comments on: do you make these project scheduling mistakes? - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/project-scheduling-mistakes/ project controls training & courses wed, 09 oct 2019 18:24:26 +0000 hourly 1 by: michael lepage //www.deco-dalles.com/project-scheduling-mistakes/#comment-46233 thu, 22 jun 2017 18:08:58 +0000 //www.deco-dalles.com/?post_type=article&p=1143#comment-46233 in reply to emma anene.

hi emma
i can’t help you in this. i advise you to look at the contract, the design doc, talk to the project experts and extract what you need to build your schedule. don’t be afraid to ask questions just because you’re not familiar with the area. assert your expertise in planning & scheduling, not in gas turbine projects.
good luck!
michael

]]>
by: emma anene //www.deco-dalles.com/project-scheduling-mistakes/#comment-46231 thu, 22 jun 2017 13:17:00 +0000 //www.deco-dalles.com/?post_type=article&p=1143#comment-46231 dear michael,

i have just been assigned as a planner for a new area that i have not worked on before, installation and commissioning of a gas turbine. please, can you help with with a typical wbs, that will aid me in preparing the project schedule.

thank you so much.

]]>
by: femi //www.deco-dalles.com/project-scheduling-mistakes/#comment-25032 sat, 15 nov 2014 12:28:29 +0000 //www.deco-dalles.com/?post_type=article&p=1143#comment-25032 the book is excellent. it is my companion now

]]>
by: m.nadeem //www.deco-dalles.com/project-scheduling-mistakes/#comment-11823 fri, 01 mar 2013 10:38:31 +0000 //www.deco-dalles.com/?post_type=article&p=1143#comment-11823 your comments
sir
i need to primaverap6 to sent me easy theory book

thnaks

]]>
by: michael lepage //www.deco-dalles.com/project-scheduling-mistakes/#comment-11822 tue, 30 oct 2012 20:12:52 +0000 //www.deco-dalles.com/?post_type=article&p=1143#comment-11822 farrukh,
as online learning options go, you might want to look at http://www.cpmsolutions.ca who have an online elearning course on primavera. otherwise, i might suggest you find a company that offers classroom courses in the mississauga area. until we here at plannertuts can offer some more comprehensive learning options, those are my recommendations.
best of luck,
michael

]]>
by: farrukh //www.deco-dalles.com/project-scheduling-mistakes/#comment-11821 sun, 28 oct 2012 00:40:06 +0000 //www.deco-dalles.com/?post_type=article&p=1143#comment-11821 dear micheal,

i am a chemical engineer worked mostly in plant operations, new to canada and want to learn the primavera 6. i am living in mississauga, ontario. i have seen few of your video tutorials and find them very interesting. can you please suggest me the best way to learn the primavera up-to a level helpful in getting a job?

regards,

]]>
by: plannertuts //www.deco-dalles.com/project-scheduling-mistakes/#comment-11820 mon, 13 aug 2012 22:05:20 +0000 //www.deco-dalles.com/?post_type=article&p=1143#comment-11820 in reply to fadzli.

hi fadzil,

i’ve updated the links in the post. you will be able to download the ebook now through the updated links.
thanks!
ptuts

]]>
by: fadzli //www.deco-dalles.com/project-scheduling-mistakes/#comment-11819 fri, 10 aug 2012 08:14:48 +0000 //www.deco-dalles.com/?post_type=article&p=1143#comment-11819 i would like to download the e-book but it seem the e-book is no longer available. it would be appreciate if someone can email it to me. here is my email address mofazus@yahoo.com

]]>
by: aftab khan //www.deco-dalles.com/project-scheduling-mistakes/#comment-11818 fri, 22 jun 2012 11:55:14 +0000 //www.deco-dalles.com/?post_type=article&p=1143#comment-11818 correction to “at completion labor units” formula on top->
1. “at completion labor units”-calculated based on “remaining duration” (in days) x units/day + actuals to date.

]]>
by: aftab khan //www.deco-dalles.com/project-scheduling-mistakes/#comment-11817 fri, 22 jun 2012 06:45:47 +0000 //www.deco-dalles.com/?post_type=article&p=1143#comment-11817 seems there are 2 sets of rules to calculate estimate at completion->
the first based on “forecast remaining duration” and the other based on “budget” and “actuals.

]]>
by: aftab khan //www.deco-dalles.com/project-scheduling-mistakes/#comment-11816 fri, 22 jun 2012 06:36:03 +0000 //www.deco-dalles.com/?post_type=article&p=1143#comment-11816 michael-

basic question->
why are the following 2 different and calculated differently?->
1. “at completion labor units”-calculated based on “remaining duration” (in days) x units/day.
compared to->
2. “estimate at completion labor units”-calculated as “budgeted units-earned units” + actual units to date.

]]>