{"id":54459,"date":"2022-05-19t13:00:17","date_gmt":"2022-05-19t17:00:17","guid":{"rendered":"\/\/www.deco-dalles.com\/?p=54459"},"modified":"2024-04-03t11:38:09","modified_gmt":"2024-04-03t15:38:09","slug":"update-baseline-feature-in-primavera-p6-use-or-not","status":"publish","type":"post","link":"\/\/www.deco-dalles.com\/update-baseline-feature-in-primavera-p6-use-or-not\/","title":{"rendered":"update baseline feature in primavera p6 use or not"},"content":{"rendered":"

in today\u2019s post, i want to talk about the primavera p6<\/a> update baseline feature. are you using it right? should you be using it at all? i want to dive into that and talk about project change management while we talk about the p6 update baseline feature.\u00a0<\/span><\/p>\n

what is the problem with update baseline?<\/span><\/h2>\n

okay. so number one update baseline; if you’ve done any digging, you know it’s fraught with errors and bugs.<\/span><\/p>\n

it has all sorts of problems trying to get update baseline to properly copy activities between the current schedule and the baseline schedule. but i’m not here to talk about that; i’m here to talk about whether you should be using it at all!<\/span><\/p>\n

in fact, i think a lot of people are trying to use update baseline when they shouldn’t be using it at all.<\/span><\/p>\n

let me talk about schedule change management for a minute. in the video below i walk you through it visually. let’s see where the progress<\/a> in our schedule; we took the time to make a great baseline schedule – at the onset, we called it b1. and now as we go through, we’re doing our update schedule so we’re always comparing it to b1.<\/span><\/p>\n