comments on: schedule % complete in oracle primavera – the missing guide (part 2) - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/ project controls training & courses tue, 09 apr 2024 14:39:41 +0000 hourly 1 by: ahmed //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-103475 sun, 13 aug 2023 11:57:40 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-103475 i can’t download the book
the url is not working

]]>
by: aman singh //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-95518 fri, 30 sep 2022 05:19:04 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-95518 sir,
schedule % completion is not showing not wbs level. how to fix this issue.

]]>
by: pushkar sonar //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-75632 sun, 01 sep 2019 12:26:40 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-75632 the activity a6 has a bac cost of 160 rs.
further,when you view it in activity usage profile – the cost are 80+80+80+160 which shall be equal to 400 rs.
so how is the activity usage profile cost for the same activity is different from bac cost ?

please reply.

regards
pushkar sonar

]]>
by: hichem guendouz //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-42152 mon, 26 dec 2016 14:05:52 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-42152 dear
for this books is free or !!!!!
regard

]]>
by: david cumming //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-40606 fri, 09 sep 2016 08:30:42 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-40606 would anyone with more of a construction background (possibly) be able to explain why the difference in calculation at an activity / wbs level?

]]>
by: sherif //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-38669 mon, 18 apr 2016 12:31:20 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-38669 gents

i have problem in my schedule , the project did not start and showing schedule % is 100 for all start milestones .. the data data is the same project start date and i checked the hours also . !!!!

]]>
by: pablo villanueva //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-31183 mon, 24 aug 2015 11:33:21 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-31183 it´s great your explanation . thank you .

]]>
by: furqan ali kirmani //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-25203 wed, 17 dec 2014 04:12:30 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-25203 sir,

this article of yours is a conceptual story !! really grateful that you shared this .
thank you

]]>
by: anthony //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-25076 sun, 23 nov 2014 21:05:48 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-25076 good and sound tutorial

]]>
by: tajamul //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-25054 wed, 19 nov 2014 04:34:24 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-25054 the article is very informative but there are some points which need the author’s clarification.
wbs-e-2 , activity a7 the schedule % is 66.67% while it showing the planned value 100% but for a4 its ok.

and also in my schedule i have loaded the units the schedule % for the activities are 100% (with no curve assigned) but the wbs is showing 0%.
i dont understand the logic for schedule %

please reply to these comments

]]>
by: sharvanan //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-23643 wed, 10 sep 2014 12:39:17 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-23643 friend

if we use uniform loaded for activities – then planned value and schedule percentage will be same right

kindly advise

]]>
by: michael lepage //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-14861 tue, 29 apr 2014 18:20:15 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-14861 in reply to jani.

if you want to show it graphically, use the resource usage profile (view -> show on bottom -> resource usage profile). right-click in the graph to configure the bars options.
m

]]>
by: jani //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-14834 tue, 29 apr 2014 13:11:12 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-14834 in reply to nader khorrami rad.

sir,

my baseline resource for an activity (say mason) is 200 hours ( 2 nos.x 10hr x 10 days).
but my actual is only 100 hours (1 no. x 10hrs x 10 days). how can i show this in primavera p6.
planned resource vs actual resource

thanks

]]>
by: waqas //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12307 thu, 12 sep 2013 17:51:02 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12307 great work brother !! highly helpful salute to you . brother kindly give me some other link to download this book because i am not able to download it from here.

]]>
by: jae lee //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12306 thu, 01 aug 2013 00:13:41 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12306 how can i say what you have accomplished in this articles…this is the greast single challenge never seen before in pm/cm area. i am certain that your reputation and contribution will be long remembered and will impact thousands of primavera admirers, leading you to great sucess in your profession.

]]>
by: nader khorrami rad //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12305 wed, 03 apr 2013 07:28:40 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12305 dear warren,
the ebook is free, and printable. you just need to download it.

]]>
by: warren //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12304 mon, 01 apr 2013 10:29:12 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12304 dear sir,

can you give us a printable copy of this e book including part 1? it will be of great help for us aspiring planners.

]]>
by: omer //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12303 wed, 06 feb 2013 09:43:58 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12303 thanx fellow for sharing your knowledge & experience, you really make it simple and clear.

br

]]>
by: moataz ahmed maher , pmp //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12302 sun, 07 oct 2012 13:54:21 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12302 thanks thanks thanks thanks …………
great job ………….
realy great …..
thank you brother,

]]>
by: arun r //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12301 mon, 20 aug 2012 19:27:32 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12301 loaded with some idea….now i have to work out and expand myself. i like that tricky portion of resource curve.

]]>
by: behzad //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12300 sun, 22 jul 2012 13:46:39 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12300 thanks, that was very helpful.

]]>
by: schedule % complete in primavera p6 | pmarchy //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12299 wed, 20 jun 2012 08:49:47 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12299 […] [schedule % complete in primavera p6, part 2] […]

]]>
by: behrang //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12298 tue, 22 may 2012 20:34:54 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12298 that’s great

]]>
by: plannertuts //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12297 mon, 07 may 2012 19:14:22 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12297 @golzaria, you were right. we’ve fixed that screenshot just for you! thanks!

]]>
by: golzarian //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12296 sun, 06 may 2012 08:24:00 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12296 thanks.that’s great.
in my opinion in the section “planned value….elaborated” a6 should highlighted instead of a5

your profile is really practical and useful for me.

]]>
by: s //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12295 sat, 05 may 2012 13:02:46 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12295 excellent brother,

can you teach online? if anyone required tution? or ask anything? may i have your email id?

]]>
by: kaushik ghosh //www.deco-dalles.com/primavera-p6-schedule-percent-complete-guide-2/#comment-12294 sat, 05 may 2012 09:11:03 +0000 //www.deco-dalles.com/?post_type=article&p=1229#comment-12294 great work done !!

]]>