations.
i would advise you to remove those lags – lags are not encouraged in schedules as they are often used to “hide” time.

]]>
by: sarah //www.deco-dalles.com/primavera-calendars-change-durations/#comment-77590 tue, 12 may 2020 04:40:24 +0000 //www.deco-dalles.com/?p=1804#comment-77590 hello micheal,
many thanks for your post.
i have to use multiple calenders (8hr/5day and 24hr/7day) assigned to different activities in different wbs levels. so when i link the activities, primavera calculates the free float total float and orginal duration in decimal numbers. i have tried to slove this problem by assiging lead/lag or setting the start date of each calender the same hour (starts at 8 am). although it gave me the exact number, i am not sure if it is correct to solve the problem by using lead or non-logical working hours. i would appreciate it if you could help me with this.
thanks

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-75712 fri, 27 sep 2019 16:31:57 +0000 //www.deco-dalles.com/?p=1804#comment-75712 in reply to rahul.

rahul,
this is a very complex question and i just can’t answer it here in a comment.

]]>
by: rahul //www.deco-dalles.com/primavera-calendars-change-durations/#comment-75706 fri, 27 sep 2019 07:23:03 +0000 //www.deco-dalles.com/?p=1804#comment-75706 hi,
i have an activity of 180d duration and calendar is 7dx8hrs. i have put a resource whose budgeted quantity is 10000. i set my budgeted quantity it every month in my resource assignment, like 1st-month 1500,2nd month 1200 etc.when i schedule my activity for 1st month and add my target (1000boq). if i can’t achieve my target(500boq), then my activity should be delayed to around 10 to 11 days, but my activity showing 1-month delay. please tell me how to fix.

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-75285 fri, 24 may 2019 13:23:20 +0000 //www.deco-dalles.com/?p=1804#comment-75285 in reply to tanvir.

it’s a manual effort that way – you’ll have to create 4 世界杯时间比赛时间 , and assign them to activities individually.
another way is to create 1 resource, with a max units/time of say %400 (ie 4 世界杯时间比赛时间 of this type) and then to assign to activities. this way provides more flexibility if the 4 lathes are all identical.

]]>
by: tanvir //www.deco-dalles.com/primavera-calendars-change-durations/#comment-75255 thu, 16 may 2019 21:34:38 +0000 //www.deco-dalles.com/?p=1804#comment-75255 michael:
suppose i have 4 lathe machines r4=lathe (l1, l2,l3, l4) i would like p6 to assign each of these like l1,l2,l3,l4 and then again l1,l2,l3,l4 but it does not do that. is there a way to make p6 do that?

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-75226 wed, 01 may 2019 21:31:28 +0000 //www.deco-dalles.com/?p=1804#comment-75226 in reply to tanvir.

ah, i see where you’re going now.
p6 isn’t a great tool for managing individual work assignments in this way. it was designed more to schedule a pool of 世界杯时间比赛时间 . like this:
if you have 7qc 世界杯时间比赛时间 who work 10hr/d, then for r-1, you set the max units/time field (see units & prices tab) to 70hr/d. this is how you represent your capacity to accomplish work (ie: the number of 世界杯时间比赛时间 of type qc).
assign r-1 to activities as you normally would, schedule the project of course.
on the resource assignments tab, with some finnagleing, you’ll be able to see what activities & days you have work assigned, and how many hr/d you need.

]]>
by: tanvir //www.deco-dalles.com/primavera-calendars-change-durations/#comment-75203 fri, 26 apr 2019 16:54:14 +0000 //www.deco-dalles.com/?p=1804#comment-75203 appreciate the response.
lets say i have a total of 7 qc 世界杯时间比赛时间 and i have more that 50 qc tasks . on the 世界杯时间比赛时间 tab i have r-1 as qc. how would p6 will schedule those 世界杯时间比赛时间 and how will i need to set this up.
working 10h/d 6 days a week (6x10s)
i want to see this on the assignments tab. so i can tell them which days they r going to work on which job. same question for non-labor 世界杯时间比赛时间 (7×24)
thanks
tanvir

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-75195 thu, 25 apr 2019 18:27:17 +0000 //www.deco-dalles.com/?p=1804#comment-75195 in reply to tanvir.

tanvir. the field “budgeted units / time” won’t summarize or roll-up to a bar. the only way i could find to see the 30hr/d is on the resource usage graph with the timescale set to “week/day”.
however, you could try this. rather than assign 3 different q/c 世界杯时间比赛时间 , or even the same q/c resource 3 times on an activity, try assigning that resource just once to the activity. then you can set “budgeted units / time” to 30hr/d.
see here: https://www.screencast.com/t/bppmr2pddx

]]>
by: tanvir //www.deco-dalles.com/primavera-calendars-change-durations/#comment-75194 thu, 25 apr 2019 16:22:11 +0000 //www.deco-dalles.com/?p=1804#comment-75194 if i am adding 3 q/c 世界杯时间比赛时间 on a job and each is working 10 h/d 6 days a week, so that is in total 30 h/d for that particular task. i have changed my calendar to 6x10s, default units/time set as 10 h/d & max unit/time 12 h/d. i would like to see that 30h/d, it that possible for p6 to show that. right now it is not showing that.
thanks
tan

]]>
by: mj //www.deco-dalles.com/primavera-calendars-change-durations/#comment-74924 wed, 06 feb 2019 20:03:56 +0000 //www.deco-dalles.com/?p=1804#comment-74924 hi all! just wanted to share another workaround:
1. export 8hrs version’s activity id’s & original durations to excel
2. change the schedule calendar to 10hrs in p6
3. export 10hrs version’s activity id’s & original durations to excel
4. use ‘vlookup’ formula in excel to replace new durations with the original ones
5. import 10hrs version back to p6

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-74903 wed, 30 jan 2019 14:35:51 +0000 //www.deco-dalles.com/?p=1804#comment-74903 in reply to segun.

hi segun,
in truth, i’m not sure what the standard is. nowadays, i tend to use 22 working days in a month, sometimes 21.5. but of course, it depends on what country you are in and what industry. here’s a link to some discussion about it: https://www.quora.com/what-is-the-average-amount-of-work-days-in-a-month

]]>
by: segun //www.deco-dalles.com/primavera-calendars-change-durations/#comment-74844 sat, 26 jan 2019 12:33:01 +0000 //www.deco-dalles.com/?p=1804#comment-74844 hello micheal,

many thanks for your post. it is indeed very helpful. my start and finish times became distorted and i became confused. your video helped me solved it even before i finish watching it. i will like post my solution here for others who might perhaps be facing the same problem to benefit from…

===

when the start and finish times of activities in a schedule are distorted. it may be that you’ve changed calendar or hours of work per day or thereabout.
you need to first solve this problem by going to your calendar, click on detailed work hours/day radio button, then click on modify => workweek to set your work hours. and then click on time periods to set it as well.
then go to the user preferences => time units and under the durations format, change the unit of time from day to hour and close the form.
then reschedule the project, your original durations column will show you the hours for each activity, however, that might be wrong. in order to really know the correct hours primavera is using to calculate each day, type in 1d and click enter. you will then see the correct hours primavera is using to calculate each day. enter 1d for all the activities and reschedule the project, you will see that the start and finish times will be corrected to suit the time you set in the calendar’s ‘detailed work hours/day’.
now, go back to the user preferences => time units and under the durations format, change the unit of time from hour to day and close the form.

===

however, micheal, please how can i calculate the time periods without any mistake, i saw in your video that you used 12 – 72 – 288 – 3744 for a 12-hour x 6 day workweek. my own calculation is 12 – 72 – 312 – 3744. yours has 24 working days in a week while mine has 26 working days in a month. can you please explain how you calculated yours. i just want to make sure i’m following the right standard.

thank you very much.

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-60701 tue, 19 jun 2018 14:56:25 +0000 //www.deco-dalles.com/?p=1804#comment-60701 in reply to pbell.

it’s only in older versions of p6 that global calendars are used to calculate the duration shown on wbs lines. i’m not sure when it changed, but i think v8 and up.
now it’s the project’s default calendar that is used (listed on the defaults tab of the project).

]]>
by: pbell //www.deco-dalles.com/primavera-calendars-change-durations/#comment-59479 fri, 01 jun 2018 20:42:18 +0000 //www.deco-dalles.com/?p=1804#comment-59479 has anyone found a way to “turn off” global calendars for overall (i.e. wbs and gantt chart) calculations/printing? my users get confused and frustrated when i try to explain why duration’s adhere to the global calendar selected not their project one. it is to the point they hate the tool and are reluctant to use it. i understand why they are there, but for a lot of us projects may share cost, 世界杯时间比赛时间 , but not necessarily calendars.

i am unable to give users access to change the global calendar – they would go in and change things without a second thought . they have to contact me prior to printing to change the default global calendar.

has anyone approached oracle to get a change incorporated to fix this? much like critical path (defined float days vs. longest path), in the project settings something like “use global or project calendar to display overall duration”. i am familiar with the schema it would seem not take that much to point from a global to a “default” project calendar for calculations. thanks.

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-59213 mon, 28 may 2018 20:32:47 +0000 //www.deco-dalles.com/?p=1804#comment-59213 in reply to soud.

i’m sorry soud, but i can’t think of how you can accomplish this in p6. it’s the reverse of what p6 does. in p6, you enter durations, and the cpm scheduling algorithm calculates the dates.

]]>
by: soud //www.deco-dalles.com/primavera-calendars-change-durations/#comment-59192 mon, 28 may 2018 12:27:46 +0000 //www.deco-dalles.com/?p=1804#comment-59192 i have a problem that i’m unable to find a solution for. maybe i don’t know the keywords.
so, i have the finish dates of activities, and the start date of the project. i would like primavera to calculate the duration from start to finish of each activity. it may not sound it’s good practice but i need to import the start and finish dates and have primavera calculate the duration rather than me giving the duration.
please help as this is getting frustrating.

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-51600 mon, 20 nov 2017 14:39:41 +0000 //www.deco-dalles.com/?p=1804#comment-51600 in reply to roma.

you are welcome.

]]>
by: roma //www.deco-dalles.com/primavera-calendars-change-durations/#comment-51570 mon, 20 nov 2017 05:36:14 +0000 //www.deco-dalles.com/?p=1804#comment-51570 in reply to michael lepage.

helped faster, thanks michael

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-51541 sun, 19 nov 2017 19:06:53 +0000 //www.deco-dalles.com/?p=1804#comment-51541 in reply to roma.

those activities are start milestones so they don’t have finish dates.

]]>
by: roma //www.deco-dalles.com/primavera-calendars-change-durations/#comment-51521 sun, 19 nov 2017 12:39:40 +0000 //www.deco-dalles.com/?p=1804#comment-51521 in reply to michael lepage.

hi michael, in the video there are empty cells under the finish column, may i know how to leave it blank?

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-41239 tue, 01 nov 2016 16:28:44 +0000 //www.deco-dalles.com/?p=1804#comment-41239 in reply to najam uddin.

hi najam,
yes, that’s one way to approach it. just to be clear, a global change cannot be applied to a calendar as you say – only to the project’s activities to alter the durations.

]]>
by: najam uddin //www.deco-dalles.com/primavera-calendars-change-durations/#comment-41210 sun, 30 oct 2016 04:26:50 +0000 //www.deco-dalles.com/?p=1804#comment-41210 in reply to michael lepage.

hi michael,

i think rohit does not want to change user preference and keep both 8 hrs and 22 hrs calendars. i will suggest to make a global change and multiply original duration of 22 hrs calendar by 0.3636, which comes from 8/22.

this golbal change should not be applied to a global calendar but project calendar, otherwise whoever will be using global calendar will change duration in their schedules too, what do you suggest michael?

]]>
by: binodprusty //www.deco-dalles.com/primavera-calendars-change-durations/#comment-41159 mon, 24 oct 2016 10:20:06 +0000 //www.deco-dalles.com/?p=1804#comment-41159 hi,
while scheduling the independent activity start date is changing from the date i have kept to the project start date. example: my project start date is 15 sep 2016 and i have put an independent activity start date as 30 oct 2016. while scheduling the activity start date is changing automatically to 15 sep 2016. but i need to keep the activity start date as 30 oct 2016. kindly help

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-40747 wed, 21 sep 2016 13:56:26 +0000 //www.deco-dalles.com/?p=1804#comment-40747 in reply to rajesh ponnaiah.

rajesh,
there is nowhere to set a default start time for an activity. often the start time is set based on the finish time of the predecessor. two things to look at that might be influencing the start hours.
1) the data date – what is the time for the data date? your start time might be picking up 0:00 from the data date.
2) the project’s start date (& time) on the project screen->dates tab. look at the hours set there as well.
correct these, correct predecessor finish time and you should get back on track.

]]>
by: rajesh ponnaiah //www.deco-dalles.com/primavera-calendars-change-durations/#comment-40707 sun, 18 sep 2016 05:53:53 +0000 //www.deco-dalles.com/?p=1804#comment-40707 hi michael,

good day…

while updating the schedule, p6 picks 00:00 hrs as default start time when the user does not show the time in user preference. is there any option to change the default start time 00:00 hrs because almost all activities in my schedule starts at 08:00 hrs?

thanks,
rajesh

]]>
by: michael john //www.deco-dalles.com/primavera-calendars-change-durations/#comment-39868 tue, 05 jul 2016 05:56:28 +0000 //www.deco-dalles.com/?p=1804#comment-39868 hi michael, thank you very much for your help.

regards,

michael john

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-39862 mon, 04 jul 2016 20:32:32 +0000 //www.deco-dalles.com/?p=1804#comment-39862 in reply to michael john.

you may have a partial duration. goto edit->user preferences -> time units and add decimals to duration. check the durations of your activities to see if any are partial.

]]>
by: michael john //www.deco-dalles.com/primavera-calendars-change-durations/#comment-39859 mon, 04 jul 2016 07:55:18 +0000 //www.deco-dalles.com/?p=1804#comment-39859 hi michael,

good day!

i just want to ask regarding duration and calendars,for example in my programme i have 1 day duration start date is 01 june 2016 and finish on 01 june 2016 same day, and the other is 1 day duration 01 june 2016 finish on 02 june 2016. how we can fix this?

thanks,

john

]]>
by: turkish_planner //www.deco-dalles.com/primavera-calendars-change-durations/#comment-38603 tue, 12 apr 2016 07:08:09 +0000 //www.deco-dalles.com/?p=1804#comment-38603 in reply to eric cunningham.

eric you should care about lag. when you change hours, calendars; lag stay same as original hour. i had same problem

]]>
by: george sze //www.deco-dalles.com/primavera-calendars-change-durations/#comment-38118 tue, 01 mar 2016 15:28:42 +0000 //www.deco-dalles.com/?p=1804#comment-38118 dear mr lepage.
looking for an explanation for the following: the totall original duration amount changes from from each update. the logic, start dates end dates, calendar and each activity’s original duration remains the same for each update. the start date and end date for the total original duration is the same for each of the new update. how come the total original duration amount changes with each update. any assistance is greatly appreciated

]]>
by: ali //www.deco-dalles.com/primavera-calendars-change-durations/#comment-37968 thu, 18 feb 2016 15:07:34 +0000 //www.deco-dalles.com/?p=1804#comment-37968 hey!
i want to change my calender, 1 week full working and after week sunday is holiday. also, 2week working in 1 day holiday. how can i do ?

thanks.

]]>
by: benjamin //www.deco-dalles.com/primavera-calendars-change-durations/#comment-37407 tue, 26 jan 2016 18:50:09 +0000 //www.deco-dalles.com/?p=1804#comment-37407 dear mr. leapage my problem is that i imported an xer file into my system from another system. the original durations changed and when i fixed the project dates changed. i compared all setting with the system where i imported from all are thr same. pls i need help.

]]>
by: gokhun //www.deco-dalles.com/primavera-calendars-change-durations/#comment-37253 sat, 23 jan 2016 05:16:58 +0000 //www.deco-dalles.com/?p=1804#comment-37253 hi michael,

thanks for the very helpful tutorial. however i would like to ask how to apply this change to the activities which have actual start dates. should i change just the remaining duration part?

thanks in advance.

]]>
by: naseeb ullah //www.deco-dalles.com/primavera-calendars-change-durations/#comment-36874 tue, 12 jan 2016 06:37:33 +0000 //www.deco-dalles.com/?p=1804#comment-36874 sir i am unable to see the tutorial.. no video at all. there is a white blank space

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-34926 thu, 12 nov 2015 14:51:49 +0000 //www.deco-dalles.com/?p=1804#comment-34926 rohit,
did you check all of the settings i discuss in the video? did you change the calendar and then see durations increase? if so, then you’ll need to do a global change or retype the durations as i show in the video.

]]>
by: rohit ravikumar //www.deco-dalles.com/primavera-calendars-change-durations/#comment-34885 mon, 09 nov 2015 10:40:57 +0000 //www.deco-dalles.com/?p=1804#comment-34885 hello michael,

in my schedule i am using 2 schedules . one is 6 days per week, 8 hrs calendar, the other is 22 hrs per day , 7 days a week. the problem i am facing now is that the durations in the wbs which is assigned the 22hr-7day schedule have increased considerably and i cant seem to find a solution for this problem. the user preference are 8hrs day, 48hrs per week, 208 hrs per month and 2496 hrs per year.

awaiting your comments / recommendations .

thanks

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-30082 wed, 05 aug 2015 21:01:50 +0000 //www.deco-dalles.com/?p=1804#comment-30082 in reply to keith m.

keith, thanks for this alternate method and the warnings! i think all things we suggest here come with an underlying warning! i may have to write this up a post – full credit!
michael

]]>
by: keith m //www.deco-dalles.com/primavera-calendars-change-durations/#comment-29792 thu, 30 jul 2015 13:04:12 +0000 //www.deco-dalles.com/?p=1804#comment-29792 this method becomes cumbersome if you have to move multiple calendars to a single calendar, especially so if there is a disconnect in non-working days (weekends etc.).

an alternative method is to target the remaining finish date (and completely ignore underlying durations):

– baseline project(s)
– set primary baseline to above
– create a layout, showing the before and after view [using bl1 above]
– filter your data to show target activities
– run a global change performing the following actions, in order…

– set “calendar” to the desired calendar
– set “remaining finish” to “bl1 finish”

this should work for most scenarios, as setting the “remaining finish” effectively forces primavera to re-calculate the equivalent working hours to achieve said result. this means you don’t have to perform a forensic inspection on the calendars/hours.

warning 1 (applies to both methods) – the global change may not yield “to the day” results, unless your target calendar happens to be a 7 day working week.

warning 2 – might not work.

]]>
by: yesha n //www.deco-dalles.com/primavera-calendars-change-durations/#comment-24701 thu, 09 oct 2014 05:14:58 +0000 //www.deco-dalles.com/?p=1804#comment-24701 hi,

i am working on a schedule which has 8 hrs per day duration and 5 days a week. however ther;s one wbs which has activities of 10 hrs per day and 6 days a week. this wbs i am copying from a different project. after copying this my durations in overall project are changing,
please can you suggest me the solution to this?

thanks

]]>
by: plannertuts //www.deco-dalles.com/primavera-calendars-change-durations/#comment-24649 sat, 04 oct 2014 11:20:10 +0000 //www.deco-dalles.com/?p=1804#comment-24649 hi
i’m not sure i fully understand what you mean by moving the finish date. but you could edit the global change to target just the 1st calendar and make the changes. you would edit the top line to say something like “where calendar = 8x5calendar”.

]]>
by: adele //www.deco-dalles.com/primavera-calendars-change-durations/#comment-24636 fri, 03 oct 2014 16:00:11 +0000 //www.deco-dalles.com/?p=1804#comment-24636 hi mr. lepage,
i am working on schedules with two calendar:
24*7
8*5
when i apply your solution i can’t move finish date just by entering days for duration.
it seems it still calculate my day as 3 * 8h/d how ever i want to keep my 24 h/d for first calendar and 8h/d fo second one.
would you please tell me how to do it? thanks

]]>
by: teo68 //www.deco-dalles.com/primavera-calendars-change-durations/#comment-21780 thu, 14 aug 2014 20:32:01 +0000 //www.deco-dalles.com/?p=1804#comment-21780 i have three calendars in my schedule.
first calendar is a 7 day per week, 8 hours per day.
second calendar is 6 day per week, 8 hours per day.
third calendar is 6 day per week, 8 hours per day and it has some days off in every month for holidays and due to weather conditions.

when i change from third calendar to the second calendar, my activity duration changes, increases, even in hours. it appears as if the activity coincides on a non-working day in the third calendar, when changed to the second calendar, these non working days are added up to the original duration.

how do i stop this?

thank you.

]]>
by: nancy cortese //www.deco-dalles.com/primavera-calendars-change-durations/#comment-12521 fri, 21 feb 2014 21:59:46 +0000 //www.deco-dalles.com/?p=1804#comment-12521 thank you, mr. lepage! i have happily run across your tutorials just today and am looking forward to looking at more of them! but i notice you are using the client version and some things i cannot figure how to do in the web version. could you please comment on the differences between them and whether or not the steps can be done in the web version?

thanks!

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-12520 fri, 14 feb 2014 16:21:58 +0000 //www.deco-dalles.com/?p=1804#comment-12520 @argent,
in the video, i explain how to set up the global change and what values to use.
where (calendar equals )
then (calendar equals )
and (original duration = original duration * )
else leave blank.

what did you try? you’ll have to provide more details.
michael

]]>
by: argent frontier //www.deco-dalles.com/primavera-calendars-change-durations/#comment-12519 mon, 10 feb 2014 22:36:54 +0000 //www.deco-dalles.com/?p=1804#comment-12519 dear mr. lepage,

(i’ve written the same at the linkedin.)

i have been watching your video tutorials about how we can schedule one project using more than one calendar but unfortuntely i don’t understand yet the moment you are talking about global change. would you be so kind and tell me what data defines your global change (original duration, calendar, working days?? and do you do it…if=(….), then=(…) else=(….)). i have tried to use this but my results doesn’ make any sense. for instance at the column working days for an activity i have 200 when i should have maybe 20. it’s a big difference. thank you for your help.

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-12518 thu, 30 jan 2014 21:05:21 +0000 //www.deco-dalles.com/?p=1804#comment-12518 @eric, it’s likely due to the definition of a day in your p6 install. my guess is when you input 1d as a duration, it defaults to 8 hrs regardless of the calendar.
verify this by setting your durations format to hours (edit -> user prefs -> time units tab), then set an activity to a 10hr/d calendar and enter”1d” as a duration (actually type in “1d” and hit enter). if you get 8hrs back, there’s the problem.
as i explain in the video, you’ll want to use that setting that allows the definition of hrs/day to be associated with calendars. i think the steps in the video should solve this. you may need to run a global change like i suggest.

]]>
by: eric cunningham //www.deco-dalles.com/primavera-calendars-change-durations/#comment-12517 thu, 30 jan 2014 16:21:10 +0000 //www.deco-dalles.com/?p=1804#comment-12517 excellent! quick question please. when using both 8 and 10 hr days, why do starts and finishes end up at all hours of the workday? i’ve been asked this, and must admit to being a little rusty. many thanks.

]]>
by: sf yip //www.deco-dalles.com/primavera-calendars-change-durations/#comment-12516 thu, 30 jan 2014 01:46:15 +0000 //www.deco-dalles.com/?p=1804#comment-12516 great tutorial. many thanks

]]>
by: michael lepage //www.deco-dalles.com/primavera-calendars-change-durations/#comment-12515 thu, 23 jan 2014 19:03:45 +0000 //www.deco-dalles.com/?p=1804#comment-12515 ryan, you’ll only see this if the work hours per day increases between the old and new calendars. if you go from say a 12hr x 5d calendar to a 12hr x 7d calendar, the durations of your activities will not change. only if your calendar increases the work hours per day.

]]>
by: ryan //www.deco-dalles.com/primavera-calendars-change-durations/#comment-12514 thu, 23 jan 2014 18:16:47 +0000 //www.deco-dalles.com/?p=1804#comment-12514 i’m having the opposite problem. my duration is not changing, the days are remaining the same even though i am increasing the work hours per week. the bar chart is adjusting appropriately, but the duration is not, pleas help!

]]>
by: dinakar.k //www.deco-dalles.com/primavera-calendars-change-durations/#comment-12513 sun, 03 nov 2013 12:38:41 +0000 //www.deco-dalles.com/?p=1804#comment-12513 kindly help in making a writeup or presentation on “resource shifts” explaining how and where do we use with example. can this feature used in turn around projects?.

]]>