{"id":33635,"date":"2016-02-09t12:55:51","date_gmt":"2016-02-09t17:55:51","guid":{"rendered":"\/\/www.deco-dalles.com\/?p=33635"},"modified":"2019-10-18t11:03:03","modified_gmt":"2019-10-18t15:03:03","slug":"remove-actuals-primavera-p6-schedule-how","status":"publish","type":"post","link":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/","title":{"rendered":"how to remove actuals from a primavera p6 schedule"},"content":{"rendered":"

though not a widely recommended practice, there are times when one might want to de-progress or remove actuals from a primavera p6 schedule. some reasons for wanting to return a schedule after weeks or months of progress updates to its state at project start are:<\/p>\n

    \n
  1. baseline not being set before applying actuals<\/a><\/li>\n
  2. wrong or no resource assignments applied when baseline was set<\/li>\n
  3. wrong logic relationships in schedule when baseline was set?<\/li>\n<\/ol>\n

    a downside to removing actuals from\u00a0a schedule is that the \u201cnew\u201d schedule will need to be progressed again to the last reporting date. this means all periodic updates carried out on the last schedule have to be repeated with same data as before.<\/p>\n

    here’s how to remove actuals from a p6 schedule<\/h2>\n

    this quick tip will show how to remove actuals from a primavera p6\u00a0schedule, returning the project to its planned values at project start in 7\u00a0steps<\/strong>. it shouldn’t matter what version of p6<\/a> you have. we\u00a0assume prior knowledge of how to use p6’s\u00a0global change<\/a><\/strong> facility. assuming we have the schedule in figure below from which we want to remove all traces of actuals with the following additional columns visible in the layout aside the usual suspects: performance % complete<\/a>, original duration, actual duration, remaining duration, actual labor units, actual nonlabor units & actual total cost.<\/strong><\/p>\n

    \"remove<\/p>\n

    all the columns listed above will be used to confirm at the end of the tutorial if we have returned our schedule to its original state at project start.<\/p>\n

    <\/h3>\n
    \n

    step 1 – project calculation tab setting<\/h3>\n

    in the projects<\/strong> view, select the open project and click on the calculations tab.<\/p>\n

    \"project<\/p>\n

    in the calculation tab, ensure that the link budget and at completion for not started activities<\/strong> checkbox is ticked and then select the reset remaining duration and units to original<\/strong> option button.<\/p>\n

    this step is required so that when we change the status of all our activities to not started<\/strong>, the remaining duration<\/strong> for our activities will be changed to same values as original duration<\/strong>.<\/p>\n

    in the next 2 steps, we need to change all actual labor units & actual nonlabor units<\/strong> to 0<\/strong>. one way of doing this is to use the fill down<\/strong> facility, but imagine if you have a schedule of thousands of activities, then the use of fill down<\/a> will be tedious. my preferred method is the use of global change<\/strong> as this enables one to save and reuse the global change in other schedules if required.<\/p>\n


    \n

    step 2 \u2013 global change actual labor units & cost<\/h3>\n

    run the global change<\/strong> shown in the figure below to change all actual labor units & actual labor cost<\/strong> to 0<\/strong>.<\/p>\n

    \"global<\/p>\n


    \n

    step 3 \u2013 global change actual nonlabor units & cost<\/h3>\n

    run the global change<\/strong> shown in the figure below to change all actual nonlabor units & actual nonlabor cost<\/strong> to 0<\/strong>.<\/p>\n

    \"global<\/p>\n


    \n

    step 4 \u2013 global change actual material units<\/h3>\n

    run the global change<\/strong> shown in the figure below to change all actual material units<\/strong> to 0<\/strong>.<\/p>\n

    \"global<\/p>\n


    \n

    step 5 \u2013 global change expense cost % complete<\/h3>\n

    run the global change<\/strong> shown in the figure below to change all actual expense cost<\/strong> to 0<\/strong> by changing expense cost % complete<\/strong> to 0<\/strong>.<\/p>\n

    \"global<\/p>\n


    \n

    step 6 \u2013 global change activity status<\/h3>\n

    run the global change<\/strong> shown in the figure below to change activity status<\/strong> for all activities to not started<\/strong>.<\/p>\n

    \"global<\/p>\n


    \n

    step 7 \u2013 schedule as at planned start<\/h3>\n

    run time analysis (f9)<\/strong> as at project start by setting the data date<\/strong> to project planned start<\/strong>. you can get the project planned start from the dates<\/strong> tab of the projects<\/strong> view.<\/p>\n

    \"schedule<\/p>\n


    \n

    result<\/h3>\n

    our schedule should now have the following for all activities as shown in figure below:<\/p>\n

      \n
    1. performance % complete = 0<\/li>\n
    2. original duration = remaining duration<\/li>\n
    3. actual labor units = 0<\/li>\n
    4. actual non-labor units =0<\/li>\n
    5. actual total cost= 0<\/li>\n<\/ol>\n

      \"remove<\/p>\n

      the schedule has no actuals and is now ready to readdress the reason for removing all actuals. use these steps and save the global change scripts so you can have the ability to remove actuals at your fingertips.<\/p>\n

      your turn<\/h2>\n

      have you ever had to remove actuals\u00a0from a schedule? why? what approach did you take?<\/p>\n","protected":false},"excerpt":{"rendered":"

      though not a widely recommended practice, there are times when one might want to de-progress or remove actuals from a…<\/p>\n","protected":false},"author":279,"featured_media":33696,"comment_status":"open","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"content-type":"","_kad_post_transparent":"","_kad_post_title":"","_kad_post_layout":"","_kad_post_sidebar_id":"","_kad_post_content_style":"","_kad_post_vertical_padding":"","_kad_post_feature":"","_kad_post_feature_position":"","_kad_post_header":false,"_kad_post_footer":false,"footnotes":""},"categories":[55],"tags":[],"content-topics":[],"class_list":["post-33635","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-primavera-p6-tutorials"],"acf":[],"yoast_head":"\nhow to remove actuals from a primavera p6 schedule<\/title>\n<meta name=\"description\" content=\"learn how to remove actuals from a primavera p6 schedule or deprogress a schedule, returning to your original schedule after weeks of progress updates.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/\" \/>\n<meta property=\"og:locale\" content=\"en_us\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"how to remove actuals from a primavera p6 schedule\" \/>\n<meta property=\"og:description\" content=\"learn how to remove actuals from a primavera p6 schedule or deprogress a schedule, returning to your original schedule after weeks of progress updates.\" \/>\n<meta property=\"og:url\" content=\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/\" \/>\n<meta property=\"og:site_name\" content=\"世界杯2022亚洲比赛时间 \" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/planacademy\" \/>\n<meta property=\"article:published_time\" content=\"2016-02-09t17:55:51+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2019-10-18t15:03:03+00:00\" \/>\n<meta property=\"og:image\" content=\"\/\/www.deco-dalles.com\/wp-content\/uploads\/2016\/02\/p6-pro-laptop-desk-with-ipad-e1455040438304.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"330\" \/>\n\t<meta property=\"og:image:height\" content=\"220\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"jerome ijachi odeh\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:creator\" content=\"@planacademy\" \/>\n<meta name=\"twitter:site\" content=\"@planacademy\" \/>\n<meta name=\"twitter:label1\" content=\"written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"jerome ijachi odeh\" \/>\n\t<meta name=\"twitter:label2\" content=\"est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"3 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"article\",\"@id\":\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#article\",\"ispartof\":{\"@id\":\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/\"},\"author\":{\"name\":\"jerome ijachi odeh\",\"@id\":\"\/\/www.deco-dalles.com\/#\/schema\/person\/0dddcb0b5c1e5202385f0623124898cc\"},\"headline\":\"how to remove actuals from a primavera p6 schedule\",\"datepublished\":\"2016-02-09t17:55:51+00:00\",\"datemodified\":\"2019-10-18t15:03:03+00:00\",\"mainentityofpage\":{\"@id\":\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/\"},\"wordcount\":675,\"commentcount\":36,\"publisher\":{\"@id\":\"\/\/www.deco-dalles.com\/#organization\"},\"image\":{\"@id\":\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#primaryimage\"},\"thumbnailurl\":\"\/\/www.deco-dalles.com\/wp-content\/uploads\/2016\/02\/p6-pro-laptop-desk-with-ipad-e1455040438304.jpg\",\"articlesection\":[\"primavera p6 tutorials\"],\"inlanguage\":\"en-ca\",\"potentialaction\":[{\"@type\":\"commentaction\",\"name\":\"comment\",\"target\":[\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#respond\"]}]},{\"@type\":\"webpage\",\"@id\":\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/\",\"url\":\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/\",\"name\":\"how to remove actuals from a primavera p6 schedule\",\"ispartof\":{\"@id\":\"\/\/www.deco-dalles.com\/#website\"},\"primaryimageofpage\":{\"@id\":\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#primaryimage\"},\"image\":{\"@id\":\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#primaryimage\"},\"thumbnailurl\":\"\/\/www.deco-dalles.com\/wp-content\/uploads\/2016\/02\/p6-pro-laptop-desk-with-ipad-e1455040438304.jpg\",\"datepublished\":\"2016-02-09t17:55:51+00:00\",\"datemodified\":\"2019-10-18t15:03:03+00:00\",\"description\":\"learn how to remove actuals from a primavera p6 schedule or deprogress a schedule, returning to your original schedule after weeks of progress updates.\",\"breadcrumb\":{\"@id\":\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#breadcrumb\"},\"inlanguage\":\"en-ca\",\"potentialaction\":[{\"@type\":\"readaction\",\"target\":[\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/\"]}]},{\"@type\":\"imageobject\",\"inlanguage\":\"en-ca\",\"@id\":\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#primaryimage\",\"url\":\"\/\/www.deco-dalles.com\/wp-content\/uploads\/2016\/02\/p6-pro-laptop-desk-with-ipad-e1455040438304.jpg\",\"contenturl\":\"\/\/www.deco-dalles.com\/wp-content\/uploads\/2016\/02\/p6-pro-laptop-desk-with-ipad-e1455040438304.jpg\",\"width\":330,\"height\":220,\"caption\":\"quick tip: how to remove actuals from a p6 schedule\"},{\"@type\":\"breadcrumblist\",\"@id\":\"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#breadcrumb\",\"itemlistelement\":[{\"@type\":\"listitem\",\"position\":1,\"name\":\"blog\",\"item\":\"\/\/www.deco-dalles.com\/\"},{\"@type\":\"listitem\",\"position\":2,\"name\":\"how to remove actuals from a primavera p6 schedule\"}]},{\"@type\":\"website\",\"@id\":\"\/\/www.deco-dalles.com\/#website\",\"url\":\"\/\/www.deco-dalles.com\/\",\"name\":\"世界杯2022亚洲比赛时间 \",\"description\":\"project controls training & courses\",\"publisher\":{\"@id\":\"\/\/www.deco-dalles.com\/#organization\"},\"potentialaction\":[{\"@type\":\"searchaction\",\"target\":{\"@type\":\"entrypoint\",\"urltemplate\":\"\/\/www.deco-dalles.com\/?s={search_term_string}\"},\"query-input\":\"required name=search_term_string\"}],\"inlanguage\":\"en-ca\"},{\"@type\":\"organization\",\"@id\":\"\/\/www.deco-dalles.com\/#organization\",\"name\":\"世界杯2022亚洲比赛时间 \",\"url\":\"\/\/www.deco-dalles.com\/\",\"logo\":{\"@type\":\"imageobject\",\"inlanguage\":\"en-ca\",\"@id\":\"\/\/www.deco-dalles.com\/#\/schema\/logo\/image\/\",\"url\":\"\/\/www.deco-dalles.com\/wp-content\/uploads\/2023\/11\/cropped-pa-logo-color.png\",\"contenturl\":\"\/\/www.deco-dalles.com\/wp-content\/uploads\/2023\/11\/cropped-pa-logo-color.png\",\"width\":500,\"height\":159,\"caption\":\"世界杯2022亚洲比赛时间 \"},\"image\":{\"@id\":\"\/\/www.deco-dalles.com\/#\/schema\/logo\/image\/\"},\"sameas\":[\"https:\/\/www.facebook.com\/planacademy\",\"https:\/\/x.com\/planacademy\",\"https:\/\/www.linkedin.com\/company\/plan-academy\",\"https:\/\/www.youtube.com\/planacademy\"]},{\"@type\":\"person\",\"@id\":\"\/\/www.deco-dalles.com\/#\/schema\/person\/0dddcb0b5c1e5202385f0623124898cc\",\"name\":\"jerome ijachi odeh\",\"image\":{\"@type\":\"imageobject\",\"inlanguage\":\"en-ca\",\"@id\":\"\/\/www.deco-dalles.com\/#\/schema\/person\/image\/\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/68da50cb6131c52d547219edf6469902?s=96&d=mm&r=pg\",\"contenturl\":\"https:\/\/secure.gravatar.com\/avatar\/68da50cb6131c52d547219edf6469902?s=96&d=mm&r=pg\",\"caption\":\"jerome ijachi odeh\"},\"description\":\"jerome ijachi odeh is a pmi certified scheduling professional who has been working in the subsea sector of the oil & gas industry since 2003. jerome also writes on his personal blog which you can find here.\",\"sameas\":[\"http:\/\/uk.linkedin.com\/pub\/jerome-ijachi-odeh\/31\/a99\/739\"],\"url\":\"\/\/www.deco-dalles.com\/author\/jodeh\/\"}]}<\/script>\n<!-- \/ yoast seo premium plugin. -->","yoast_head_json":{"title":"how to remove actuals from a primavera p6 schedule","description":"learn how to remove actuals from a primavera p6 schedule or deprogress a schedule, returning to your original schedule after weeks of progress updates.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/","og_locale":"en_us","og_type":"article","og_title":"how to remove actuals from a primavera p6 schedule","og_description":"learn how to remove actuals from a primavera p6 schedule or deprogress a schedule, returning to your original schedule after weeks of progress updates.","og_url":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/","og_site_name":"世界杯2022亚洲比赛时间 ","article_publisher":"https:\/\/www.facebook.com\/planacademy","article_published_time":"2016-02-09t17:55:51+00:00","article_modified_time":"2019-10-18t15:03:03+00:00","og_image":[{"width":330,"height":220,"url":"\/\/www.deco-dalles.com\/wp-content\/uploads\/2016\/02\/p6-pro-laptop-desk-with-ipad-e1455040438304.jpg","type":"image\/jpeg"}],"author":"jerome ijachi odeh","twitter_card":"summary_large_image","twitter_creator":"@planacademy","twitter_site":"@planacademy","twitter_misc":{"written by":"jerome ijachi odeh","est. reading time":"3 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"article","@id":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#article","ispartof":{"@id":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/"},"author":{"name":"jerome ijachi odeh","@id":"\/\/www.deco-dalles.com\/#\/schema\/person\/0dddcb0b5c1e5202385f0623124898cc"},"headline":"how to remove actuals from a primavera p6 schedule","datepublished":"2016-02-09t17:55:51+00:00","datemodified":"2019-10-18t15:03:03+00:00","mainentityofpage":{"@id":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/"},"wordcount":675,"commentcount":36,"publisher":{"@id":"\/\/www.deco-dalles.com\/#organization"},"image":{"@id":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#primaryimage"},"thumbnailurl":"\/\/www.deco-dalles.com\/wp-content\/uploads\/2016\/02\/p6-pro-laptop-desk-with-ipad-e1455040438304.jpg","articlesection":["primavera p6 tutorials"],"inlanguage":"en-ca","potentialaction":[{"@type":"commentaction","name":"comment","target":["\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#respond"]}]},{"@type":"webpage","@id":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/","url":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/","name":"how to remove actuals from a primavera p6 schedule","ispartof":{"@id":"\/\/www.deco-dalles.com\/#website"},"primaryimageofpage":{"@id":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#primaryimage"},"image":{"@id":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#primaryimage"},"thumbnailurl":"\/\/www.deco-dalles.com\/wp-content\/uploads\/2016\/02\/p6-pro-laptop-desk-with-ipad-e1455040438304.jpg","datepublished":"2016-02-09t17:55:51+00:00","datemodified":"2019-10-18t15:03:03+00:00","description":"learn how to remove actuals from a primavera p6 schedule or deprogress a schedule, returning to your original schedule after weeks of progress updates.","breadcrumb":{"@id":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#breadcrumb"},"inlanguage":"en-ca","potentialaction":[{"@type":"readaction","target":["\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/"]}]},{"@type":"imageobject","inlanguage":"en-ca","@id":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#primaryimage","url":"\/\/www.deco-dalles.com\/wp-content\/uploads\/2016\/02\/p6-pro-laptop-desk-with-ipad-e1455040438304.jpg","contenturl":"\/\/www.deco-dalles.com\/wp-content\/uploads\/2016\/02\/p6-pro-laptop-desk-with-ipad-e1455040438304.jpg","width":330,"height":220,"caption":"quick tip: how to remove actuals from a p6 schedule"},{"@type":"breadcrumblist","@id":"\/\/www.deco-dalles.com\/remove-actuals-primavera-p6-schedule-how\/#breadcrumb","itemlistelement":[{"@type":"listitem","position":1,"name":"blog","item":"\/\/www.deco-dalles.com\/"},{"@type":"listitem","position":2,"name":"how to remove actuals from a primavera p6 schedule"}]},{"@type":"website","@id":"\/\/www.deco-dalles.com\/#website","url":"\/\/www.deco-dalles.com\/","name":"世界杯2022亚洲比赛时间 ","description":"project controls training & courses","publisher":{"@id":"\/\/www.deco-dalles.com\/#organization"},"potentialaction":[{"@type":"searchaction","target":{"@type":"entrypoint","urltemplate":"\/\/www.deco-dalles.com\/?s={search_term_string}"},"query-input":"required name=search_term_string"}],"inlanguage":"en-ca"},{"@type":"organization","@id":"\/\/www.deco-dalles.com\/#organization","name":"世界杯2022亚洲比赛时间 ","url":"\/\/www.deco-dalles.com\/","logo":{"@type":"imageobject","inlanguage":"en-ca","@id":"\/\/www.deco-dalles.com\/#\/schema\/logo\/image\/","url":"\/\/www.deco-dalles.com\/wp-content\/uploads\/2023\/11\/cropped-pa-logo-color.png","contenturl":"\/\/www.deco-dalles.com\/wp-content\/uploads\/2023\/11\/cropped-pa-logo-color.png","width":500,"height":159,"caption":"世界杯2022亚洲比赛时间 "},"image":{"@id":"\/\/www.deco-dalles.com\/#\/schema\/logo\/image\/"},"sameas":["https:\/\/www.facebook.com\/planacademy","https:\/\/x.com\/planacademy","https:\/\/www.linkedin.com\/company\/plan-academy","https:\/\/www.youtube.com\/planacademy"]},{"@type":"person","@id":"\/\/www.deco-dalles.com\/#\/schema\/person\/0dddcb0b5c1e5202385f0623124898cc","name":"jerome ijachi odeh","image":{"@type":"imageobject","inlanguage":"en-ca","@id":"\/\/www.deco-dalles.com\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/68da50cb6131c52d547219edf6469902?s=96&d=mm&r=pg","contenturl":"https:\/\/secure.gravatar.com\/avatar\/68da50cb6131c52d547219edf6469902?s=96&d=mm&r=pg","caption":"jerome ijachi odeh"},"description":"jerome ijachi odeh is a pmi certified scheduling professional who has been working in the subsea sector of the oil & gas industry since 2003. jerome also writes on his personal blog which you can find here.","sameas":["http:\/\/uk.linkedin.com\/pub\/jerome-ijachi-odeh\/31\/a99\/739"],"url":"\/\/www.deco-dalles.com\/author\/jodeh\/"}]}},"_links":{"self":[{"href":"\/\/www.deco-dalles.com\/wp-json\/wp\/v2\/posts\/33635"}],"collection":[{"href":"\/\/www.deco-dalles.com\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"\/\/www.deco-dalles.com\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"\/\/www.deco-dalles.com\/wp-json\/wp\/v2\/users\/279"}],"replies":[{"embeddable":true,"href":"\/\/www.deco-dalles.com\/wp-json\/wp\/v2\/comments?post=33635"}],"version-history":[{"count":0,"href":"\/\/www.deco-dalles.com\/wp-json\/wp\/v2\/posts\/33635\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"\/\/www.deco-dalles.com\/wp-json\/wp\/v2\/media\/33696"}],"wp:attachment":[{"href":"\/\/www.deco-dalles.com\/wp-json\/wp\/v2\/media?parent=33635"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"\/\/www.deco-dalles.com\/wp-json\/wp\/v2\/categories?post=33635"},{"taxonomy":"post_tag","embeddable":true,"href":"\/\/www.deco-dalles.com\/wp-json\/wp\/v2\/tags?post=33635"},{"taxonomy":"content-topics","embeddable":true,"href":"\/\/www.deco-dalles.com\/wp-json\/wp\/v2\/content-topics?post=33635"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}