comments on: use primavera p6 reflections to merge scenario projects - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/ project controls training & courses thu, 01 aug 2024 19:38:18 +0000 hourly 1 by: david cumming //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-75012 sun, 10 mar 2019 10:10:30 +0000 //www.deco-dalles.com/?p=32#comment-75012 in reply to sima jafari.

hi sima,

often it’s as simple as pressing f5 to see the reflection you made.
also, check there’s no filters on.

lastly – are you using p6 in an eppm environment / shared database, or is it standalone?

sometimes, you will find that the service on the eppm server needs restarting.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-72375 mon, 07 jan 2019 21:02:34 +0000 //www.deco-dalles.com/?p=32#comment-72375 in reply to sima jafari.

you must be using primavera p6 eppm then. the reflection is sent to a job applet that makes the copy. the applet may need some technical attention. i would check with your administrator or an it guy to help sort it out.

]]>
by: sima jafari //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-71517 sat, 05 jan 2019 07:50:41 +0000 //www.deco-dalles.com/?p=32#comment-71517 when i want to creat a reflection from project it gives me this message :your job has been scheduled see job status for more detail
but i can not see a copy of project in the node?

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-66344 mon, 19 nov 2018 21:39:35 +0000 //www.deco-dalles.com/?p=32#comment-66344 in reply to victor.

ideally, you would merge projects with the same data date. however, i would use the earliest data date 18oct. you can still update activities in the merged copy to get everything to 30oct.

]]>
by: victor //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-66141 thu, 15 nov 2018 01:19:44 +0000 //www.deco-dalles.com/?p=32#comment-66141 dear michael,

i merged three schedules from different companies with different data dates on it.

e.g. company a dd : 18 oct
b dd : 20 oct
c dd: 30 oct

once i merged these three and i want to update, which data date i will use?

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-46082 thu, 15 jun 2017 10:04:55 +0000 //www.deco-dalles.com/?p=32#comment-46082 in reply to nirav sheth.

thanks nirav!

]]>
by: nirav sheth //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-45952 thu, 08 jun 2017 00:08:39 +0000 //www.deco-dalles.com/?p=32#comment-45952 in reply to nirav sheth.

hi everyone,

i already have tried the above scenario and i can confirm it works. there is a little catch. once we complete step5 and upload contractors file into p6 by opening reflection project we need to check the project status. with importing microsoft project file it actually changed my project status to “active” so this was not allowing me to merge the reflection. now if you change the project status back to “what if” and do the right click it will show you merge option again!!!!
also once you finish your merge reflection this will keep the data date unchanged. so you will need to review the changes and if you are happy with it you can change the data date. i really liked this functionality as imagine if you have created 3-4 reflections for different contractors and you are getting their responce one-by-one. you really dont want ot change the data date untill you receive everyones update!!!

sharing is caring

regards
nirav

]]>
by: nirav sheth //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-45932 wed, 07 jun 2017 06:57:42 +0000 //www.deco-dalles.com/?p=32#comment-45932 hi michael,

first of all thanks for the wonderful tutorial and for giving us insights of reflections.

now i have a question. we are client and using primavera. out contractors are usig microsoft project. now i got one microsoft project file from them which i have converted in p6. at the month end i would like to send them the reflection of current porgram and make them update so i can merge it back. i am thinkng of following below steps. can you please suggest if there is a better way of doing it.
1) create p6 program reflection
2) open reflection. export it into microsoft project format
3) send it to contractor & contractor opens imports it into his database (microsoft project)
4) contractor performs update and sends us updated file (probably microsoft project)
5) we import his file into p6 (i will keep the reflection project open when importing)
6) p6 reflection updated
7) now merge the reflerction with main project and complete the update.

can you please review the above steps and let me know if you think it can work.

thanks in advance
nirav

]]>
by: caleb //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-45845 sat, 03 jun 2017 12:38:22 +0000 //www.deco-dalles.com/?p=32#comment-45845 please i need a primavera software tutorial step by step on how to prepare a project portfolio of more than one project, i.e combining more than one projects which are started same time and sharing same 世界杯时间比赛时间 .

]]>
by: caleb //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-45844 sat, 03 jun 2017 12:35:36 +0000 //www.deco-dalles.com/?p=32#comment-45844 the tutorial was helpful but can someone help me a step by step procedure on how to carryout portfolio management on primavera p6?

]]>
by: jaseem //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-43623 wed, 22 mar 2017 08:41:40 +0000 //www.deco-dalles.com/?p=32#comment-43623 hi michael ,

i am updating master project based on the progress update i receive from multiple users in reflection project. i wish to update the forecasted dates in reflection project on daily basis based on the updated master project schedule . is there any option to achieve this requirement without creating another reflection project .

in short , my requirement is as below

daily activity status update – from reflection project(multiple users) to master project (planner)
daily updated schedule with new dates – from master project(planner) to reflection project (for multiple users)

]]>
by: dd //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-41156 mon, 24 oct 2016 01:30:55 +0000 //www.deco-dalles.com/?p=32#comment-41156 hi everyone,

i want to know, can i update 2 baseline program in 1 layout, because my boss ask me to do 2 baseline program which 1 we submit to client and another one for internal used which the completion date much early. i just a new planner because before this i was engineer. all this still new to me and i hope someone can help me. thank you.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-39865 mon, 04 jul 2016 20:38:52 +0000 //www.deco-dalles.com/?p=32#comment-39865 in reply to bilal.

sounds like you want to make a scenario. copy your project and do the scenario in the copy. if the boss like it, make the same changes in your original project or make this scenario project the new go-forward project. then rebaseline.

]]>
by: bilal //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-39833 wed, 29 jun 2016 08:27:32 +0000 //www.deco-dalles.com/?p=32#comment-39833 hi everyone,
i am working on a project and project is on midway. i already updating actual data on project. but now my boss is saying to change the scenario of the project by hiring more contractors and overlapping the activities. please suggest me how can i make changes on a midway project with already applying actual with baseline?

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-38762 thu, 28 apr 2016 18:40:07 +0000 //www.deco-dalles.com/?p=32#comment-38762 in reply to stefanos.

yes, you can unlink it. you simply have to change the “project status” field from “what-if” to something else – “active” perhaps. then the merge feature goes away. if you set it back to “what-if” you can merge it again.

]]>
by: stefanos //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-38741 wed, 27 apr 2016 06:45:08 +0000 //www.deco-dalles.com/?p=32#comment-38741 in reply to michael lepage.

if the relationship changes cannot be merged back, can i “unlink” the reflection from the main project and make it a stand-alone ? this way i could put the base project as a baseline to this stand-alone to implement the changes and maintain visibility of the past.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-37815 thu, 11 feb 2016 15:35:43 +0000 //www.deco-dalles.com/?p=32#comment-37815 in reply to arunkumar gunaseelan.

that would be great, but i don’t think p6 can do that.

]]>
by: arunkumar gunaseelan //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-37811 thu, 11 feb 2016 11:18:09 +0000 //www.deco-dalles.com/?p=32#comment-37811 michael.

is there any possible to create reflection for multiple project at a time? i have seen reflection when select single project that opened. give me the solution becuase i am using more than 20 projects and make schedule for every day. your solution would be really helpful for me.

thanks
arun

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-35675 mon, 30 nov 2015 21:26:25 +0000 //www.deco-dalles.com/?p=32#comment-35675 in reply to haytham saad.

unfortunately, you can’t merge any relationship changes using reflections. michael

]]>
by: haytham saad //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-35655 mon, 30 nov 2015 12:20:09 +0000 //www.deco-dalles.com/?p=32#comment-35655 can i edit the relationships ?? because the reflection isn’t showing any relation for activities

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-34925 thu, 12 nov 2015 14:48:03 +0000 //www.deco-dalles.com/?p=32#comment-34925 in reply to mujahid.

sorry – i can’t see any way you can hide 世界杯时间比赛时间 when you create a reflection. it’s a complete copy of the project. i think the only way is to move their work into a separate project and link the 2 projects together.

]]>
by: mujahid //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-34889 tue, 10 nov 2015 08:09:21 +0000 //www.deco-dalles.com/?p=32#comment-34889 hi michael,
i have a question if you can help me answering it. i am main contractor and there is a subcontractor recently inducted by our contracts department. i want to get schedule activities related to that subcontractor updated by subcon through reflection tool. but problem is that my schedule is loaded with boq cost (in the form of resource) which i don’t want my subcon to see when i send them reflection of schedule for updating.

can you guide me please how can i solve this issue?

thank you in advance.

]]>
by: shoshana //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-29773 thu, 30 jul 2015 05:52:02 +0000 //www.deco-dalles.com/?p=32#comment-29773 jeans is the fascination with the whole total. it is not much of a area for affordable procuring several these trying to
find big rate reductions need turn out to be conscious belonging to the point.

they are available males and women and you can have ones for different occasions
like sports or merely to put on all of the beach.
leave your short shorts, miniskirts and white sneakers at residential home.
cheap ralph lauren polo uk kids

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-25488 thu, 19 feb 2015 21:41:32 +0000 //www.deco-dalles.com/?p=32#comment-25488 in reply to jazzy.

yes, you can. just delete the original. the reflection will stay – these are all just projects in the end.

]]>
by: jazzy //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-25474 wed, 18 feb 2015 05:44:33 +0000 //www.deco-dalles.com/?p=32#comment-25474 hi,
can you keep the reflection & blow away the original?
do you have to merge it back?
then rename the reflection to be what the original project was?

]]>
by: plannertuts //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-20974 mon, 21 jul 2014 13:12:25 +0000 //www.deco-dalles.com/?p=32#comment-20974 in reply to hassan.

hassan,
before you import, open the original project first. it sounds like you have no project open when you do the import so p6 doesn’t offer the update options.

]]>
by: hassan //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-20946 sun, 20 jul 2014 06:03:53 +0000 //www.deco-dalles.com/?p=32#comment-20946 in reply to mlepage.

hi,
when i tried to import the reflective programme back from my sub-contractor, under the import action i could only see two options as create a new project & ignore existing project.i cant find the update the existing project option as i find trouble in merging the reflection into source project. need assistance.

thanks & regards,
hassan a

]]>
by: arnold //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12039 sat, 08 feb 2014 07:46:41 +0000 //www.deco-dalles.com/?p=32#comment-12039 dear michael,

is there a way we can load data from excel to the work products and documents in p6. i have tried exporting and importing including using global change but it’s not working.

best regards,

arnold

]]>
by: ramy //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12038 mon, 09 dec 2013 08:23:33 +0000 //www.deco-dalles.com/?p=32#comment-12038 dear sir;
i have 2 copies of same project (same activities same relations) but different 世界杯时间比赛时间 because one of them loaded by budgeted 世界杯时间比赛时间 (cash out) and another one loaded by selling prices to give invoices (cash in) .
i make time & dates update which is same in both projects – but financials different .
how to use what-if to merge updates to the another copy of the project (not source project)

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12037 tue, 03 dec 2013 21:55:02 +0000 //www.deco-dalles.com/?p=32#comment-12037 no. calendars are assigned only to activities. to change the calendar for all activities in a wbs, add the “calendar” column to your layout and use “fill down”. (edit menu -> fill down).

]]>
by: dayal //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12036 thu, 28 nov 2013 17:02:02 +0000 //www.deco-dalles.com/?p=32#comment-12036 is it possible to set a different calender for each and every wbs?any single option?

]]>
by: chris f. //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12035 wed, 23 oct 2013 20:06:53 +0000 //www.deco-dalles.com/?p=32#comment-12035 that process would work, except our integrated master schedule (ims) has a great deal of interdependency linking between the projects that are not the reflections. changing to “ignore relationships to and from other projects” ignores all the logic created between all of those non-reflection ims projects.

i was afraid that was the case, but hoped to be wrong.

thanks

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12034 wed, 23 oct 2013 19:25:28 +0000 //www.deco-dalles.com/?p=32#comment-12034 @chris,
hmmmm…good catch. i think you are probably correct. see if this helps.

in the reflection project, click the options button on the scheduler window (like you’re rescheduling).
in options, check “ignore relationships to and from other projects”. then run your scenario. this setting should make sure you don’t drive dates to your other projects when they are rescheduled.
let me know how it works out.
m

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12033 wed, 23 oct 2013 19:19:44 +0000 //www.deco-dalles.com/?p=32#comment-12033 @moises
apparently when moving projects to a new database, the link for reflected projects breaks. here’s the workaround:

– create a reflection from the broken source project and open only that project.
– export the copy or broken reflection that won’t merge to an xer file.
– import the xer back into the database as ‘update existing’ to the created reflection.

make sense?

]]>
by: moises //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12032 wed, 23 oct 2013 11:18:41 +0000 //www.deco-dalles.com/?p=32#comment-12032 what happend when the link between de reflected and source project is broken? i mean: i have exported both source and reflection, and imported in other machine. but now, field “source project” is blank, and there is not option to merge the reflection project into de source porject.

thanks in advance.

]]>
by: chris feagan //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12031 tue, 15 oct 2013 17:54:15 +0000 //www.deco-dalles.com/?p=32#comment-12031 we work in an multiple project ims, with major inter-linking between tasks of the projects (a-to-b, c, d; b-to-c, e, f; etc.) and have entertained the use of “reflections” for “what-if” scenario processing.

examples projects: “a” “b” “c” “d” “e” “f” “reflection of a”

my concern is that when the reflection is created (“reflection of a”
), it created duplicate logic ties to the non-reflection projects (“b” “c” “d” “e” “f”) in our ims.

won’t the “reflection” processing changes affect my non-reflection project dates based on predecessor / successors from the “reflection”?

]]>
by: farooq //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12030 sat, 05 oct 2013 04:57:07 +0000 //www.deco-dalles.com/?p=32#comment-12030 i have problem installing the p6, the problem arrives when create database. it shows bad user name or invalid private user name. can some rectify this problem

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12029 thu, 29 aug 2013 18:19:33 +0000 //www.deco-dalles.com/?p=32#comment-12029 @danu – probably not. if you have 2 projects with unmatched activity ids and names, then it seems like they are completely separate projects, and i’m not sure how a merging of these two would work.
if you need to combine them into 1 project, you can always open both and copy from one into the other.
michael

]]>
by: danu //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12028 wed, 28 aug 2013 05:37:22 +0000 //www.deco-dalles.com/?p=32#comment-12028 how can i merged an updated two (2) .xer files with unmatched id’s, activity names and data date.

appreciate your help.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12027 wed, 07 aug 2013 01:06:59 +0000 //www.deco-dalles.com/?p=32#comment-12027 @nicole,
that’s a tough one. you’re sort of stuck keeping 2 projects in sync with status until someone decides to go forward with the what-if scenario. you’ll likely have to test this out with a small project to see how it behaves. i suspect it’s not going to do what you’re hoping.
obvious (but probably not favourable) would be to status both the real project and the what-if project.
i suggest you run some tests. sorry i can’t offer more.
michael

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12026 wed, 07 aug 2013 00:57:01 +0000 //www.deco-dalles.com/?p=32#comment-12026 hi,

i don’t have any clue and couldn’t dig up any known bugs that might be related. did you try a screen refresh (f5) after merging? when you merge, it’s possible to copy the merging stuff and to paste into a notepad doc – or print it – then you can go over it in detail to ensure it’s working as expected.
sorry i can’t offer more than this.
michael

]]>
by: manuel milla //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12025 tue, 06 aug 2013 22:25:13 +0000 //www.deco-dalles.com/?p=32#comment-12025 hi michael, i have a little problem with reflection, when i merge the projects, the labor units triplicates, why is that happening?

thanks for the tutorial and for any comment.

]]>
by: nicole //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12024 thu, 25 jul 2013 20:52:54 +0000 //www.deco-dalles.com/?p=32#comment-12024 if i made a reflection to model some changes and the project i made a reflection of is statused, is there a way for me to have that status merged into my reflection? in this example the what if senario is taking several months and regular status is still continuing. my what if is becoming out of date. any ideas?

thank you in advance!

]]>
by: dixon //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12023 fri, 05 jul 2013 04:09:03 +0000 //www.deco-dalles.com/?p=32#comment-12023 hi.
sir,
is there any option in p6 to generate the the s-curve to express planned and actual progress.

with regards.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12022 fri, 17 may 2013 00:36:08 +0000 //www.deco-dalles.com/?p=32#comment-12022 @wtaylorcooper,
unfortunately relationships do not merge. same goes with resource assignments. you have to update these manually in the merged project – the merging feature will not do it for you.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12021 fri, 17 may 2013 00:33:28 +0000 //www.deco-dalles.com/?p=32#comment-12021 hi, yes, i believe you can. the link is not by name, but through another field which eludes me now.
m

]]>
by: cara z //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12020 tue, 07 may 2013 15:06:51 +0000 //www.deco-dalles.com/?p=32#comment-12020 hello. great thread as always!

can you re-name the reflection project without compromising it’s functionality?

]]>
by: w. taylorcooper //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12019 mon, 29 apr 2013 18:07:41 +0000 //www.deco-dalles.com/?p=32#comment-12019 my question concerns the use of reflections and changing activity relationships.
can i change the activity relationships in reflection project and upon merge, will these “revised” relationship replace what i have in the current project?
we have a scenario for some offshore work that we want to look at different marine vessel sequencing and this would allow me to do “what – if” planning in several plans to present to offshore team.
thanks in advance for your assistance.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12018 thu, 25 apr 2013 12:58:06 +0000 //www.deco-dalles.com/?p=32#comment-12018 it sounds like someone else has one of your projects open. you can check who is using a project by going to file->open, select your project and click the users’ button.

]]>
by: benjamin //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12017 wed, 24 apr 2013 09:09:22 +0000 //www.deco-dalles.com/?p=32#comment-12017 hello.i have an issue concerning the merge reflection into a source project, when i try to do the merge i got this message : “cannot open both projects exclusively.you will not be able to merge.” .any idea about how solving this matter? many thanks in advance.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12016 tue, 26 feb 2013 19:41:26 +0000 //www.deco-dalles.com/?p=32#comment-12016 @jayant
by design, merging will not remove items from the source project that have been deleted from the reflection. if major elements of a project have been deleted from the reflection, the user will have to manually delete them from the source project.

elements that are not deleted during a merge include:

activities
relationships
resource assignments
wbs elements
work products and documents
project expenses
project issues
project risks

]]>
by: jayant dahiya //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12015 fri, 22 feb 2013 07:35:05 +0000 //www.deco-dalles.com/?p=32#comment-12015 hi,
i have dissolved some activities in reflection of the project. now before merge all change in base project i want to be sure that these activites will going to be dissolve in base project as well. is it possible to do so or is there is any other way we can make reflection as a base project?

thank you in advance.

best regards

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12014 thu, 30 aug 2012 13:02:01 +0000 //www.deco-dalles.com/?p=32#comment-12014 in reply to kash.

hi kash,

a few options.
1) you could create a new activity to replace a b c, then delete a b c. but as you said, it would disturb your plan. if you delete a b c, it might also upset any baselines that have those activities in them as well.
2) a second option is to use a level of effort activity (set activity type to level of effort on general tab) to “summarize” those 3 activities. a level of effort activity is a special type that can summarize groups of activities – it will automatically span the duration from the start of a to the end of c. create a new activity (loe). set it to be a “level of effort” activity type. create a predecessor from loe to a – set as start-start. create a successor from loe to c – set as finish-finish. reschedule your project and loe will summarize those activities – it’s duration will be auto-calculated as the duration from the start of a to the finish of c.
give that a try and let us know if it helps. you may also review this tutorial which explains level of effort somewhat //www.deco-dalles.com/use-a-level-of-effort-to-add-work-stoppage-info-to-a-project-and-still-track-to-your-primavera-baseline/.
regards,
michael

]]>
by: kash //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12013 thu, 30 aug 2012 08:08:06 +0000 //www.deco-dalles.com/?p=32#comment-12013 hi michael,
there are different activities like a,,b,c, in my plan.they having different start dates and end dates..predecessor and successor activities.after preparing my plan i realize that its one time activity and i want to merge all these activities as one one activity.because if i deleted all activities it will disturb my whole plan. what should i do now??i want to merge all activities as a one time activity.
thanks

regards
kash

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12012 wed, 18 jul 2012 13:11:31 +0000 //www.deco-dalles.com/?p=32#comment-12012 in reply to doug young.

hi doug,

p6 has no problems with creating baselines mid-project. after you merge your reflection in, you can rebaseline your schedule to capture it with the newly merged changes.
hopefully that answers your question. if not, drop us another line here.
regards,
michael

]]>
by: doug young //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12011 tue, 17 jul 2012 14:14:05 +0000 //www.deco-dalles.com/?p=32#comment-12011 hi sir. i’m using reflections to do lots of changes etc, and hope to pull all back into the original plan. however, i also want a new baseline of said changes. how does p6 react when re-baselining, a quarter way through the plan, and where i have %ages, earned values etc,,
thanks for any help.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12010 tue, 29 may 2012 12:48:25 +0000 //www.deco-dalles.com/?p=32#comment-12010 in reply to krishna.

hello krishna,
please browse the site. all our tutorials are posted here and are currently free to peruse.
warmest regards,
michael

]]>
by: krishna //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12009 tue, 29 may 2012 12:11:32 +0000 //www.deco-dalles.com/?p=32#comment-12009 how can i get all the tutorials of you. please advise.

]]>
by: the planner tutorials hub- ppm community project management blogs //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12008 wed, 09 may 2012 12:22:39 +0000 //www.deco-dalles.com/?p=32#comment-12008 […] use reflections in primavera p6 to merge scenarios back into your project […]

]]>
by: approve updates from subcontractors in primavera p6 using reflections //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12007 wed, 04 apr 2012 00:54:06 +0000 //www.deco-dalles.com/?p=32#comment-12007 […]  if you’ve perused our p6 tutorials, you may already know reflection projects are great for working with and managing scenarios.  but they can also provide a way to preview and selectively approve activity updates from […]

]]>
by: the planner tutorials hub //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12006 wed, 21 mar 2012 09:59:53 +0000 //www.deco-dalles.com/?p=32#comment-12006 […] use reflections in primavera p6 to merge scenarios back into your project […]

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12005 tue, 21 feb 2012 15:31:10 +0000 //www.deco-dalles.com/?p=32#comment-12005 in reply to dave morrow.

thanks dave! we really appreciate your positive feedback and will strive to continue to helping this community.

]]>
by: dave morrow //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12004 fri, 17 feb 2012 19:32:59 +0000 //www.deco-dalles.com/?p=32#comment-12004 your comments
your tutorials were recommended to me by a colleague. i have found them all to be very useful as i didn’t know primavera was so versitile!
now i am looking forward to the next lot of tutorials to further impress my bosses!!
as sunchana states ‘it does what it says on the tin’
keep up the good work

]]>
by: sunchana johnston //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12003 sun, 27 nov 2011 16:22:24 +0000 //www.deco-dalles.com/?p=32#comment-12003 your comments
while looking for some on-line tutorials for advanced work (linking projects together, reflections, etc) in primavera p6, i came across michael’s tutorials and comments on youtube and //www.deco-dalles.com. loved it, i’m a fan!
michael’s tutorials are professional, free of gimmicks and dubious music choices imposed upon me. i’ve enjoyed watching every one of them! fortunately, i’ve been able to successfully put it in practice and live-test for the benefit of my own company. glad to say that “it does what it says on the tin”.
great work michael, please keep them coming – virtual classroom at its best!

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12002 thu, 20 oct 2011 13:17:21 +0000 //www.deco-dalles.com/?p=32#comment-12002 in reply to vicky shinde.

hi vicky,

i have a better understanding of your scenario now. if i was in your shoes, here’s how i would proceed.

1) my first choice is, if at all possible (even by nagging managers and it folks), get these contractors to work directly in my primavera database. if i can do that, i’ll have the utmost control over the flow of data and security to keep each contractor focused on only their activities.

2) if i have exhausted all possibilities of acheiving 1) above, then my second choice is to divide the project into 2 separate project plans. each contractor can then perform updates via .xer file without interfering with the other contractor’s updates or activities. it is possible in primavera to work with multiple projects as though they are 1 project, by opening them together, using activity codes to essentially merge the two projects together for viewing and analysis even though they are separate. depending on what you’ve agreed to with the client, this is the next best option, however it is not perfect either. there could be challenges if both contractors don’t update their projects at the same (or reasonably close). each project will have separate data date and if these dd’s become very out of sync, then i would have other challenges to deal with.

3) if neither 1) nor 2) was an option, then my next choice would be to enforce regular project updates from both contractors using reflections. when you merge the reflection project, i’ll be able to see if there were major changes (new activities, new resource assignments, etc.). since these major changes can’t be merged, i would have to preserve the project before (make a copy or baseline) and then either do an .xer import or manually update the major changes. i might use the claim digger tool to compare the differences after the import. i would also ask contractors to perform status updates more regularly to manage fewer updates each time.

i know it sounds difficult and tedious, and in some ways it is but using the tools in 3) would ensure that i’m very careful with the data to ensure one contractor doesn’t affect the other’s section of the project.

4) i have one further option i might pursue. bring complete control of the schedule in-house – ie: don’t allow the contractors to update their schedules, do it for them. many companies also take this approach and find it can help to better manage their contractors as well. this way, we get rid of hassle of updating and merging, but now we need to have a good communication strategy to get information from the contractor when we require an update.

vicky, i hope i’ve given some viable options to consider. this is all tricky business. but i really think if you can go with option 1), it’ll make life alot easier.

please feel free to email again if you’ve more questions. i’m here to help.

michael

]]>
by: vicky shinde //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12001 wed, 19 oct 2011 00:39:02 +0000 //www.deco-dalles.com/?p=32#comment-12001 good morning sir,
as said by you, “reflections don’t update all data”, it’ll be
difficult for me to use that option.
how importing .xer file can help?
i mean suppose if i (abc company) prepare baseline schedule for all 3
types of activities (activities for abc, xyz & combine). i export the
project as xer file, send it to other contractor (xyz company), during
the execution of the project say in 1st month, i will update my
portion of activities ( abc company activities), xyz company will
update their portion & send .xer file to me.
now when i import this .xer file & if i use “update existing project”
option in import action in import window
then will it be correct import or there are any chances of mistakes?
how can i check that ?
i mean the resulting project will show updates by both companies correctly?

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-12000 tue, 18 oct 2011 17:08:12 +0000 //www.deco-dalles.com/?p=32#comment-12000 in reply to vicky shinde.

hi vicky,

the best approach to updates is to have the companies work in the database where the project resides. this eliminates all sorts of hassle with importing data and updates. you’ll want to ensure you have proper security profiles set up for each company that logs in.

however, if having the contractors log in to the database is not possible, as you’ve stated, then importing .xer files is probably the next best approach.
yes, you can use reflections for updating projects as well. i think it would be a good choice for you to use in this situation. i might suggest you make a copy of the project to test the reflection updates on first – so can you get a feel for how they work. just remember that reflections don’t update all data. if there are major changes in the reflected project, like new relationships and resource changes, the reflection merge will not import them and you’ll have to do it manually. however, you can still import a .xer without using a reflection in that case.
if your contractors are merely providing status / actuals updates on existing activities, i do recommend you use reflections. you’ll have the ability to review the changes in the reflection differences report before merging them in.

this will be the topic of a future tutorial soon.

please feel free to contact me via with any other questions. i’m happy to help. michael@plannertuts.com
michael

]]>
by: vicky shinde //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-11999 tue, 18 oct 2011 08:56:24 +0000 //www.deco-dalles.com/?p=32#comment-11999 sir i’ve a question,
i’m working on 1 project which will be executed by 2 companies
i’ve more than 4500 activities divided in 3 categories
1. activities by abc company
2. activities by xyz company
3. activities by both companies (combine)
all this activities are interlinked

now my question is
the xyz company want to have their part of schedule i.e activities by xyz company & common activities (i.e activities by both companies) & they will update & send that schedule to us. but the client wants only 1 schedule for the whole project which is natural & standard.

both the companies are located far away geographically.
web access to xyz company is also not possible due to security policy.

what will you suggest in this situation?
can reflection project option help me in this case?

thanks in advance for your reply

]]>
by: mlepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-11998 wed, 14 sep 2011 14:06:09 +0000 //www.deco-dalles.com/?p=32#comment-11998 in reply to rob jones.

hi rob,

another good question and likely scenario. this is a nice way to use reflections for updating which i hope to cover soon.

i was able to create a reflection, export it to .xer, reimport it and merge the changes. one thing that might be tripping you up is during the import – you have to make sure that you have the reflection project open before you perform the import. this will update the reflection project in your database from the .xer file. if you don’t have the reflection project open, p6 will try to create a new project in the database and you won’t be able to perform the merge.

steps:
1) open the reflection project.
2) goto file -> import.
3) select your file.
4) choose from the import option dropdown to “update existing project” and select the project in the “import to” field to the right.
5) complete the import.
6) merge the reflection project back into the source.

drop me a line back if this doesn’t fix it for you. thanks for the comments.

]]>
by: rob jones //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-11997 tue, 13 sep 2011 11:07:47 +0000 //www.deco-dalles.com/?p=32#comment-11997 hi – yes i agree this looks very usefull, however my scenario is slightly more complex as the ‘reflected’ programme will need to be backed up (xer) and issued to subcontractor for update. when i have tried this and imported the updated xer it doesnt give me the ‘merge’ facility – is there a way round this?

rob

]]>
by: mlepage //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-11996 thu, 18 aug 2011 15:43:55 +0000 //www.deco-dalles.com/?p=32#comment-11996 in reply to dick buxton.

great question.
i did some checking and testing on what permissions you need to both create a reflection and to perform a merge. the p6 user guide says that you don’t need global “admin superuser” privileges to create a reflection. you only need to have privileges to create projects. as for project-level permissions, you do need to have “project superuser” privileges for both the source project and the reflection project.

project superuser gives you all of the project privileges in the profiles setup screen, as well as the following (which are unstated for some reason):

1. can change the responsible manager for any project that they have access to
2. allowed to import into an existing project with the following options – update, add into or replace
3. select or deselect the option to copy activities when copying a wbs node
and i guess we would add…
4. can merge reflection projects back into the source project.
m

]]>
by: dick buxton //www.deco-dalles.com/primavera-p6-reflections-merge-scenarios/#comment-11995 tue, 16 aug 2011 17:43:09 +0000 //www.deco-dalles.com/?p=32#comment-11995 i understand that you need superuser privileges to be able to merge reflections. however, i also understand that there is something called project superuser. can you merge reflections with project superuser privs or do is admin superuser required? also, what other privileges come with project superuser?

]]>