comments on: schedule % complete in oracle primavera – the missing guide (part 1) - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/ project controls training & courses tue, 25 jul 2023 21:37:52 +0000 hourly 1 by: richard ginder //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-103103 tue, 25 jul 2023 21:37:52 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-103103 thank you for the explanation of schedule % complete. it sounds great in theory. my question is how does p6 determine the baseline start and finish dates to determine planned value and/or schedule % complete if a project baseline or user baseline has not been assigned. in the instance where a xer file is submitted to the owner or owner’s consultant for a schedule update, will they be able to view the same schedule % complete and planned value as i.

]]>
by: rizwan //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-100062 wed, 22 feb 2023 09:35:21 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-100062 in reply to ahmed.

hi,
have you found the way to change the schedule percent complete based on late dates.
i also tried to find it but found nothing in p6
it is possible through excel

many thanks
rizwan

]]>
by: yousufuddin khaja mohammed //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-99105 mon, 16 jan 2023 12:55:02 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-99105 dear sir,

we have an option to get performance % complete – labor units. is there an option to get planned % complete – labor units on a selected data date?

kindly guide me, as our project schedule is loaded with labor units for monitoring purpose.

thanks and best regards,

]]>
by: rehan //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-75701 wed, 25 sep 2019 02:33:07 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-75701 nice explanation. your idea is applicable for a new program. but in case of current program where i have to spread the remaining cost after data date by using resource curve, it guess it is not applicable. plz explain

]]>
by: ranto //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-53142 fri, 15 dec 2017 01:10:57 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-53142 hi mr,
thank you for your website sir,

could you help me sir,
how to create/show in primavera p6 progress last week?
for example my progress this week is 15%, and progress last week is 10%.
i want to show the progress last week & progress this week in primavera.

thank a lot sir,

ranto

]]>
by: manohar //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-51201 tue, 14 nov 2017 12:08:34 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-51201 dear sir,

i want to get the planned % units corresponding to the updated date kindly explain me is schedule %will give the same if my activity is only loaded with manpower without giving any cost.

]]>
by: anonymous //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-43092 tue, 21 feb 2017 06:38:07 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-43092 hello,i check your blog named “schedule % complete in oracle primavera – the missing guide (part 1)” like every week.your writing style is witty, keep up the good work! and you can look our website about ???????? 2017 http://www.matb3aa.com/%d9%85%d9%87%d8%b1%d8%ac%d8%a7%d9%86%d8%a7%d8%aa-%d8%b4%d8%b9%d8%a8%d9%89-2.

]]>
by: vjbaskar //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-42841 sat, 04 feb 2017 09:55:33 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-42841 that was nice guidelines, can p6 be interfaced to an asset management system & will it prepare the optimum project scheduling with accessible time, budget and 世界杯时间比赛时间 ??? best primavera training

]]>
by: home //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-42016 tue, 20 dec 2016 08:50:37 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-42016 gxdedbmwovlbruseijunnwmazyerprrppmcedsryokiulozozbl
home https://www.ultrahoverboard.com

]]>
by: ahmed //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-41425 wed, 23 nov 2016 07:26:17 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-41425 in reply to michael lepage.

how can we get p6 to use late dates to calculate schedule % complete on late dates?

ideally, we would like to see schedule % complete based on both early and late dates for prudent analysis of the required performance.

i wan unable to find an option to select late dates to change the default from early dates. appreciate if you can assist.

]]>
by: ilori hamzat b //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-39973 sun, 17 jul 2016 11:07:20 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-39973 i read this material two years ago and it still remains the best so far.

]]>
by: ilori hamzat b //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-39972 sun, 17 jul 2016 11:06:07 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-39972 in reply to kumar.

you probably do not have cost assigned or a measurable unit assigned to your activities. try assigning cost even as low as 1currency value, it will surely roll up.

]]>
by: kumar //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-39085 thu, 12 may 2016 06:15:45 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-39085 i have a updated programme wherein schedule % completion is not rolling for wbs elements. all the activities has schedule% complete except wbs. i have done many changes however its not coming. pls guide.

]]>
by: yinka //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-38765 thu, 28 apr 2016 20:57:23 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-38765 nader, thanks for your detailed explanation.
i’ve followed the whole explanation step by step trying to practice it but i discovered that one needs to have one key setting in place for the schedule % complete to work .
the setting is on the project settings tab – baseline for earned value calculations should be set to the baseline you are going to use (either the project baseline or user baseline).
when i assigned the project baseline but didn’t select it to be used for earned value, the schedule % remained at 0 even after moving the data date.

]]>
by: aamir sohail //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-36551 sat, 02 jan 2016 07:54:03 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-36551 dear nader

if we have two 世界杯时间比赛时间 in schedule one is labor (assigned budgeted units as man-hours to each activity) other is cost for each activity as a separate non-labor resource.

based on above info how the schedule % complete info drives , how it will be calculated. if we want to drive the physical progress based on labor means man-hours.

thanks
aamir

]]>
by: qasim //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-35822 fri, 04 dec 2015 12:17:15 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-35822 hello! sir my question is that i,m physically updating my project (physical percent complete) but my schedule percent complete is showing 0% complete in front of every activity..so how can i make this schedule % complete column with this physical % compplete..

]]>
by: muhammed //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-34484 thu, 22 oct 2015 13:13:35 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-34484 simply wonderful, but i have a query & hope to get some clarification on that.
and the query is.
in wbs case, will the calculation consider only the cost assigned to activity or all non labour units. or it will consider all types of units assigned.
is there anyway to make the process use labour units in lue of cost.
if this option gives you the planned status in one column for wbs & activities using cost & time respectively then what can be corresponding column for actual status of running program to compare with.

thanks

]]>
by: m. roldan //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-34259 thu, 15 oct 2015 20:15:45 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-34259 i have some issues on p6 using alap constraint, as follows:

“task b – fabricate and deliver to site” with alap constraint is linked to “task c – equipment installation”. task b follows “task a – shop drawings approved” which has considerable float-the reason i’m using alap constraint. however, task b is picking up tf of task c which is in critical path. is there a setting in p6 that i need to change in order that task b could start earlier and remove it from critical path? more so, task b has plenty of float in front of it.

thanks.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-33880 tue, 06 oct 2015 18:30:21 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-33880 in reply to islam.

yes, early dates are used by default.

]]>
by: islam //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-33866 tue, 06 oct 2015 14:15:13 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-33866 hi,

thank you for sharing.
schedule % complete(act) = ( [data date] – [baseline start] ) / ( [baseline finish] – [baseline start] )
in this formula, if the activity is not critical, there will be early and late dates. as a result, in a specific time we will have tow values of schedule% complete, early & late, p6 uses early dates by default am i correct?

thanks again.

]]>
by: imran //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-29776 thu, 30 jul 2015 06:42:11 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-29776 great work..

]]>
by: ben kenneth //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-26691 tue, 21 apr 2015 11:23:47 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-26691 nader is not only an expert, he is a gifted instructor. his explanations with diagrams are just excellent. great work, great resource, great help.
thank you nader.

]]>
by: amir //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-25534 tue, 03 mar 2015 03:43:58 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-25534 thanks a lot for the post. i learn a lot about this subject. now i’m still learning and refreshing my skill in planning and p6. hope you guys can contribute more tutorials for everyone. keep up the good work and i will following this website from time to time. thanks

]]>
by: toufik //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-25385 wed, 28 jan 2015 06:17:12 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-25385 thank you for explaining in such a simple way.
thank you again. you are great.

]]>
by: ziad //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-25357 mon, 19 jan 2015 08:11:18 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-25357 wonderful … very wonderful explanation , thank you very much

]]>
by: plannertuts – primavera p6 tutorials from beginner to advanced: 53 project scheduling terms that every planner needs to know | project management buzz //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-25199 tue, 16 dec 2014 16:52:31 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-25199 […] weighted percent complete: overall progress completion measurement, using activity weightings to normalize disparate activities. […]

]]>
by: tajamul //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-25049 tue, 18 nov 2014 11:36:07 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-25049 in reply to khairat ismaeel.

in that case target schedule will work as baseline and all the calculation will be based on that.

]]>
by: tajamul //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-25048 tue, 18 nov 2014 11:33:32 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-25048 while the other building activities have schedule % of 100 but the wbs level show 0%.

need your kind help in this regard

best regard
tajamul

]]>
by: tajamul //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-25047 tue, 18 nov 2014 11:27:38 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-25047 i have resource loaded schedule of 163 days, i have updated some of activities after 18 days and the actual progress on wbs is 5.48% but the schedule % is showing for the wbs level is 100%. data date is 18 days ahead of bs .

]]>
by: osvaldo cruz //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-24987 mon, 10 nov 2014 20:59:46 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-24987 very useful

]]>
by: khairat ismaeel //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-21727 thu, 14 aug 2014 10:08:02 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-21727 thanks for the explanation, but i have a question for you
based on the above explanation, schedule % depending on baseline dates (no actual progress), so what if i have a revised schedule (with actual progress) and i want to set it as a target schedule??!!!
any advice?!!

]]>
by: abdulhafiz suara //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-21374 sun, 03 aug 2014 13:26:46 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-21374 in reply to yasser.

do you have cost loaded on the schedule?

]]>
by: sunil babu //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-20578 thu, 10 jul 2014 09:32:11 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-20578 excellent work , very good share of knowledge ..congrats

]]>
by: khalid //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-19476 tue, 03 jun 2014 05:31:34 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-19476 sir i need to add a column in planned % labour unit. please guide houw i can show it

]]>
by: yasser //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-19425 fri, 30 may 2014 16:32:28 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-19425 i’ am having a problem with schedule % complete and also with performance % complete in primavera program i don’t have a total for both columns beside wbs and i checked my data date and my base lines date in the upper equation manually ( i had a result ) but in primavera program ( no total for both ) beside the project summary …..

]]>
by: howard kech //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12931 thu, 10 apr 2014 08:29:15 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12931 i have recently had to re-baseline my project as we had been delayed and were not able to complete as per contract finish. without as baseline schedule % complete = (or at least should be) actual % complete. however my schedule % complete is still showing me higher than the actual giving me a variance when there shouldnt be.
how do i make my actual schedule my baseline and keep the variance at zero so i can calculate the planned progress for the remaining works for the remainder of the project

]]>
by: abrar //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12263 tue, 28 jan 2014 06:57:33 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12263 i am having negative lags in my schedule, what is the best way to calculate them to positive.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12262 wed, 08 jan 2014 17:54:05 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12262 @abhay, please check out this tutorial //www.deco-dalles.com/build-lookahead-filters-primavera-p6/. you have to use specific dates in your filter.

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12261 wed, 08 jan 2014 17:40:13 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12261 @ahmed,
schedule % complete is based on the baseline assigned to the project. do you have the same baselines and data date?
michael

]]>
by: ahmed //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12260 sun, 05 jan 2014 08:20:41 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12260 dear all,

actually i have a problem for the schedule percent complete, our consultant don’t get the same % on the wbs level.

on activity level, we have the same schedule % complete, same cost, wbs total cost also same.

our wbs % complete is correct because manual calculation give the same value.

so, where is the problem? why we haven’t the same value?

thank you in advance for your help.

best regards.

]]>
by: abhay //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12259 tue, 24 dec 2013 18:36:25 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12259 i want 2 weeks lookahead programme in p6,my project data date is 11th march-11, but i want the activities of dec-13 in 2weeks lookahead programme, so can anyone help me in getting the same

]]>
by: hb brasos //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12258 tue, 13 aug 2013 10:44:59 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12258 i made a sample project in p6 and tried 1 activity with 20 days as the duration. i displayed the total and the duration appeared as 15 (not 20). i tried to match the calendar used in the sample project with the entries at the user preferences, the result was the same. i tried to make some adjustments with the admin preferences. user preferences and calendar still the durations for the activity and total are not the same. how can i solved this?
thanks a lot in advance.

]]>
by: jefferson enríquez //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12257 tue, 18 jun 2013 16:36:33 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12257 dear nader

i have a question … i need to get my schedule % complete with the curve of resource of activity … so i put a kind of curve with my own % curve, then i save the baseline and the i use in project baseline but when i upload to my data date, my activity that is duration type show me in schedule % complete the % of the duration of the activity and i want the % of my curve of the resource. how can i get this percentage in my schedule % complete?

thank you

]]>
by: samer //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12256 mon, 08 apr 2013 19:42:30 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12256 really
thank you very much for explanation very well

]]>
by: nader khorrami rad //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12255 mon, 01 apr 2013 12:47:10 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12255 dear aladdin,
you’re probably using the “current project” option as a baseline. you should save and assign a real baseline at the beginning, and those values will stay constant.

]]>
by: nader khorrami rad //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12254 mon, 01 apr 2013 12:45:10 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12254 dear maged,
it can have different reasons, such as:
1. you’ve used retained logic rescheduling and a predecessor has moved the remaining of the activity to a later date, or
2. there’s a none-working period between your data date and the earliest time for the remaining of the activity.
those were the two reasons i can think of right now.

]]>
by: maged eid //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12253 wed, 27 mar 2013 09:01:45 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12253 dear aladdin fayoumi,

i think when you make update ,the bac. is not change but the actual and remaining budgeted cost is change due to update

]]>
by: aladdin fayoumi //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12252 tue, 26 mar 2013 09:01:20 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12252 dear sir,

i’d like to thank you so much for your helpful information.
but i face a problem when i do schedule for my updated schedule, the cash flow for the entire project change automatically at each update, which gives me a wrong schedule% to compare with performance or physical%.
how could i keep my base cash flow fixed during all project period.

regards,

]]>
by: maged eid //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12251 mon, 25 mar 2013 13:45:10 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12251 i ask about why there is a gap between the data date of any activity and it’s remaining early start when i make update? please inform me. thanks alot

]]>
by: warren //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12250 tue, 19 mar 2013 09:11:05 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12250 nice. i need to study more…

]]>
by: satish //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12249 wed, 06 feb 2013 15:18:32 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12249 i wonder how you guys do that..!! the way you explain is simply amazing..!!

cheers mate

thanks for the information

]]>
by: nader khorrami rad //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12248 fri, 18 jan 2013 20:52:13 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12248 dear maged,
you should look for hard constraints in the whole schedule.
if you are using a fixed end schedule, having negative floats will not be a problem. however, if you are using a more common form of free-end schedule, you should avoid hard constraints completely.

]]>
by: maged //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12247 fri, 18 jan 2013 17:30:44 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12247 dear sir,
when i have a negative float in my time schedule how can i find the activity that make this negative float and solve this issue ?

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12246 mon, 07 jan 2013 14:25:30 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12246 hi,
on the gantt chart, all activities on the critical path are shown in red. total float can be found for each activity on the “status” tab of the activity, down in the bottom corner.
hope that helps!
michael

]]>
by: srinivas //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12245 wed, 02 jan 2013 05:46:18 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12245 hi sir,
can u please provide me how to find critical path and float in primavera p6?

]]>
by: mustafa //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12244 sat, 01 dec 2012 10:39:03 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12244 great job nader thanks for your very helpful tutorial

]]>
by: nader khorrami rad //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12243 sun, 14 oct 2012 15:18:39 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12243 in reply to joey de leon.

no, not a complete one yet… just that short ebook about progresses.

]]>
by: plannertuts //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12242 wed, 10 oct 2012 14:06:42 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12242 in reply to joey de leon.

hi joey, we have more ebooks in the works. but for now, feel free to peruse and print from our library of tutorials and articles.
pt

]]>
by: joey de leon //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12241 tue, 09 oct 2012 20:51:52 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12241 hi,

just wandering, if you have a compete e-books for the application of p6

]]>
by: farooq //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12240 wed, 03 oct 2012 17:46:54 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12240 good information about the glitches.

]]>
by: arun r //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12239 mon, 20 aug 2012 18:54:47 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12239 great work. getting lots of new things for learning. i am really happy today.

]]>
by: nader khorrami rad //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12238 mon, 23 jul 2012 05:27:30 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12238 in reply to huda.

dear huda,
the performance % complete article will be published in near future. please re-visit the site or subscribe to its feed to be informed of the new articles.
– nader

]]>
by: huda //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12237 mon, 23 jul 2012 04:51:02 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12237 hi nader
thank you for sharing your valuable knowledge, i am looking for performance % but cant find it on your site, would you please send me te link.

]]>
by: schedule % complete in primavera p6 | pmarchy //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12236 wed, 20 jun 2012 08:48:31 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12236 […] [schedule % complete in primavera p6, part 1] […]

]]>
by: phansuek kulap //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12235 thu, 07 jun 2012 03:18:32 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12235 big thanks for your presentation; it’s so useful for planner.

]]>
by: units percent complete in primavera p6 - the missing guide //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12234 tue, 05 jun 2012 16:48:30 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12234 […] already covered duration % complete and schedule % complete.  this post will explore units % complete and future posts will continue to cover physical % […]

]]>
by: nader khorrami rad //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12233 thu, 10 may 2012 20:06:24 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12233 dear mostafa;

–1–
yes, it’s always the case in planning world: non-working times are not counted (as briefly discussed in part 2 of this article).
[finish]-[start]-[non-working-time] is not an appropriate syntax for it and [finish]-[start] is common. we actually define the “-“ operator in a way that does not count non-working times.

–2–
[baseline finish] – [baseline start] is not always equal to original duration.

–3–
when your activities’ costs are front loaded, you have the potential of having the second scenario. an extreme example: we have a wbs element with three activities. all the activities start in day one and have at least two days baseline duration. their costs are all in their start. ok, what happens when we pass day 1? wbs element’s schedule % complete would be 100%, but its activities are all less than 100%.

best wishes

]]>
by: mostafa //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12232 wed, 09 may 2012 11:41:17 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12232 i think scenario two is never possible
take a sample please for me

]]>
by: mostafa //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12231 wed, 09 may 2012 11:32:37 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12231 this formula always gives the correct answer

schedule % complete (act) = ([data date] – [baseline start] – holly day) / ([baseline finish] – [baseline start] – holly day=od)

]]>
by: mostafa //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12230 wed, 09 may 2012 11:24:38 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12230 hi
this formula is true only when that the project does not have holiday

schedule % complete(act) = ( [data date] – [baseline start] ) / ( [baseline finish] – [baseline start]

]]>
by: mstafa //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12229 wed, 09 may 2012 11:14:50 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12229 ?? ????
??? ?????
schedule % complete(act) = ( [data date] – [baseline start] ) / ( [baseline finish] – [baseline start] )
???? ????? ???? ??? ?? ?????? ?? ???? ????? ????? ???? ?????? ????

]]>
by: plannertuts //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12228 mon, 07 may 2012 19:13:10 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12228 thanks for your comments pramod!

]]>
by: pramod dwivedi //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-1/#comment-12227 sat, 05 may 2012 20:10:32 +0000 //www.deco-dalles.com/?post_type=article&p=1180#comment-12227 i am so much thank fully to you ,that you make it so simple to understand ,you are really great , thanks a lot

]]>