comments on: primavera p6 activity calendars don’t match wbs calendar - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/ project controls training & courses tue, 16 jul 2024 20:04:06 +0000 hourly 1 by: veasna lam //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-100751 sun, 26 mar 2023 08:44:07 +0000 //www.deco-dalles.com/?p=36328#comment-100751 i also have another question on summary line (wbs line), how can i know which calendar is used for summary line if activities inside that summary line are used different calendars.

thanks & regards,

veasna

]]>
by: blake //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-100347 thu, 09 mar 2023 14:50:33 +0000 //www.deco-dalles.com/?p=36328#comment-100347 hi michael,
is there any reason why i should have my major milestones calendar match my activity calendar? i have always set my milestone calendar to 7x24. my activity calendar will vary between 1 & 2- 10 hour shifts, 5-7 days a week.

]]>
by: rahul doshi //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-98831 wed, 04 jan 2023 19:42:22 +0000 //www.deco-dalles.com/?p=36328#comment-98831 hi team,

we are having a similar issue where in the p6 application at the wbs summary level, no of hours are different and in the database for same wbs no of hours are different.

please help.

thanks,
rahul doshi

]]>
by: precious henry //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-78308 fri, 19 jun 2020 10:24:59 +0000 //www.deco-dalles.com/?p=36328#comment-78308 thanks.

the f5 key worked for me

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-75811 thu, 31 oct 2019 12:46:34 +0000 //www.deco-dalles.com/?p=36328#comment-75811 in reply to sayas.

sorry – p6 only supports gregorian calendar. interesting because i’ve had this question a few times lately. maybe you can use ordinal dates?

]]>
by: sayas //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-75804 tue, 29 oct 2019 07:11:03 +0000 //www.deco-dalles.com/?p=36328#comment-75804 hi dear michael lepage when i schedule projects the calendar type p6 is meladi or garigory but the client do not let me to miladi and say me to make it solar calendar or hijri shamsi please help and inform me.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-53636 wed, 20 dec 2017 20:40:59 +0000 //www.deco-dalles.com/?p=36328#comment-53636 in reply to sandeep.

calendars are actually assigned to each activity – on the general tab for the activity. you have to make the change there, for each activity. you can also do a fill down to help you do this quickly, rather than 1 activity at a time. here’s how: //www.deco-dalles.com/primavera-p6-fill-down/

]]>
by: sandeep //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-52326 sat, 02 dec 2017 09:01:47 +0000 //www.deco-dalles.com/?p=36328#comment-52326 i am having an issue where i changed my projects default calendar but activities are still showing me the previous assigned one. i have just started learning primavera.

]]>
by: junaid ali //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-48506 wed, 13 sep 2017 17:33:41 +0000 //www.deco-dalles.com/?p=36328#comment-48506 i have an issue with my schedule, wbs is showing wrong (sum of units at wbs is more than the sum of activities )…

can any body how to fix this?

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-45174 thu, 11 may 2017 11:26:25 +0000 //www.deco-dalles.com/?p=36328#comment-45174 in reply to vivek garg.

please refer to other articles such as this one: //www.deco-dalles.com/5-things-know-primavera-p6-calendars/

]]>
by: vivek garg //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-44899 fri, 05 may 2017 10:08:27 +0000 //www.deco-dalles.com/?p=36328#comment-44899 in reply to vivek garg.

further, even after refresh … checking out user preferences and admin preferences …its not showing same …..

please help

]]>
by: vivek garg //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-44898 fri, 05 may 2017 10:07:33 +0000 //www.deco-dalles.com/?p=36328#comment-44898 i am having the above shown problem … i.e. for same start and finish dates … my wbs element and activities under it are showing different durations

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-44319 wed, 19 apr 2017 10:45:00 +0000 //www.deco-dalles.com/?p=36328#comment-44319 in reply to jack.

glad to hear it!

]]>
by: jack //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-44318 wed, 19 apr 2017 04:48:37 +0000 //www.deco-dalles.com/?p=36328#comment-44318 thank you very much !
had me confused there !
f5 did the trick !

thanks again

]]>
by: mujahid //www.deco-dalles.com/primavera-p6-calendars-dont-match-wbs-calendar/#comment-40776 sat, 24 sep 2016 11:03:14 +0000 //www.deco-dalles.com/?p=36328#comment-40776 thanx michael. ask 世界杯2022亚洲比赛时间 is really a good initiative.

]]>