comments on: how to show the critical path in p6 - 瑞士vs喀麦隆足彩赔率 //www.deco-dalles.com/show-critical-path-in-p6/ project controls training & courses mon, 16 sep 2024 15:01:41 +0000 hourly 1 by: reshma sadhu //www.deco-dalles.com/show-critical-path-in-p6/#comment-81453 thu, 05 nov 2020 15:14:44 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-81453 in reply to navid.

hi navid,

the cpm scheduling 101: how primavera scheduling works blog post may help.

regards.

]]>
by: navid //www.deco-dalles.com/show-critical-path-in-p6/#comment-81282 fri, 30 oct 2020 12:42:32 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-81282 hi michael,

thank you for your knowledge sharing.

how p6 calculate early start & late start in order to calculate total float for each activity?
i think some of my activities have total float incorrectly and i don’t know why !
can you help me?

]]>
by: michael lepage //www.deco-dalles.com/show-critical-path-in-p6/#comment-77912 fri, 29 may 2020 15:32:10 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-77912 in reply to talha siddiqui.

if they are on the critical path, how do you know they are not critical and need to be removed? seems like maybe you have your own definition of critical path.
you don’t remove activities from your critical path. if you have incorrectly linked an activity, and it shows up on your critical path, then correct the links. but accept that all activities on your critical path, are critical.

]]>
by: talha siddiqui //www.deco-dalles.com/show-critical-path-in-p6/#comment-77845 tue, 26 may 2020 19:06:27 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-77845 hello michael lepage,

how to remove unnecessary activities in critical path, basically which are not critical activities ?

]]>
by: michael lepage //www.deco-dalles.com/show-critical-path-in-p6/#comment-75184 mon, 22 apr 2019 00:23:29 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-75184 in reply to mary.

mary, this sounds a bit complex to be able to grasp and reply in a comment form. feel free to reach out to our office.

]]>
by: mary //www.deco-dalles.com/show-critical-path-in-p6/#comment-75145 sat, 13 apr 2019 13:22:23 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-75145 hi michael,
i am preparing a schedule for a land development project. my client has the master schedule, and mine has design, tenders, and construction administration services for the specific sites.
in the client master plan, they planned to do some of tender& construction works related to our sites, in 2020 and the rest in 2021.
my schedule now is broken. between completing design phase and some tenders i have 1 year pause. as a result i a lot of float and there is not one critical path. also, wondering how can i get rid of a few constraints i had to put for external inputs.

what do you suggest?

]]>
by: engr. obieda omari //www.deco-dalles.com/show-critical-path-in-p6/#comment-54834 mon, 22 jan 2018 06:31:48 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-54834 excellent

go ahead

]]>
by: kannen aryan //www.deco-dalles.com/show-critical-path-in-p6/#comment-44285 tue, 18 apr 2017 09:09:26 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-44285 in reply to michael lepage.

go to group & sort

uncheck the dialogue box “hide if empty”

]]>
by: michael lepage //www.deco-dalles.com/show-critical-path-in-p6/#comment-43846 mon, 03 apr 2017 08:47:05 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-43846 in reply to rephinus.

assign 世界杯时间比赛时间 to all activities as normal – i assume you’re resource-loading your schedule. go into filters and turn on the critical filter so only your critical path shows. then goto view->show on bottom ->resource usage profile and configure the graph to show your s-curve (cummulative curves).

]]>
by: michael lepage //www.deco-dalles.com/show-critical-path-in-p6/#comment-43845 mon, 03 apr 2017 08:44:53 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-43845 in reply to sunny.

yes of course – 0 float means it’s a critical activity based on the p6 criticality filter. try this. press f9 (schedule) click options, select longest path as the option to define critical activities.

]]>
by: rephinus //www.deco-dalles.com/show-critical-path-in-p6/#comment-43807 sat, 01 apr 2017 12:05:09 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-43807 how can i filter resource assignment that are only assigned to activities on the critical path? i want to develop critical path s-curve

the only approach i can take to generate critical path s-curve is to assign 世界杯时间比赛时间 to all activities on the critical path and use resource assignment weight to generate critical path s-curve. is there any other way?

kind regards
rephinus

]]>
by: sunny //www.deco-dalles.com/show-critical-path-in-p6/#comment-43794 fri, 31 mar 2017 18:09:45 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-43794 hey michael,
every activity in my plan has got zero float and hence primavera is showing every activity as critical activity, do you have any solution for this.
p.s- i haven’t assigned 世界杯时间比赛时间 yet.

]]>
by: zyre mehdi //www.deco-dalles.com/show-critical-path-in-p6/#comment-40799 tue, 27 sep 2016 05:57:43 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-40799 there’s another possibility. if different calendars have been assigned to different activities, primavera might not consider some activities with zero float as critical. probably because the float is calculated in days while difference in calendar could be in hours (e.g. difference in workhours). it just happened to me.

]]>
by: osama abu zied //www.deco-dalles.com/show-critical-path-in-p6/#comment-40620 sat, 10 sep 2016 19:49:37 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-40620 i remove the project end date from the schedule and then use the filter
best regards

]]>
by: michael lepage //www.deco-dalles.com/show-critical-path-in-p6/#comment-34807 thu, 05 nov 2015 22:10:47 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-34807 in reply to john.

not sure – turn off any filters you have on.

]]>
by: john //www.deco-dalles.com/show-critical-path-in-p6/#comment-34730 mon, 02 nov 2015 00:33:23 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-34730 i added activities to the wbs but i cant view all the activities but some.it is only the wbs showing.please what can i do to view the activities

]]>
by: michael lepage //www.deco-dalles.com/show-critical-path-in-p6/#comment-33595 tue, 29 sep 2015 17:00:29 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-33595 in reply to jyothi.

jyothi, it’s pretty apparent that you will have to revisit all remaining work and re-plan it to build a recovery schedule. look at your critical path and see if it makes sense. work with contacts in the field to see if you can get the schedule to accurately reflect how the work will be produced. talk to supervisors about the using the schedule daily – get support from management. it’s going to be a tough job, one that likely very frustrating. but the schedule is important.

]]>
by: jyothi //www.deco-dalles.com/show-critical-path-in-p6/#comment-33587 tue, 29 sep 2015 10:04:41 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-33587 hi michael,

due to many dependent activities and other conditions at site. schedules are not followed by the team as per the base plan.
there are so many delays in schedule.
kindly advice how to recover the delay by means of recovery plan / recovery schedule.

jyothi

]]>
by: michael lepage //www.deco-dalles.com/show-critical-path-in-p6/#comment-31592 mon, 31 aug 2015 01:41:48 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-31592 in reply to rajaram redkar.

rajaram,
it’s probably because the mandatory constraint is forcing an activity to a date earlier than the network logic – thus breaking the network logic. the result is negative float on the mandatory activity causing it to be critical.
it’s a general consensus not to use mandatory constraints on any project. as they break the network logic, the integrity of your project’s logic is gone….and only with good logic can you have / track / manage your critical path. with broken logic, the critical path is uncertain.
the proper approach is to use non-mandatory or soft constraints and to monitor their effect on total float.
hope that helps.

]]>
by: rajaram redkar //www.deco-dalles.com/show-critical-path-in-p6/#comment-31561 sun, 30 aug 2015 06:13:58 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-31561 is there any problem with this kind of critical path??

]]>
by: rajaram redkar //www.deco-dalles.com/show-critical-path-in-p6/#comment-31560 sun, 30 aug 2015 06:13:00 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-31560 those activities which has constrains as mandatory start showing as critical activity,why?

]]>
by: michael lepage //www.deco-dalles.com/show-critical-path-in-p6/#comment-31261 wed, 26 aug 2015 02:12:14 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-31261 in reply to alex.

thanks alex! we aim to be uber helpful!
michael

]]>
by: alex //www.deco-dalles.com/show-critical-path-in-p6/#comment-31245 tue, 25 aug 2015 20:57:38 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-31245 thank you mike, your lessons as usual are right to the point and are always unique and cannot be find anywhere else for free.

]]>
by: b //www.deco-dalles.com/show-critical-path-in-p6/#comment-25399 fri, 30 jan 2015 18:42:13 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-25399 thanks, this super clear directions.

]]>
by: marios k //www.deco-dalles.com/show-critical-path-in-p6/#comment-24988 mon, 10 nov 2014 23:03:32 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-24988 in reply to plannertuts.

thank you very much for your reply. i wasn’t sure about the duration while filtering the project by critical path.

]]>
by: plannertuts //www.deco-dalles.com/show-critical-path-in-p6/#comment-24985 mon, 10 nov 2014 15:39:52 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-24985 in reply to marios k.

hi marios,
put on the critical filter, and make sure you have grouping set to wbs. the duration at the very top is the duration of the critical path. to see the variance, you could create a baseline of your project before leveling. assign the baseline to the project. then, add a column to your view – “variance – bl project duration”. this will be the variance after leveling.
m

]]>
by: marios k //www.deco-dalles.com/show-critical-path-in-p6/#comment-24984 mon, 10 nov 2014 14:39:52 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-24984 dear mike,

your lesson about critical path is really useful. but i have just one question. can the primavera programm calculate the duration of critical path or i have to do that manually. i cant find any command at p6. my definite target is to calculate the variance of critical path duration between the cp duration before and after levellling.

thanks in advance

]]>
by: mustafa //www.deco-dalles.com/show-critical-path-in-p6/#comment-24947 wed, 05 nov 2014 11:27:55 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-24947 please can i have any plan in primavera contact me by s6eefalqwasmah@gmail.com please i have a homework (any subject by primavera)

]]>
by: temico //www.deco-dalles.com/show-critical-path-in-p6/#comment-11975 tue, 25 feb 2014 17:20:08 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-11975 tnx michael it was good

]]>
by: michael lepage //www.deco-dalles.com/show-critical-path-in-p6/#comment-11974 wed, 08 jan 2014 17:29:23 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-11974 @jose, yes and no. the screenshot in 2. shows which activities are critical by the total float method (critical column) and which activities are critical by the longest path method (longest path column).

over here https://www.plannertuts.com/article/critical-path-vs-longest-path/ i explain that the longest path is a critical path, but not all critical paths are the longest.

what is happening is that there are 2 ways to define what’s critical. yes, some activities on the longest path may not be considered critical by total float. thus, i recommend being aware that this is the case and being aware of the longest path.
m

]]>
by: jose abraham //www.deco-dalles.com/show-critical-path-in-p6/#comment-11973 wed, 08 jan 2014 07:06:22 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-11973 dear mike,

in the figure attached with item 2, we find the items marked as in the longest path, are not critical. is it possible for activities in the longest path not to be critical?

]]>
by: jorge campos //www.deco-dalles.com/show-critical-path-in-p6/#comment-11972 wed, 18 dec 2013 18:20:48 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-11972 jody, good point to ensure we may have a must finish by date set on your project or that the project is finishing earlier than the must finish by deadline

]]>
by: mani //www.deco-dalles.com/show-critical-path-in-p6/#comment-11971 wed, 11 dec 2013 19:13:58 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-11971 sir

using mutiple folat path can you say me how to show number of longest paths in the schedule that affect project completion date .

]]>
by: michael lepage //www.deco-dalles.com/show-critical-path-in-p6/#comment-11970 wed, 11 dec 2013 14:23:20 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-11970 @matt,
strange – are there any lags in your loe relationships by chance? i did some testing and i did find that my loes were on the longest path (not completely sure why). are the tasks that your loe is summarizing not on the longest path?

]]>
by: sf yip //www.deco-dalles.com/show-critical-path-in-p6/#comment-11969 wed, 11 dec 2013 03:33:58 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-11969 thanks, michael. i learned something new.

]]>
by: david cumming //www.deco-dalles.com/show-critical-path-in-p6/#comment-11968 tue, 10 dec 2013 21:22:19 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-11968 good, snappy points.
on point two there may be a constrained milestone as the project finish a little (or not) after the latest finishing activity

]]>
by: mostafa //www.deco-dalles.com/show-critical-path-in-p6/#comment-11967 tue, 10 dec 2013 18:58:58 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-11967 good lesson
thanks

]]>
by: rod ward //www.deco-dalles.com/show-critical-path-in-p6/#comment-11966 tue, 10 dec 2013 16:11:38 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-11966 i have used level of effort with p6 eppm 8.2 many times. it gives the loe activities a duration dependant on other activities and removes te loe activities from the critical path. however, they can be on the longest path. this makes sense to me, but i wouldn’t mind it if the loe activities stayed off the longest path.

]]>
by: matt kay //www.deco-dalles.com/show-critical-path-in-p6/#comment-11965 tue, 10 dec 2013 14:30:35 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-11965 i’ve just tested the review of the longest path in p6 r7, and it would appear that the use of level of effort tasks completely renders the longest path calculations useless. loe tasks and the final milestones are the only tasks which appear. pity for those of us who use loe tasks.

]]>
by: michael lepage //www.deco-dalles.com/show-critical-path-in-p6/#comment-11964 tue, 10 dec 2013 13:55:58 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-11964 thanks marcus!

]]>
by: marcus //www.deco-dalles.com/show-critical-path-in-p6/#comment-11963 tue, 10 dec 2013 11:16:04 +0000 //www.deco-dalles.com/?post_type=article&p=2085#comment-11963 excellent lesson.

]]>