in layman’s terms, free float tells you if an activity is “bumped up” to its successor activity (ff=0) or if there is a delay between the activity and its successor (ff>0). use free float to help you understand if you have flexibility to delay / extend an activity without delaying its successor. you can bump right up to it. this is valuable in manual resource leveling where you may have to delay work if your 世界杯时间比赛时间 are already busy at that time. you can check free float to see how far you can delay the work.
michael is an avid project controls blogger and is the chief learning officer here at 世界杯2022亚洲比赛时间 . michael has taught 1000s professionals how to use project controls software like primavera p6 over the past 10 years through his online courses and tutorials. michael is a member of aace, the guild of project controls and holds his pmp certification from pmi.