comments on: the big problem with primavera p6 calendars and how to fix it - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/primavera-p6-calendars-big-problem/ project controls training & courses wed, 09 oct 2019 17:43:29 +0000 hourly 1 by: sunny //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-64796 tue, 02 oct 2018 10:54:04 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-64796 hi..
while adding activity details the original duration is not matching with start date and finish date.
for eg: my planned activity start date is 01-june-2018 and finish date is 31-july 2018. the original duration is showing 65 days. why is it so?

]]>
by: anniek //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-52207 thu, 30 nov 2017 09:07:02 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-52207 i recently encountered a bug that if the global calendar is inherited to a project calendar, but this global calendar is not assigned to any activities, the p6 allows you to delete it. i deleted one of that global calendar and later found out all the holiday information on the project calendar was gone, thus the whole project dates moved! the project was received and import to my p6, so it was created by others.

oracle finally admits this is a bug as p6 allows you to delete it and think it is not being used.

]]>
by: parth //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-40009 wed, 20 jul 2016 08:05:09 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-40009 my project data is grey,pls help with solution

]]>
by: parth //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-40008 wed, 20 jul 2016 06:38:19 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-40008 my project button is grey and inactive
how to solve in p6 32 bits

]]>
by: tangkas88 //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-39915 tue, 12 jul 2016 00:56:27 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-39915 what’s up, i check your the biggest problem with primavera p6 calendars and how you can fix it blog on a regular basis. your story-telling style is awesome, keep doing what you’re doing! tangkas88 http://arenabolabet.com/

]]>
by: rafael davila //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-36403 sat, 26 dec 2015 14:58:31 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-36403 in reply to rafael davila.

and what when an unassigned resource works several hours or days on an activity?

at some point it becomes too much. i use the hands down approach of keeping the details on the payroll records, time cards and job unit costing system. these records complement the schedule i use to plan rather than for an over detailed record keeping via the schedule updates.

]]>
by: rafael davila //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-36402 sat, 26 dec 2015 13:45:04 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-36402 in reply to idris.

this is weird, the software shall allow recording work hours different to as planned. similar to work on saturdays, work on overtime can be different as planned. there must be a way to record true actual and keep true plans.

what happens if using time cards the calendar is 8 hr per day, 5 days a week and the resource worked 10 one of the regular day of the week? i suppose it would get it right, then if direct data entry you shall be able to get it right.

]]>
by: rafael davila //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-36391 fri, 25 dec 2015 11:36:06 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-36391 i use different software and can organize the activities gantt as well as the resource gantt in a way similar to what you propose.

]]>
by: rafael davila //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-36390 fri, 25 dec 2015 11:28:14 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-36390 activities as well as assigned 世界杯时间比赛时间 can use different calendars.

how do you filter/organize for calendars used by activities vs calendars used by 世界杯时间比赛时间 when different?

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-35806 thu, 03 dec 2015 14:06:09 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-35806 in reply to jyothi.

in this case, you would need to create a calendar that allows weekend work and assign it to those activities. then you can progress the weekend dates as actuals.

]]>
by: idris //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-35805 thu, 03 dec 2015 13:33:28 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-35805 hi jyothi,
i think you need to go back to your calendar and make those actual dates (holidays) as an exception on your calendar.

regards,

idris

reply

]]>
by: idris //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-35804 thu, 03 dec 2015 13:32:20 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-35804 hi,
i think you need to go back to your calendar and make those actual dates (holidays) as an exception on your calendar.

regards,

idris

]]>
by: jyothi //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-33793 mon, 05 oct 2015 06:06:47 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-33793 hi michael,

in the beginning of scheduling , i fix the calendar with working as 5days/week & considering other national holidays.
some of the activities are completed at site on weekends and holidays to recover the delay in schedule.
but , while updating the physical progress in system. system not allowing the actual dates , which we already mentioned as holidays.
kindly advice to update the actual dates in system.

regards,
jyothi

]]>
by: plannertuts //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-25538 wed, 04 mar 2015 19:09:33 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-25538 in reply to michael hindman.

full agreement.

]]>
by: plannertuts //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-25537 wed, 04 mar 2015 19:08:50 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-25537 in reply to michael hindman.

michael,
i’m not debating anything from your comment. global calendars were probably meant to be used exactly as you describe. however, in my experience, too many users have access to edit global calendars, and sometimes no knowledge of the kind of impact they are making. if 50 projects are referencing a global calendar, and some inexperienced user changes that calendar to suit his/her needs ignorant of the 50 projects that are now impacted.
it’s not truly an issue of calendar functionality – it’s an issue of user privileges. we recommend you make a project calendar as a copy of a global. then users are free to make changes to the calendar as they need. the database can handle thousands of calendars.
it sounds like you’ve already been bitten by this privilege issue – since you’ve “locked down” your global calendars. that’s definitely an option i recommend as well. but i start with using project calendars as debunking p6 privileges is another huge time killer.

]]>
by: michael hindman //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-25526 sun, 01 mar 2015 01:26:56 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-25526 in reply to hamildub.

if the global calendar is appropriate for the project, then why would i tell a user to copy it as a project calendar? i tell them to use the global calendar in the project because that is why global calendars were created by primavera in the first place. this gets away from the archaic 15 year old technology of the old betrieve p3.

here is an example using gac’s. i have an automatic interface that posts data to a single gac. i have nine sites where this gac is used. the interface is a write once where if the field is null, it will write the value, but if it already has a value, it ignores the field. this means the schedulers can in fact change the field value and it does not get over written. before we locked down the user from creating a duplicate project activity code, we had over four hundred duplicate codes of the global code. enough of these and you begin to have performance problems.

the global calendar was the same problem. example, we have a default 7×24 global calendar because we are a 7×24 company working around the clock. before we locked down the project calendars, we had hundreds of duplicate 7×24 project calendars. another is the standard 40 hour week calendar. before we locked project calendars down we had hundreds of those duplicate calendars.

so, because the global calendar can be used in any project at any site and we can name them as standards for our business, why in the world would we allow thousands of duplicate calendars in aggregate, when i can have none or very few unique project calendars that do not rise to the level of voting to create a common approved global calendar?

]]>
by: michael hindman //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-25525 sun, 01 mar 2015 00:58:17 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-25525 this shows how to do a one time fix. however, it does not set up config controls to prevent the problem in the first place. first, set up users where only the top schedulers leads can import into a test instance. set up a corporate procedure to explain how to clean up the import to prevent corruption of the production instance. removing any non approved global codes, any project codes, changing out calendars to approved global calendars, remove any non approved notebook topics, non approved udf’s, etc. then set controls to where only a handful of local site admins to have security to add any new globalk calendars, activity codes, udf’s etc. turn off user ability to create project calendars and project activity codes. if a new one is wanted, then the site admin can coordinate with other site admins to vote on whether to add or not.

once all the controls are set up via security, you will see significant reduction in duplicate and abandoned codes, calendars, etc. last is to have one of the admins set up in an access db via read only odbc connection a series of queries to guickly determine if a new gloabal code, calenders, etc has been created by looking at the create dates. check once every two weeks. then the ruthless part – create a corporate p6 configuration controls procedure and in it state the rules for adding a new global activity code, udf, calendar, etc. state that the rules are that all site admins must talk and vote on whether to approves a new one. and that if a new code is discovered and that new code was not appoved by all site admins, then it will be deleted when found.

once all of the p6 configuration controls are in place, you will find life is much easier and p6 does not grow uncontrolled and have hundreds of duplicate codes, calendars, udf, eps codes, and all the other areas schedulers love to add the spur of the moment code only to abandon it in a fews weeks.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-25449 wed, 11 feb 2015 18:46:42 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-25449 in reply to kristen.

good question kristen – in enterprise->calendars, highlight a calendar, the click the “used by” button. you’ll get a list of projects that the highlighted cal is linked to. any project names with a “- b1” are baselines. that should do the trick!

]]>
by: kristen //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-25448 tue, 10 feb 2015 20:19:12 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-25448 are there any tips for finding what project a global calendar is assigned to if that xer is an embedded baseline?

]]>
by: mostafa //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-25402 mon, 02 feb 2015 23:13:57 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-25402 thanks alot

]]>
by: hamildub //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-20605 thu, 10 jul 2014 22:00:02 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-20605 @divenpuff; how are project calendars uselss? i limit my users to being able to edit the project calendars associated with projects that they are responsible for and the global calendars can only be edited by certain users. when they create a project they choose from one of the global calendars that has the closest fit and then can create a project calendar if they need to edit further. can you expand on why this method doesn’t work? so far we’ve had success.

]]>
by: divenpuff //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-19977 thu, 26 jun 2014 12:35:01 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-19977 frank: no, project calendars do not take care of all the issues, as this posting explains. in fact, in a multi-user, multi-project p6 db, project calendars are quite useless, as are project-level activity codes.

]]>
by: frank //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-11994 wed, 05 mar 2014 03:20:22 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-11994 why bother with global calendars when you can use project calendars which take care of all the issues.

]]>
by: jack gargett //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-11993 tue, 04 mar 2014 20:14:26 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-11993 your comments many thanks an interesting and sensible method of controlling the mass of calendars which we tend to ignore until we really want that special one and are unable to find it. thanks again jack

]]>
by: gowtham sundar //www.deco-dalles.com/primavera-p6-calendars-big-problem/#comment-11992 tue, 04 mar 2014 14:58:19 +0000 //www.deco-dalles.com/?post_type=article&p=2135#comment-11992 this is the nice way to manage calendars!

]]>