comments on: duration percent complete in primavera p6 – the missing guide - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/ project controls training & courses fri, 12 jan 2024 16:05:17 +0000 hourly 1 by: michael lepage //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-80349 thu, 17 sep 2020 18:18:47 +0000 //www.deco-dalles.com/?p=1287#comment-80349 in reply to amr salah.

the performance % complete of the wbs element will be calculated by [performance % complete] = ev / bac formula. it’s not the sum of the underlying activities. check ev & bac for the wbs element.

]]>
by: amr salah //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-80033 sun, 06 sep 2020 09:50:29 +0000 //www.deco-dalles.com/?p=1287#comment-80033 why the performance % complete for wbs is zero although it equals the activity % for every task

]]>
by: jessica flare //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-75892 sat, 30 nov 2019 07:57:48 +0000 //www.deco-dalles.com/?p=1287#comment-75892 waiting for your other articles: activity % complete, performance % complete

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-75788 thu, 24 oct 2019 19:45:39 +0000 //www.deco-dalles.com/?p=1287#comment-75788 in reply to faysal farhat.

sorry, p6 only has the option for 1 or 2 decimals. there’s always excel.

]]>
by: faysal farhat //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-75783 tue, 22 oct 2019 09:46:30 +0000 //www.deco-dalles.com/?p=1287#comment-75783 why primavera p6 does not take more than 2 decimals for performance % completion?
how can i make it to take more than 5 decimals

]]>
by: rory //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-65620 sun, 28 oct 2018 21:37:01 +0000 //www.deco-dalles.com/?p=1287#comment-65620 if you use a global change to change the original duration then you are changing the durations that you planned therefore your as built schedule will not be useful for estimating durations on future similar projects. therefore you will not able to review your planned durations (original duration) against your actual durations. using your global change methosshould not be recommended in my opinion.

]]>
by: de jong //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-44644 fri, 28 apr 2017 16:41:44 +0000 //www.deco-dalles.com/?p=1287#comment-44644 in reply to emmy d. onuoha.

emmy,

concerning the financial project performance:
in many projects the clocked manhours are in a different software system , and primavera calculates the earned value hours. the calculation of the earned value is done by % complete times 1% of the baseline budget.
this means that it does not matter what kind of % kpl you use.

physical % complete has also problems of its own ,regarding the end date of a project.

as % complete and the rest duration are not connected , an activity of for instance 10 days can be given 90% complete with a rest duration of 8 days.this implicates that a project with a duration of for instance 12 months can be reported 80% complete with a rest duration of 10 months. nice when there is a fixed end date of a project and you report to the management that they are 80% complete.

anyway, working with a pdm network, the time schedule is driving by duration and not by manhours.

]]>
by: emmy d. onuoha //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-38393 wed, 23 mar 2016 07:39:50 +0000 //www.deco-dalles.com/?p=1287#comment-38393 duration % complete is a lazy man’s way progressing activities of a programme. never to be used in a complex and multiple trades environments. monitoring duration is does not help at all. my advice is to use physical % complete. project performanace is judged by physical work done not duration taken.

]]>
by: kriss //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-37607 tue, 02 feb 2016 12:48:00 +0000 //www.deco-dalles.com/?p=1287#comment-37607 in reply to manoj.

in a cost loaded schedule, go to columns and expand the option percent completes where you can find “schedule % complete”. add this filed to your columns. this will give the planned %.

]]>
by: amin //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-33190 mon, 21 sep 2015 18:37:01 +0000 //www.deco-dalles.com/?p=1287#comment-33190 duration % complete for wbs elements
how to calc wbs element ?

]]>
by: afsaneh //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-28925 sat, 11 jul 2015 07:56:34 +0000 //www.deco-dalles.com/?p=1287#comment-28925 hi
can you explain, how calculate the original duration for activity that planned to starts on 7-may an finished on 1-july….it is equal to 25 not 20.am i right?

]]>
by: arul //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-25801 mon, 23 mar 2015 09:57:06 +0000 //www.deco-dalles.com/?p=1287#comment-25801 when ll you post unit % and physical %

]]>
by: sunil //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-25195 tue, 16 dec 2014 07:09:17 +0000 //www.deco-dalles.com/?p=1287#comment-25195 please tell me how i can reschedule/update a project with out affecting the end date of the project.

normally when i update a project, the end date/completion date keeps on moving forward. i want to keep the end date fixed so that i can rearrange my 世界杯时间比赛时间 accordingly.

]]>
by: plannertuts //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-24568 wed, 24 sep 2014 18:25:09 +0000 //www.deco-dalles.com/?p=1287#comment-24568 in reply to muhammad zahid iqbal.

is this helpful? //www.deco-dalles.com/primavera-p6-relationship-lines-baseline-bars/

]]>
by: muhammad zahid iqbal //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-24369 sun, 21 sep 2014 11:45:12 +0000 //www.deco-dalles.com/?p=1287#comment-24369 in reply to mamoun.

performance percentage is linked with physical percentage so you have to put it manually. 100 percent means your activity is actually finished but as planned its not finished. reason is that an activity might have actually started earlier than planned date

]]>
by: aria //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-15704 thu, 08 may 2014 03:49:46 +0000 //www.deco-dalles.com/?p=1287#comment-15704 i think “suppose that it’s currently may 29th”; is correct . would you check again?

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-14727 mon, 28 apr 2014 18:22:19 +0000 //www.deco-dalles.com/?p=1287#comment-14727 in reply to aamer.

aamer,
for duration type, stick to fixed duration & units/time – only change this if you’re trying to have p6 calculate durations or number of 世界杯时间比赛时间 (in very special circumstances – like a change request or scenario).
most industries use physical % complete. units is never used, and duration is the default but not ideal – stick to physical. i teach both of these subjects in great detail on plannertuts premium – our online training portal.
michael

]]>
by: aamer //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-13024 fri, 11 apr 2014 17:02:13 +0000 //www.deco-dalles.com/?p=1287#comment-13024 could any one please tell me how
how does the factors below affects an activity’s performance
in short how do we decide what duration type to select for an activity ?

1.fix duration &units
2.fix duration &units/time
3.fix units
4.fix units/time

then what percentage type you usually adopt.
1.duration
2.physical
3.unit.
i am very confused with all these- perhaps, a calculator/pen/paper would be the best option
kind regards
aamer

]]>
by: alexander //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12337 fri, 15 nov 2013 07:00:13 +0000 //www.deco-dalles.com/?p=1287#comment-12337 thank you for helpful article.
where i can find the next topics about duration complete?

good luck.

]]>
by: mike kenny //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12336 sun, 03 nov 2013 14:47:19 +0000 //www.deco-dalles.com/?p=1287#comment-12336 your tutorials are really useful , but are you able to answer a problem i have.
i’m using p6 r8.0. my activities are duration pc and fixed duration / units. they are being planned with expected finish and constraint dates. whilst i understand that the schedule will update the remaining duration (using expected date – data date) … why would the schedule process set my planned (original) duration and units to zero?

]]>
by: physical percent complete in primavera p6 - the missing guide //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12335 fri, 01 nov 2013 20:12:34 +0000 //www.deco-dalles.com/?p=1287#comment-12335 […] are three different methods of calculating the actual progress of activities: duration percent complete, units percent complete, and physical percent complete. the first two are explained in the previous […]

]]>
by: abdulhafiz s //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12334 fri, 27 sep 2013 21:58:23 +0000 //www.deco-dalles.com/?p=1287#comment-12334 mohammed f…,

the scenario you described is perfectly valid, especially if your %complete type is set to duration.

this kind of scenario will occur when your work is not evenly distributed with time.

i would suggest that you use physical % complete type for tasks like construction activities whose progress is often not distributed evenly over the duration.

however if you feel duration % complete is right for you, you might want to fiddle with your original duration or your remaining duration.

this is as far as i understand.

regards

]]>
by: mohammed faizal //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12333 mon, 23 sep 2013 16:02:11 +0000 //www.deco-dalles.com/?p=1287#comment-12333 dear nader,

found your article helpful, but wonder why some quest arises in mind that

scenario
1. od= 10
2. ad= 10
3. rd= 10
3. % compl= 0%
but still some quantity of work progressed and duration lapsed and resource did some work. could u please explain.

]]>
by: mamoun //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12332 sun, 08 sep 2013 08:32:49 +0000 //www.deco-dalles.com/?p=1287#comment-12332 dear sir
i have a problem and i can’t understand this case
in my project duration % complete is 71.76 %
& performance % complete is 100 %

what’s mean please ??

br

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12331 wed, 07 aug 2013 00:57:58 +0000 //www.deco-dalles.com/?p=1287#comment-12331 @cris – sorry it’s only available on our premium site.

]]>
by: cris benecio //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12330 tue, 06 aug 2013 10:14:52 +0000 //www.deco-dalles.com/?p=1287#comment-12330 any article of performance % complete? i’m waiting for it…

]]>
by: jae lee //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12329 wed, 31 jul 2013 21:43:22 +0000 //www.deco-dalles.com/?p=1287#comment-12329 how can i say what you have accomplished in this articles…this is the greast single challenge never seen before in pm/cm area. i am certain that your reputation and contribution will be long remembered and will impact thousands of primavera admirers, leading you to great sucess in your profession.

]]>
by: blythe engineer //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12328 fri, 19 jul 2013 18:11:20 +0000 //www.deco-dalles.com/?p=1287#comment-12328 hi,
in our project progress, my project finish date is passing the required finish date. is there any way that i can assign a constraint and remaining activity durations get smaller to hit the target finish date? for example, my project finishes on 14-jan-2014, but i want to finish it on 28-nov-2014. what should i set my activity type and duration type and percent complete type for primavera to auto shorten the remaining durations but keeping the same budgeted labor units. i sincerely appreciate any help.

]]>
by: chris r //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12327 fri, 28 jun 2013 13:24:36 +0000 //www.deco-dalles.com/?p=1287#comment-12327 why does p6 calculate duration % complete with the formula mentioned above? if you change your original duration, to match your at complete duration, how will you ever get p6 to give you an spi value other than 1.00?

]]>
by: manoj //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12326 sat, 22 jun 2013 14:35:33 +0000 //www.deco-dalles.com/?p=1287#comment-12326 sir, let me know how to calculate the planned % from my schedule. our physical progress is 86.4%.target completion date is september data date is 13-6-13

]]>
by: david hutchinson //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12325 wed, 29 may 2013 18:50:36 +0000 //www.deco-dalles.com/?p=1287#comment-12325 nader… we have noticed that there are times when ‘actual duration’ + ‘remaining duration’ do not equal at ‘complete duration’. it appears that this can be caused when a predecessor’s early finish date is overridden with actual start and finish dates. comments?

]]>
by: viju //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12324 mon, 06 may 2013 16:15:55 +0000 //www.deco-dalles.com/?p=1287#comment-12324 we have observed the following – for some activities, when the activities are complete, the at completion goes to zero, but for some the at completion shows the real cost. why?

]]>
by: nafis //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12323 tue, 16 apr 2013 08:41:20 +0000 //www.deco-dalles.com/?p=1287#comment-12323 hi

i find this site recently, i could solve some of my problems by this site,
thanks alot

]]>
by: plannertuts //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12322 wed, 13 mar 2013 00:53:47 +0000 //www.deco-dalles.com/?p=1287#comment-12322 in reply to hosna.

hosna, the activity details sometimes goes gray if you have multiple activities highlighted or if you are a highlighting a wbs or group bar. if this doesn’t solve it, reply back with more info.
pt

]]>
by: hosna //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12321 tue, 12 mar 2013 07:49:13 +0000 //www.deco-dalles.com/?p=1287#comment-12321 hi
i have some problem with my p6 i was wondering if you could help me with that
in activities detail i want to set details but it is inactive so what can i do? what can cause this mather?
bests
hosna

]]>
by: nader khorrami rad //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12320 mon, 11 mar 2013 10:23:53 +0000 //www.deco-dalles.com/?p=1287#comment-12320 dear shuvro, it’s simply [ (actual duration) / (original duration) ], and it’s not used in other calculations that i’m aware of. and yes, it can go higher than 100%.

]]>
by: shuvro //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12319 wed, 27 feb 2013 06:07:05 +0000 //www.deco-dalles.com/?p=1287#comment-12319 dear sir,

great post !

can you please enlighten about duration % of original. how is it calculated (formula) and how is it different from dur % complete. and when it should be used?.

regards

shuvro.

]]>
by: nader khorrami rad //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12318 sat, 22 sep 2012 11:23:01 +0000 //www.deco-dalles.com/?p=1287#comment-12318 in reply to mohamed khafagi.

dear mohammad,
the most likely problem is that you did not define any costs for activities. the calculation of performance % complete is depended on them.

]]>
by: mohamed khafagi //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12317 fri, 14 sep 2012 00:01:52 +0000 //www.deco-dalles.com/?p=1287#comment-12317 i have problem in p6 that the performance % is equal zero , even the activity percentage changed with values , what could be the cause , even i reviewed the admin prefrences & check activity % with the performance % technique.mments

]]>
by: nader khorrami rad //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12316 mon, 20 aug 2012 18:48:40 +0000 //www.deco-dalles.com/?p=1287#comment-12316 in reply to arun r.

you’re welcome arun; i’m glad that you’ve found it helpful.

]]>
by: arun r //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12315 mon, 20 aug 2012 18:14:12 +0000 //www.deco-dalles.com/?p=1287#comment-12315 dear mr.nader,
i can’t say what i feel reading your article. it’s very helpful & is mentioned so simply. i like that. i am waiting for performance % complete article. plannertuts is one of the best websites i seen which publishes great helpful article. i waiting for more article that help me to grow.

]]>
by: behzad //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12314 sun, 22 jul 2012 11:01:12 +0000 //www.deco-dalles.com/?p=1287#comment-12314 i really thank you. and i am stronglywaiting for performance % complete article.

]]>
by: nader khorrami rad //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12313 thu, 05 jul 2012 07:17:00 +0000 //www.deco-dalles.com/?p=1287#comment-12313 in reply to s.a. mallick.

i’m happy that you’ve found it useful.
the physical % complete will be covered in the next article, which will be published in near future.

]]>
by: s.a. mallick //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12312 wed, 04 jul 2012 06:08:27 +0000 //www.deco-dalles.com/?p=1287#comment-12312 your comments
the above mention information is really very useful . is it possible to give information for physical percnt complete method also and also about cost loading in detail considering i am very new in planning job
thanks and regards
s.a.mallick

]]>
by: duration percent complete in primavera p6 | pmarchy //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12311 tue, 19 jun 2012 16:26:21 +0000 //www.deco-dalles.com/?p=1287#comment-12311 […] latest article titled “duration percent complete in primavera p6 – the missing guide” is published in […]

]]>
by: ramkumar //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12310 tue, 12 jun 2012 09:56:43 +0000 //www.deco-dalles.com/?p=1287#comment-12310 i am very much great ful to you , i have a great experience with your subject,please guide the planners in the same manner so that the planning world shuold be the ruler in the universe.

please let us teach about 世界杯时间比赛时间 also

]]>
by: units percent complete in primavera p6 - the missing guide //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12309 tue, 05 jun 2012 13:04:08 +0000 //www.deco-dalles.com/?p=1287#comment-12309 […] already covered duration % complete and schedule % complete.  this post will explore units % complete and future posts will continue […]

]]>
by: duration percent complete in primavera p6 – the missing guide | on project management //www.deco-dalles.com/primavera-p6-duration-percent-complete-guide/#comment-12308 tue, 15 may 2012 05:16:21 +0000 //www.deco-dalles.com/?p=1287#comment-12308 […] latest article titled “duration percent complete in primavera p6 – the missing guide” is published in plannertuts. window.___gcfg = {lang: "en"}; (function() { var po = […]

]]>