comments on: how to remove actuals from a primavera p6 schedule - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/ project controls training & courses tue, 15 aug 2023 07:49:51 +0000 hourly 1 by: ahmed ramadan khalifa //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-103495 tue, 15 aug 2023 07:49:51 +0000 //www.deco-dalles.com/?p=33635#comment-103495 i’m using physical activities %

]]>
by: ahmed //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-103494 tue, 15 aug 2023 07:48:59 +0000 //www.deco-dalles.com/?p=33635#comment-103494 same problem for me

the completed activities and the actuals units never change

]]>
by: doug galt //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-84476 sun, 21 mar 2021 04:54:34 +0000 //www.deco-dalles.com/?p=33635#comment-84476 is there a way to remove the actuals from a master schedule but keep the budget total costs and / or budget total hours?

regards,

doug
dgalt09@gmail.com

]]>
by: leonardo gomes //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-76132 thu, 13 feb 2020 10:43:55 +0000 //www.deco-dalles.com/?p=33635#comment-76132 hello,

how unlink to columns budgeted nonlabor units and budgeted nonlabor cost?

]]>
by: ahubi //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-75942 tue, 17 dec 2019 23:07:57 +0000 //www.deco-dalles.com/?p=33635#comment-75942 hi jerome

that was really helpful for me. thanks for sharing

]]>
by: jerome odeh //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-75861 sun, 17 nov 2019 14:09:55 +0000 //www.deco-dalles.com/?p=33635#comment-75861 in reply to ola.

hi ola,

i can’t replicate your error. get in touch via linkedin and i’ll see how i can help you.

jerome

]]>
by: jerome odeh //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-75860 sun, 17 nov 2019 14:08:30 +0000 //www.deco-dalles.com/?p=33635#comment-75860 in reply to eral.

hi eral,

i can’t replicate your error. get in touch via linkedin and i’ll see how i can help you.

jerome

]]>
by: ola //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-75855 fri, 15 nov 2019 02:47:35 +0000 //www.deco-dalles.com/?p=33635#comment-75855 sir,

i followed above step on how to remove actual. i have a problem when i am in step #3, there is error that pop-up everytime i click changes.

“error(s) occurred while processing the global change. please review the report before committing the changes”

and when i click commit changes and view result some activities are changes to not started, but most of the activities still same (still completed).

please sir help me with regards to this issue and kindly let me know the reasons why this error pop-up.

thank you and good day.

]]>
by: eral //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-75663 sun, 15 sep 2019 02:39:09 +0000 //www.deco-dalles.com/?p=33635#comment-75663 sir,

i followed the steps but when i commit changes on step number 6, error were prompted :

” error(s) occurred while processing the global change. please review the report before committing the changes”

and when i click ok and click on commit changes, some activities that are completed not replaced by not started. however some items changes to not started. can anyone help me on how to resolve this issue. i am using p6 r8.3.

thank you and good day

]]>
by: zeeshan ali //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-60698 tue, 19 jun 2018 14:21:36 +0000 //www.deco-dalles.com/?p=33635#comment-60698 thanks for the explanation. i am unable to upload a screenshot here. just to let you know that, you could easily add in parameters for all type of 世界杯时间比赛时间 , excluding expenses, under just one global change, saving you time and hassle.

]]>
by: rizwan //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-57884 tue, 01 may 2018 15:07:21 +0000 //www.deco-dalles.com/?p=33635#comment-57884 in reply to ab.

export the progress in excel before removing the actual and then you can import it back after you removed actual and done with your changes

]]>
by: jerome odeh //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-47942 fri, 25 aug 2017 18:18:55 +0000 //www.deco-dalles.com/?p=33635#comment-47942 in reply to syed muzaffar.

syed,

make sure you have picked “activities” from the “select subject area” dropdown box as activity type is associated with activities and not activity resource assignment.

=jerome

]]>
by: syed muzaffar //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-47941 fri, 25 aug 2017 16:13:37 +0000 //www.deco-dalles.com/?p=33635#comment-47941 i followed the method you mentioned point by point, however, i was left with some activities still ‘actualised’, they all had activity type = ‘task dependent’. when i tried to create a new global change for activity type = ‘task dependant’ i couldn’t find ‘activity type’ in the list of parameters. please can you help in this regard. thanks,

]]>
by: andy //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-47439 fri, 11 aug 2017 14:18:05 +0000 //www.deco-dalles.com/?p=33635#comment-47439 very informative and easy to understand and implement

]]>
by: ramana //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-45941 wed, 07 jun 2017 12:33:08 +0000 //www.deco-dalles.com/?p=33635#comment-45941 thanks alot. it worked & saved lot of my time.

]]>
by: jerome ijachi odeh //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-42192 wed, 28 dec 2016 10:05:07 +0000 //www.deco-dalles.com/?p=33635#comment-42192 asif,

you still have some actual resource units or cost for construction activities. ensure that you have followed the steps outlined for removing resource or expense actuals.

kind regards,
=jerome

]]>
by: asif iqbal //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-42191 wed, 28 dec 2016 09:48:36 +0000 //www.deco-dalles.com/?p=33635#comment-42191 i did the same as explained & it worked for procurement & engineering activities. but the thing is that, it is not working for the construction activities. the same message “cannot set status to not started if activity has actuals”. is displayed.

can some help please…..

]]>
by: qasim //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-40848 sat, 01 oct 2016 07:11:05 +0000 //www.deco-dalles.com/?p=33635#comment-40848 thank you. it was useful.

]]>
by: mohammed iqbal ali khan //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-40843 fri, 30 sep 2016 20:34:22 +0000 //www.deco-dalles.com/?p=33635#comment-40843 dear sir,

i need to know, how to evaluate the progress % complete by using phyiscal perentage complete foe each wbs.

awaitng your respond.

br.

]]>
by: amar iadaden //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-40358 wed, 17 aug 2016 17:16:52 +0000 //www.deco-dalles.com/?p=33635#comment-40358 i would like to remove actual duration to change the activity status from completed to not started, but i havn’t in the second parameter (after “then”).please advise.

]]>
by: adam salam //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-39924 wed, 13 jul 2016 13:08:37 +0000 //www.deco-dalles.com/?p=33635#comment-39924 very high values in actual cost!!!

in primavera p6 after partial planning and trying to enter actual units for cost/time control i found that the resultant actual cost very high!!! where could be the problem?…

]]>
by: evan phillips //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-38840 thu, 05 may 2016 11:41:16 +0000 //www.deco-dalles.com/?p=33635#comment-38840 i’ve noticed that if you’ve stored period performance and then try to remove actuals they delta will show for that period. my work-around is to display all used period columns and zero fill-down the last period, store, then repeat for each previous period until i get to the start date. it’s tedious but i’d love to hear if anyone has a better idea.

]]>
by: jerome odeh //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-38547 sun, 03 apr 2016 20:45:33 +0000 //www.deco-dalles.com/?p=33635#comment-38547 in reply to padmanabhan.

following the steps outlined in the tutorial should return actual start & actual finish dates to the start & finish dates before progress update provided the logic relationships are still the same as they were at project start.

]]>
by: padmanabhan //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-38543 sun, 03 apr 2016 09:54:38 +0000 //www.deco-dalles.com/?p=33635#comment-38543 in reply to jerome.

how to change actual finish start and actual finish dates, back to orgininal

]]>
by: padmanabhan //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-38542 sun, 03 apr 2016 07:26:30 +0000 //www.deco-dalles.com/?p=33635#comment-38542 how to correct out of sequence activities in a fatser way. appreciate a feed back

]]>
by: bahij ashoor //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-38359 sun, 20 mar 2016 08:09:19 +0000 //www.deco-dalles.com/?p=33635#comment-38359 hi mr. jerome

every thing is ok but what about the logic being changed because of the out-of-sequence activities leads to change the relationships when the progress runs out of schedule

]]>
by: jerome //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-37836 fri, 12 feb 2016 08:28:27 +0000 //www.deco-dalles.com/?p=33635#comment-37836 in reply to sonali nair.

hi sonali,

suggest you take a copy of your schedule and try the steps below (i’ll also try these steps myself tonight & see if it works, i’ll do a blog post for it).

– ensure that the schedule is fully logic linked. i know some people don’t worry about logic links for completed activities, but to achieve what you are after, you need to ensure proper logic are in place and that includes resolving any out of sequence activities

– run a global change to make original duration = actual duration

– run a 2nd global change to change activity status to “not started”

– run a time analysis (f9) with data date set at project actual start (remember to set your definition of critical activities to longest path in scheduling options)

– run a filter for critical activities and fingers crossed, voila you should have your longest path

=jerome

hopefully,

]]>
by: sonali nair //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-37831 fri, 12 feb 2016 04:49:10 +0000 //www.deco-dalles.com/?p=33635#comment-37831 hi jerome,

your information is very helpful.
i am stuck up in a situation.i have to find the longest path taken by a project schedule which is already completed. all the dates are actual. can it be solved in some way by using global change by “removing actual dates”?

thnx
sonali nair

]]>
by: jerome //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-37814 thu, 11 feb 2016 14:37:30 +0000 //www.deco-dalles.com/?p=33635#comment-37814 in reply to jay bergstrom.

hi jay,

my understanding is that “equipment” is of material resource type and step 4 takes care of this resource type.

on budgeted units. you’ll notice that my global change only affects actual units, so your budgeted units should the same as you had it before assigning actuals based on your duration type definition.

step 6 unchecks the actual boxes for you, so you do not need to do it manually.

=jerome

reply

]]>
by: jerome //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-37813 thu, 11 feb 2016 14:37:00 +0000 //www.deco-dalles.com/?p=33635#comment-37813 in reply to ab.

hi ab,

unfortunately, i don’t know of a fast way of assigning progress. as mentioned in the blog post, this is the downside of removing actuals from a schedule.

maybe you should explore the use of sdk and see if it will help speed things up.

=jerome

]]>
by: jose recendiz //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-37812 thu, 11 feb 2016 11:49:32 +0000 //www.deco-dalles.com/?p=33635#comment-37812 ab you can progress all activities by the following,
reflect actual dates using the logic ( relationships), or with constrains
remember that every time you change logic you need to do f9 to recalculate but without changing data date
then once you are sure all dates are correct you can run the progress update to the desire new data date and p6 will progress all activities like if everything happened without deviations ( of course any deviation were already reflected on step one before the progress update)

]]>
by: clement ani //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-37809 thu, 11 feb 2016 07:54:55 +0000 //www.deco-dalles.com/?p=33635#comment-37809 thanks as i have tried doing this before in a different way and it messed my programme up.

]]>
by: jerome //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-37788 wed, 10 feb 2016 12:34:31 +0000 //www.deco-dalles.com/?p=33635#comment-37788 hi jay,

my understanding is that “equipment” is of material resource type and step 4 takes care of this resource type.

on budgeted units. you’ll notice that my global change only affects actual units, so your budgeted units should the same as you had it before assigning actuals based on your duration type definition.

step 6 unchecks the actual boxes for you, so you do not need to do it manually.

=jerome

]]>
by: jerome //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-37787 wed, 10 feb 2016 12:21:13 +0000 //www.deco-dalles.com/?p=33635#comment-37787 hi ab,

unfortunately, i don’t know of a fast way of assigning progress. as mentioned in the blog post, this is the downside of removing actuals from a schedule.

maybe you should explore the use of sdk and see if it will help speed things up.

=jerome

]]>
by: jay bergstrom //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-37786 wed, 10 feb 2016 12:15:46 +0000 //www.deco-dalles.com/?p=33635#comment-37786 jerome, i noticed that you didn’t include equipment in your global change report. were you assuming that equipment was in the expense field? also i have had bad experiences with the budgets not being restored properly by p6 as well as the units/time. this may be different in the latest version of p6 but i’ve always stayed away from reusing ant activity that has been actualized. you also don’t mention unchecking the actuals boxes. how is that accomplished?
thanks for the input. jay bergstrom

]]>
by: ab //www.deco-dalles.com/remove-actuals-primavera-p6-schedule-how/#comment-37785 wed, 10 feb 2016 11:56:48 +0000 //www.deco-dalles.com/?p=33635#comment-37785 dear jerome,

this info is helpful, thanks,

now, i removed all the progress did my changes and assigned baseline again.

now i have thousand of activities to progress, can you guide how to progress those activities faster? if i progress those manually it may take weeks.

regards,

ab

]]>